Courseiva
Process — Managing Technical AspectsmediumDrag & DropObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

Order the steps for closing a project or phase.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Verify deliverables → Report on project performance → Obtain sign-off → Release resources → Review lessons learned

Project closure: verify deliverables, report, obtain sign-off, release resources, and review lessons.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Verify deliverables → Report on project performance → Obtain sign-off → Release resources → Review lessons learned

    Why this is correct

    This is the correct order because project closure begins with verifying that deliverables meet requirements, then reporting performance to stakeholders, obtaining formal acceptance, releasing project resources, and finally reviewing lessons learned to improve future projects.

  • Obtain sign-off → Release resources → Verify deliverables → Report on project performance → Review lessons learned

    Why it's wrong here

    This sequence is incorrect because formal acceptance (sign-off) must be predicated on verified deliverables and a comprehensive performance report, not precede them. Obtaining sign-off prematurely risks accepting incomplete or unvalidated work. Furthermore, releasing resources before deliverables are verified and accepted can severely impede any necessary rework or final adjustments, leading to costly delays if resources must be re-acquired.

  • Review lessons learned → Verify deliverables → Report → Obtain sign-off → Release resources

    Why it's wrong here

    This order is incorrect because reviewing lessons learned is an output activity that synthesizes knowledge from the entire project, including performance and stakeholder feedback, which are gathered and analyzed later in the closure process. Initiating closure with lessons learned would mean attempting to capture insights before the project's final outcomes are fully realized, verified, or reported, making the review incomplete and less effective. It disrupts the logical flow of validating completion before reflecting on the journey.

  • Verify deliverables → Obtain sign-off → Report → Release resources → Review lessons learned

    Why it's wrong here

    This option is incorrect because the official project performance report provides critical context and data that stakeholders require to make an informed decision regarding formal acceptance. Obtaining sign-off before presenting the comprehensive performance report undermines transparency and the basis for formal project or phase acceptance. Stakeholders need to understand the project's overall success, challenges, and final metrics before providing their formal endorsement.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.