Question 85 of 892
Process — Managing Technical AspectseasyMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Refer to the exhibit.
```
Task A: 5 days
Task B: 3 days (depends on A)
Task C: 4 days (depends on A)
Task D: 2 days (depends on B and C)
```

Refer to the exhibit. What is the critical path duration?

Question 1easymultiple choice
Read the full NAT/PAT explanation →

Exhibit

Refer to the exhibit.
```
Task A: 5 days
Task B: 3 days (depends on A)
Task C: 4 days (depends on A)
Task D: 2 days (depends on B and C)
```

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

11 days

The critical path is the longest path through the network diagram, determining the shortest possible project duration. By summing the durations along each path, Path A-B-E-F totals 11 days (3+2+4+2), which is longer than the other paths, making 11 days the correct critical path duration.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 9 days

    Why it's wrong here

    No path sums to 9 days.

  • 11 days

    Why this is correct

    Critical path is A-C-D = 11 days.

    Related concept

    Read the scenario before looking for a memorised answer.

  • 10 days

    Why it's wrong here

    That is the duration of path A-B-D.

  • 12 days

    Why it's wrong here

    Overestimated.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often mistakenly sum all activity durations in the diagram or pick the shortest path, rather than identifying the longest path through the network.

Detailed technical explanation

How to think about this question

The critical path method (CPM) identifies the sequence of activities with zero total float; any delay on this path directly delays the project. In this network, Path A-B-E-F has no float, while other paths have positive float, meaning they can slip without affecting the end date. Real-world project managers use CPM to prioritize resources on critical activities and compress schedules via crashing or fast-tracking.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: 11 days — The critical path is the longest path through the network diagram, determining the shortest possible project duration. By summing the durations along each path, Path A-B-E-F totals 11 days (3+2+4+2), which is longer than the other paths, making 11 days the correct critical path duration.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.