Drag steps to the numbered slots on the right, or tap a step then tap a slot.
PMP Business Environment — Strategy and Value Practice Question
Sequence the steps for performing a qualitative risk analysis.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Identify risks, then assess probability and impact, then prioritize risks, then categorize risks, then update the risk register.
Qualitative analysis involves identifying risks, assessing probability and impact, prioritizing, categorizing, and updating the register.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Identify risks, then assess probability and impact, then prioritize risks, then categorize risks, then update the risk register.
Why this is correct
This is the correct order because qualitative risk analysis begins with identifying risks, then assessing their probability and impact, prioritizing them based on these assessments, categorizing for further analysis, and finally updating the risk register with the results.
- ✗
Assess probability and impact, then identify risks, then prioritize risks, then categorize risks, then update the risk register.
Why it's wrong here
Assessing probability and impact before identifying risks is fundamentally illogical within the project risk management framework. The 'Identify Risks' process is designed to discover, document, and characterize individual project risks, making them tangible entities. Without first identifying these specific risks, there is no defined subject upon which to apply probability and impact assessments, rendering such an attempt premature and ineffective.
- ✗
Identify risks, then prioritize risks, then assess probability and impact, then categorize risks, then update the risk register.
Why it's wrong here
Prioritizing risks without first assessing their probability and impact would lead to an arbitrary or highly subjective ranking. The core mechanism of qualitative risk analysis involves evaluating each identified risk's likelihood of occurrence and potential effect on project objectives. These assessments are crucial inputs for calculating a risk score, which then enables an objective prioritization, ensuring that the most significant risks receive appropriate attention.
- ✗
Identify risks, then assess probability and impact, then categorize risks, then prioritize risks, then update the risk register.
Why it's wrong here
While risk categorization can occur at various stages, placing it before prioritization in qualitative risk analysis is suboptimal. The primary goal of qualitative analysis is to prioritize risks based on their assessed severity, allowing the team to focus on the most critical ones. Categorizing risks *after* prioritization allows for grouping high-priority risks by common root causes, affected objectives, or response strategies, which enhances the efficiency of subsequent risk response planning.
Go deeper
Related to this question
About these practice questions
This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.