PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Exhibit
Refer to the exhibit.
```
Task A: 5 days
Task B: 3 days (depends on A)
Task C: 4 days (depends on A)
Task D: 2 days (depends on B and C)
```
Refer to the exhibit. What is the critical path duration?
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
11 days
The critical path is the longest path through the network diagram, determining the shortest possible project duration. By summing the durations along each path, Path A-B-E-F totals 11 days (3+2+4+2), which is longer than the other paths, making 11 days the correct critical path duration.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
✗
9 days
Why it's wrong here
No path sums to 9 days.
✓
11 days
Why this is correct
Critical path is A-C-D = 11 days.
Related concept
Read the scenario before looking for a memorised answer.
✗
10 days
Why it's wrong here
That is the duration of path A-B-D.
✗
12 days
Why it's wrong here
Overestimated.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often mistakenly sum all activity durations in the diagram or pick the shortest path, rather than identifying the longest path through the network.
Detailed technical explanation
How to think about this question
The critical path method (CPM) identifies the sequence of activities with zero total float; any delay on this path directly delays the project. In this network, Path A-B-E-F has no float, while other paths have positive float, meaning they can slip without affecting the end date. Real-world project managers use CPM to prioritize resources on critical activities and compress schedules via crashing or fast-tracking.
KKey Concepts to Remember
Read the scenario before looking for a memorised answer.
Find the constraint that changes the correct option.
Eliminate answers that are true in general but not in this case.
TExam Day Tips
→Watch for words such as best, first, most likely and least administrative effort.
→Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
Related glossary terms
Concepts from this question explained
These glossary pages explain the core terms tested in this PMP question in full detail.
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: 11 days — The critical path is the longest path through the network diagram, determining the shortest possible project duration. By summing the durations along each path, Path A-B-E-F totals 11 days (3+2+4+2), which is longer than the other paths, making 11 days the correct critical path duration.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.