Question 585 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is to perform an impact analysis and submit the change request to the Change Control Board (CCB). This is correct because the first step in any change request impact analysis is to assess how the proposed change affects the project’s triple constraints—scope, schedule, cost, quality, and risk—before any decision can be made. On the PMP exam, this scenario tests your understanding of the Integrated Change Control process, where the project manager’s role is to analyze impacts, not to approve or reject changes unilaterally. A common trap is to think you should implement the change because the project has buffer, but the correct sequence is always analyze first, then submit to the CCB. Remember the mnemonic “A.C.T.”: Assess the impact, Communicate the analysis, then Turn it over to the CCB for a decision.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

During a project's execution phase, you receive a change request from a stakeholder that would improve the product's performance but is not required by the original specifications. The change is estimated to add 2 weeks to the schedule and $10,000 to the budget. The project is currently on schedule and under budget. What should you do FIRST?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Perform an impact analysis and submit the change request to the CCB

The PM should first assess the impact of the change on the project constraints (scope, schedule, cost, quality, risk) and then present the analysis to the CCB for a decision. Proceeding without approval or rejecting outright are not appropriate.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Instruct the team to implement the change and adjust the project plan later

    Why it's wrong here

    Implementing without approval bypasses change control.

  • Approve the change since the project has contingency

    Why it's wrong here

    The PM should not approve changes without following the change control process.

  • Perform an impact analysis and submit the change request to the CCB

    Why this is correct

    The PM should evaluate the change and let the CCB decide based on the analysis.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Reject the change because it is out of scope

    Why it's wrong here

    Rejecting without evaluation is not the PMI approach; changes should be assessed through the process.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Perform an impact analysis and submit the change request to the CCB — The PM should first assess the impact of the change on the project constraints (scope, schedule, cost, quality, risk) and then present the analysis to the CCB for a decision. Proceeding without approval or rejecting outright are not appropriate.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

3 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During a project's execution phase, a key stakeholder requests a change that would add a new feature. The project manager estimates the impact: 2 additional weeks to schedule and $15,000 to budget. The project currently has 0 schedule reserve and $5,000 contingency reserve. What should the project manager do first?

medium
  • A.Approve the change using contingency reserve and inform the stakeholder
  • B.Implement the change immediately since the stakeholder is key
  • C.Reject the change because there is insufficient reserve
  • D.Document the change request and conduct a formal impact analysis

Why D: Option D is correct because the PMBOK Guide mandates that all change requests must be formally documented and analyzed for impact before any approval or rejection. Even though the project has a contingency reserve, the change introduces a new feature, which is a scope change requiring a formal change control process. The project manager must first document the request and conduct a thorough impact analysis to assess alternatives, risks, and stakeholder implications before deciding on the change.

Variation 2. During project execution, a key stakeholder requests a change that will increase the scope. The project manager follows the formal change control process. What is the first step the project manager should take?

easy
  • A.Communicate the change to the project team.
  • B.Submit the change request to the change control board (CCB).
  • C.Document the change request in the change log.
  • D.Analyze the impact on the project constraints.

Why C: Option C is correct because the first step in the formal change control process, as defined by the PMBOK Guide, is to document the change request in the change log. This ensures that all proposed changes are formally recorded and tracked before any analysis or approval activities occur. Without this initial documentation, there is no official record of the request, which undermines the integrity of the change control system.

Variation 3. During project execution, a key stakeholder requests a change that will increase project scope by 15% but will also reduce operational costs by 20% after deployment. The project is currently on schedule and under budget. The project manager should FIRST:

hard
  • A.Implement the change as it provides clear business value.
  • B.Reject the change because it increases scope beyond the approved baseline.
  • C.Document the change request and analyze its impact on the project constraints.
  • D.Present the change to the Change Control Board (CCB) for approval.

Why C: Option C is correct because, per the PMBOK Guide, the project manager must first document any change request and analyze its impact on the project constraints (scope, schedule, cost, quality, resources, and risk) before any decision is made. Even though the change appears beneficial, the formal change control process requires a documented impact analysis to ensure the trade-offs are fully understood and the change is properly evaluated against the project's baselines.

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.