A stakeholder bypasses you and gives direct instructions to a team member to add a new report. The team member has already started working on it. What should the project manager do first?

⚠ Common exam trap

Many exam-takers choose to escalate immediately (Option C) or ignore the issue (Option A), failing to recognize that the PMI expects the project manager to first attempt direct resolution with the stakeholder using the established change control process, not bypassing it or escalating prematurely.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Meet with the stakeholder to reinforce the change control process and request that all changes go through you

The correct first step is to meet with the stakeholder to reinforce the change control process and request that all changes go through you. This directly addresses the bypass while maintaining professional communication, and it aligns with the PMI's emphasis on managing stakeholder expectations and following the integrated change control process. The project manager must protect the team from unauthorized work and ensure any change is formally evaluated for impact on scope, schedule, and budget.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ignore it to avoid conflict, but document the incident

    Why it's wrong here

    Ignoring a direct breach of project governance, even while documenting it, is a passive approach that fails to uphold established processes and control. This inaction allows the unauthorized behavior to persist, potentially setting a precedent that undermines the project manager's authority and the integrity of the change control system. Effective project management requires proactive engagement to enforce agreed-upon procedures and maintain project order.

  • Meet with the stakeholder to reinforce the change control process and request that all changes go through you

    Why this is correct

    The most appropriate first step is to directly engage the stakeholder to reinforce the established change control process. This proactive communication clarifies expectations, educates the stakeholder on the correct protocol for submitting changes, and re-establishes the project manager's role as the central point of contact for all project modifications. This approach aligns with PMI principles by addressing issues at the lowest possible level and maintaining project governance through direct stakeholder engagement.

  • Escalate to the sponsor that the stakeholder is interfering

    Why it's wrong here

    Immediately escalating to the sponsor is premature and can damage stakeholder relationships by bypassing direct problem-solving. PMP best practices advocate for attempting to resolve conflicts and process deviations directly with the involved parties first, demonstrating leadership and problem-solving skills. Escalation should be reserved for situations where direct communication has failed to resolve the issue or when the impact is significant enough to warrant higher-level intervention.

  • Ask the team member to ignore the stakeholder's request and stop working

    Why it's wrong here

    Instructing the team member to ignore the stakeholder's request places the team member in an awkward and potentially conflicting position, undermining their ability to perform effectively. This action fails to address the root cause of the issue, which is the stakeholder bypassing the established process, and does not resolve the underlying communication breakdown. The project manager's responsibility is to manage stakeholder interactions and enforce processes, not to delegate conflict resolution to team members or create confusion regarding directives.

Go deeper

Related to this question

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.