Question 268 of 892
Process — Managing Technical AspectseasyMultiple SelectObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is developing the project schedule. Which TWO techniques can be used to compress the schedule without changing project scope?

Question 1easymulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Fast tracking

Fast tracking is a schedule compression technique that involves performing activities in parallel that would normally be done sequentially. This can shorten the project schedule without altering the project scope, as it only changes the logical relationships between tasks.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Fast tracking

    Why this is correct

    Fast tracking performs activities in parallel that were originally sequential.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Critical chain method

    Why it's wrong here

    Critical chain adds buffers and does not compress the schedule.

  • Crashing

    Why this is correct

    Crashing adds resources to critical path tasks to reduce duration.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Resource leveling

    Why it's wrong here

    Resource leveling often extends the schedule to resolve resource over-allocations.

  • Monte Carlo simulation

    Why it's wrong here

    Monte Carlo is used for risk analysis, not schedule compression.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is confusing schedule compression techniques (fast tracking and crashing) with schedule optimization or analysis techniques like critical chain, resource leveling, or Monte Carlo simulation, which do not directly compress the schedule without scope change.

Detailed technical explanation

How to think about this question

Fast tracking works by overlapping phases or tasks that were originally planned in sequence, such as starting construction before all design is complete. This increases risk of rework because later tasks may be based on incomplete information, but it does not change the project scope. Crashing, the other correct answer, adds resources (e.g., overtime, extra staff) to critical path activities to reduce duration, also without scope change.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Fast tracking — Fast tracking is a schedule compression technique that involves performing activities in parallel that would normally be done sequentially. This can shorten the project schedule without altering the project scope, as it only changes the logical relationships between tasks.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.