Question 31 of 503

Quick Answer

The answer is that the project is over budget and ahead of schedule. This interpretation comes directly from earned value management CPI and SPI interpretation: a Cost Performance Index below 1.0, like 0.8, means the project is spending more than planned for the work completed, indicating a cost overrun, while a Schedule Performance Index above 1.0, like 1.2, means more work has been completed than planned, indicating the project is ahead of schedule. On the Certified Associate in Project Management CAPM exam, this concept tests your ability to read performance indices without calculation—a common trap is mixing up the direction of the indices, such as thinking a CPI below 1 means under budget. A reliable memory tip is to remember that “less than 1 is less than good” for both indices: CPI below 1 means cost is less favorable (over budget), and SPI below 1 means schedule is less favorable (behind schedule); conversely, above 1 means better than planned.

CAPM Practice Question: Project Management Fundamentals and Core Concepts

This CAPM practice question tests your understanding of project management fundamentals and core concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

In earned value management, if the Cost Performance Index (CPI) is 0.8 and the Schedule Performance Index (SPI) is 1.2, what does this indicate?

Question 1hardmultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is over budget and ahead of schedule.

Option D is correct because a CPI less than 1 indicates cost overrun, and an SPI greater than 1 indicates ahead of schedule. Options A, B, and C describe incorrect combinations.

Key principle: NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is over budget and behind schedule.

    Why it's wrong here

    SPI>1 indicates ahead of schedule.

  • The project is under budget and behind schedule.

    Why it's wrong here

    CPI<1 means over budget, SPI>1 means ahead of schedule.

  • The project is over budget and ahead of schedule.

    Why this is correct

    CPI=0.8 means over budget, SPI=1.2 means ahead of schedule.

    Related concept

    Static NAT maps one inside address to one outside address.

  • The project is on budget and on schedule.

    Why it's wrong here

    CPI and SPI should be 1.0.

Common exam traps

Common exam trap: NAT rules depend on direction and matching traffic

NAT is not only about the public address. The inside/outside interface roles and the ACL or rule that matches traffic are just as important.

Detailed technical explanation

How to think about this question

NAT questions usually test address translation, overload/PAT behaviour, static mappings and whether the right traffic is being translated. Read the interface direction and address terms carefully.

KKey Concepts to Remember

  • Static NAT maps one inside address to one outside address.
  • PAT allows many inside hosts to share one public address using ports.
  • Inside local and inside global describe the private and translated addresses.
  • NAT ACLs identify traffic for translation, not always security filtering.

TExam Day Tips

  • Identify inside and outside interfaces first.
  • Check whether the scenario needs static NAT, dynamic NAT or PAT.
  • Do not confuse NAT matching ACLs with normal packet-filtering intent.

Key takeaway

NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related CAPM NAT questions on configuration and troubleshooting.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Static NAT maps one inside address to one outside address..

What is the correct answer to this question?

The correct answer is: The project is over budget and ahead of schedule. — Option D is correct because a CPI less than 1 indicates cost overrun, and an SPI greater than 1 indicates ahead of schedule. Options A, B, and C describe incorrect combinations.

What should I do if I get this CAPM question wrong?

Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related CAPM NAT questions on configuration and troubleshooting.

What is the key concept behind this question?

Static NAT maps one inside address to one outside address.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on CAPM

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Refer to the exhibit. What is the cost performance index (CPI)?

easy
  • A.0.83
  • B.0.91
  • C.1.20
  • D.1.10

Why A: Option C is correct. CPI = EV/AC = 5000/6000 = 0.83. Options A, B, and D are incorrect calculations.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.