- A
Stakeholder analysis
Stakeholder analysis is part of the stakeholder register output.
- B
Stakeholder management plan
Why wrong: This is an output of Plan Stakeholder Engagement.
- C
Issue log
Why wrong: Issue log is an output of Manage Stakeholder Engagement.
- D
Stakeholder register
Stakeholder register is a direct output of Identify Stakeholders.
- E
Stakeholder engagement plan
Why wrong: This is an output of Plan Stakeholder Engagement.
Quick Answer
The answer is the Stakeholder Register. This is the primary formal output of the Identify Stakeholders process because it documents all individuals, groups, or organizations that may impact or be impacted by a project, along with their interests, expectations, and influence levels. On the Certified Associate in Project Management CAPM exam, this question tests your ability to distinguish between a process output and a tool or technique, as Stakeholder Analysis is a common trap—it is a method used to create the register, not the output itself. A frequent exam twist is that the analysis results are documented in the register, so some answer keys may accept "Stakeholder analysis" as a secondary output, but the register remains the definitive deliverable. To remember, think: "Identify outputs a list, not the method to make it"—the Stakeholder Register is the tangible result you hand off to the next process.
CAPM Practice Question: Project Management Fundamentals and Core Concepts
This CAPM practice question tests your understanding of project management fundamentals and core concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Which TWO of the following are outputs of the Identify Stakeholders process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Stakeholder analysis
The Identify Stakeholders process is the first process in the Project Communications Management knowledge area (PMBOK Guide, 6th Edition). Its primary output is the Stakeholder Register, which lists all identified stakeholders and their key details. Stakeholder Analysis is a technique used within this process, not an output; however, the question's answer key treats 'Stakeholder analysis' as a correct output because the analysis results are documented and become part of the project records. The Stakeholder Register is the formal, documented output that captures the analysis.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Stakeholder analysis
Why this is correct
Stakeholder analysis is part of the stakeholder register output.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Stakeholder management plan
Why it's wrong here
This is an output of Plan Stakeholder Engagement.
- ✗
Issue log
Why it's wrong here
Issue log is an output of Manage Stakeholder Engagement.
- ✓
Stakeholder register
Why this is correct
Stakeholder register is a direct output of Identify Stakeholders.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Stakeholder engagement plan
Why it's wrong here
This is an output of Plan Stakeholder Engagement.
Common exam traps
Common exam trap: answer the scenario, not the keyword
PMI often tests the distinction between outputs of the Identify Stakeholders process (Stakeholder Register and Stakeholder Analysis documentation) and outputs of later planning processes (Stakeholder Engagement Plan, Stakeholder Management Plan), causing candidates to confuse the planning outputs with the initial identification outputs.
Trap categories for this question
Command / output trap
This is an output of Plan Stakeholder Engagement.
Detailed technical explanation
How to think about this question
The Stakeholder Register is a living document that is updated throughout the project. It typically includes identification information (name, role, organization), assessment information (power/interest grid classification), and stakeholder classification (e.g., internal/external, supporter/resistor). The Stakeholder Analysis technique involves gathering and evaluating quantitative and qualitative information to determine whose interests should be taken into account. In practice, the Stakeholder Register is often maintained in a project management information system (PMIS) and feeds directly into the Plan Stakeholder Engagement process.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Fundamentals and Core Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Fundamentals and Core Concepts practice questions
Targeted practice on this topic area only
- →
All CAPM questions
503 questions across all exam domains
- →
Certified Associate in Project Management CAPM study guide
Full concept coverage aligned to exam objectives
- →
CAPM practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related CAPM practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Agile Frameworks and Methodologies practice questions
Practise CAPM questions linked to Agile Frameworks and Methodologies.
Project Management Fundamentals and Core Concepts practice questions
Practise CAPM questions linked to Project Management Fundamentals and Core Concepts.
Predictive Plan-Based Methodologies practice questions
Practise CAPM questions linked to Predictive Plan-Based Methodologies.
Business Analysis Frameworks practice questions
Practise CAPM questions linked to Business Analysis Frameworks.
CAPM fundamentals practice questions
Practise CAPM questions linked to CAPM fundamentals.
CAPM scenario practice questions
Practise CAPM questions linked to CAPM scenario.
CAPM troubleshooting practice questions
Practise CAPM questions linked to CAPM troubleshooting.
Practice this exam
Start a free CAPM practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this CAPM question test?
Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Stakeholder analysis — The Identify Stakeholders process is the first process in the Project Communications Management knowledge area (PMBOK Guide, 6th Edition). Its primary output is the Stakeholder Register, which lists all identified stakeholders and their key details. Stakeholder Analysis is a technique used within this process, not an output; however, the question's answer key treats 'Stakeholder analysis' as a correct output because the analysis results are documented and become part of the project records. The Stakeholder Register is the formal, documented output that captures the analysis.
What should I do if I get this CAPM question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 30, 2026
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.