Question 53 of 892
Business Environment: strategy and project benefitsmediumMultiple SelectObjective-mapped

Quick Answer

The answer is to update the project management plan and communicate the change to relevant stakeholders. After an approved change request affecting the critical path, the project manager must first integrate the change into the formal project baselines—such as the schedule and cost baselines—by updating the project management plan, then immediately notify all impacted parties to ensure alignment and prevent rework. On the PMP exam, this scenario tests your understanding of the Perform Integrated Change Control process and the distinction between updating documents versus executing the change; a common trap is selecting “implement the change” too early, but implementation occurs only after the plan is updated and communicated. Remember the mnemonic “U and C” for Update and Communicate—never skip informing stakeholders after a critical path adjustment, as it directly impacts dependencies and resource availability.

PMP Practice Question: Business Environment: strategy and project benefits

This PMP practice question tests your understanding of business environment: strategy and project benefits. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is leading a project that has a change request that would affect the critical path. The change request has been approved. Which TWO actions should the PM take next?

Question 1mediummulti select
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Update the project management plan to reflect the approved change

Option B and C are correct because after approval, the PM must update the project management plan and communicate the changes. Option A is incomplete, D is not a direct action for this change, E may be part of plan but not immediate.

Key principle: NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Update the lessons learned repository

    Why it's wrong here

    Lessons learned are captured throughout the project, but this is not the next immediate action.

  • Implement the change immediately

    Why it's wrong here

    Implementation should be done after updating plans and communicating.

  • Update the project management plan to reflect the approved change

    Why this is correct

    The PM must update all relevant baselines and plans.

    Related concept

    Static NAT maps one inside address to one outside address.

  • Update the change log only

    Why it's wrong here

    While the change log should be updated, it is not sufficient; the plan must also be updated.

  • Communicate the change to relevant stakeholders

    Why this is correct

    Stakeholders need to be informed of approved changes.

    Related concept

    Static NAT maps one inside address to one outside address.

Common exam traps

Common exam trap: NAT rules depend on direction and matching traffic

NAT is not only about the public address. The inside/outside interface roles and the ACL or rule that matches traffic are just as important.

Detailed technical explanation

How to think about this question

NAT questions usually test address translation, overload/PAT behaviour, static mappings and whether the right traffic is being translated. Read the interface direction and address terms carefully.

KKey Concepts to Remember

  • Static NAT maps one inside address to one outside address.
  • PAT allows many inside hosts to share one public address using ports.
  • Inside local and inside global describe the private and translated addresses.
  • NAT ACLs identify traffic for translation, not always security filtering.

TExam Day Tips

  • Identify inside and outside interfaces first.
  • Check whether the scenario needs static NAT, dynamic NAT or PAT.
  • Do not confuse NAT matching ACLs with normal packet-filtering intent.

Key takeaway

NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Business Environment: strategy and project benefits — This question tests Business Environment: strategy and project benefits — Static NAT maps one inside address to one outside address..

What is the correct answer to this question?

The correct answer is: Update the project management plan to reflect the approved change — Option B and C are correct because after approval, the PM must update the project management plan and communicate the changes. Option A is incomplete, D is not a direct action for this change, E may be part of plan but not immediate.

What should I do if I get this PMP question wrong?

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.

What is the key concept behind this question?

Static NAT maps one inside address to one outside address.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.