Question 716 of 892
Process — Managing Technical AspectshardMultiple ChoiceObjective-mapped

Quick Answer

The answer is that the project is over budget and behind schedule. This conclusion is drawn from interpreting EV, PV, and AC data through earned value analysis: the Cost Performance Index (CPI) is 0.833, calculated as EV divided by AC, which is below 1.0 and signals a cost overrun, while the Schedule Performance Index (SPI) is 0.909, calculated as EV divided by PV, which is also below 1.0 and confirms the project is lagging behind its planned timeline. On the PMP exam, this type of question tests your ability to quickly compute and interpret CPI and SPI from raw EV, PV, and AC figures, often appearing in scenario-based items where you must assess overall health without additional context. A common trap is focusing only on one metric—for instance, seeing a low CPI and assuming the project is simply over budget, while missing the schedule delay revealed by the SPI. To remember the formulas, think of CPI as “cost” (AC in the denominator) and SPI as “speed” (PV in the denominator); both must be above 1.0 for a healthy project.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project is 50% complete, and your earned value analysis shows: EV = $200,000, PV = $220,000, AC = $240,000. Based on this data, what is the most accurate assessment of the project's performance?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is over budget and behind schedule

CPI = EV/AC = 200,000/240,000 = 0.833 (over budget); SPI = EV/PV = 200,000/220,000 = 0.909 (behind schedule). The project is both over budget and behind schedule.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is over budget and behind schedule

    Why this is correct

    CPI < 1 means over budget; SPI < 1 means behind schedule.

    Related concept

    Read the scenario before looking for a memorised answer.

  • The project is under budget and ahead of schedule

    Why it's wrong here

    Both CPI and SPI are less than 1, indicating over budget and behind schedule.

  • The project is over budget but ahead of schedule

    Why it's wrong here

    SPI < 1 indicates behind schedule, not ahead.

  • The project is under budget but behind schedule

    Why it's wrong here

    CPI < 1 indicates over budget, not under.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: The project is over budget and behind schedule — CPI = EV/AC = 200,000/240,000 = 0.833 (over budget); SPI = EV/PV = 200,000/220,000 = 0.909 (behind schedule). The project is both over budget and behind schedule.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Your project is halfway through its schedule. Earned value analysis shows: EV = $120,000, PV = $150,000, AC = $140,000. What is the best interpretation of the project's performance?

medium
  • A.The project is behind schedule but under budget.
  • B.The project is behind schedule and over budget.
  • C.The project is on schedule and under budget.
  • D.The project is ahead of schedule but over budget.

Why B: SPI = EV/PV = 0.8, indicates behind schedule. CPI = EV/AC = 0.857, indicates over budget. The project is both behind schedule and over budget.

Variation 2. At the midpoint of your 18-month project, the earned value analysis shows: EV = $450,000, PV = $500,000, AC = $550,000. What should you be most concerned about?

medium
  • A.The project is ahead of schedule but over budget.
  • B.The project is both behind schedule and over budget.
  • C.The project is on schedule and on budget.
  • D.The project is behind schedule but on budget.

Why B: With EV < PV and EV < AC, the project is behind schedule and over budget. The cost performance index (CPI) is 0.82, indicating cost efficiency is poor. Both schedule and cost are concerns, but cost overrun is more severe.

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.