Question 209 of 503
Project Management Fundamentals and Core ConceptsmediumMultiple ChoiceObjective-mapped

Quick Answer

The correct answer is to implement critical chain project management. This technique is specifically designed to reduce unplanned work by inserting strategic buffers—such as a project buffer at the end and feeding buffers at integration points—which absorb delays and protect the critical path from disruptions. By enforcing a "relay race" work ethic where team members focus on one task at a time and pass work forward without multitasking, CCPM directly addresses the root cause of unplanned work eating into schedule reserves. On the CAPM exam, this question tests your understanding of how CCPM differs from traditional critical path method; a common trap is confusing it with simply adding more resources or crashing the schedule. Remember the memory tip: "Buffers beat burnout"—the buffers in CCPM are not slack but deliberate shields against the chaos of unplanned tasks, keeping the team focused on priority order.

CAPM Practice Question: Project Management Fundamentals and Core Concepts

This CAPM practice question tests your understanding of project management fundamentals and core concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project team is working on a software development project. The project manager notices that the team is spending too much time on unplanned work, resulting in delays to the critical path. What technique should the project manager use to reduce unplanned work and improve focus?

Question 1mediummultiple choice
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Implement critical chain project management.

Critical chain project management (CCPM) is specifically designed to protect the critical path from disruptions like unplanned work by inserting buffers (e.g., feeding buffers, project buffer) and enforcing a 'relay race' work ethic. This technique reduces multitasking and focuses the team on completing tasks in priority order, directly addressing the root cause of delays from unplanned work.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Apply crashing to the critical path activities.

    Why it's wrong here

    Crashing adds resources to speed up, but doesn't reduce unplanned work.

  • Perform resource leveling to smooth resource usage.

    Why it's wrong here

    Resource leveling may delay the project, not reduce unplanned work.

  • Use fast tracking to overlap activities.

    Why it's wrong here

    Fast tracking may increase rework and unplanned work.

  • Implement critical chain project management.

    Why this is correct

    Critical chain focuses on resource constraints and buffers, reducing unplanned work.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates confuse schedule compression techniques (crashing, fast tracking) with schedule protection techniques, failing to recognize that unplanned work requires a buffer-based approach like CCPM rather than simply accelerating planned activities.

Detailed technical explanation

How to think about this question

CCPM uses a 'buffer management' mechanism where the project buffer (typically 50% of the critical path duration) absorbs delays from unplanned work, and feeding buffers protect the critical path from non-critical chain delays. In practice, CCPM enforces a 'no multitasking' rule by prioritizing tasks based on buffer penetration, which directly reduces the time lost to context switching and unplanned interruptions. A real-world scenario is a software team using CCPM to shield the critical path from urgent bug fixes by allocating a 'buffer' for such unplanned work, ensuring the core feature delivery stays on track.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Implement critical chain project management. — Critical chain project management (CCPM) is specifically designed to protect the critical path from disruptions like unplanned work by inserting buffers (e.g., feeding buffers, project buffer) and enforcing a 'relay race' work ethic. This technique reduces multitasking and focuses the team on completing tasks in priority order, directly addressing the root cause of delays from unplanned work.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.