The Practices domain covers how PRINCE2's seven practices are applied and tailored across a project: Business Case, Organizing, Plans, Quality, Risk, Issues, and Progress. Practitioner questions present scenarios and ask you to select the most appropriate action, management product, or role responsibility, testing whether you can apply the method rather than merely recall definitions.
Focused practice
Practice Practices questions
Scored sessions drawing only from this domain — pick a length below.
Start 20-question practice test →What this domain covers
What to know about Practices
You must be able to choose the right PRINCE2 practice output or role action for a scenario, not just define it. The single most important thing is to justify each decision against the principles and the project's tolerances and tailoring.
Selecting the correct management product for a given process, such as the Business Case or Benefits Management Approach.
Assigning responsibilities across the project board, Project Manager, Project Assurance, and Change Authority.
Tailoring plans, controls, and product dependencies to iterative or linear delivery approaches.
Applying the risk, issue, and quality registers and their associated tolerances and escalation routes.
Watch out for
Common Practices exam traps
- ▸Confusing Project Assurance with Project Support: Assurance monitors the project independently on behalf of the board, while Support administers tools and information.
- ▸Assuming the Business Case is only written once at the start; it must be reviewed and updated at each stage boundary and when significant change occurs.
- ▸Treating the Plans practice as only the Project Plan, ignoring stage plans, team plans, and the product breakdown and flow needed for dependencies.
Question index
All Practices questions (127)
Click any question to see the full explanation, or start a practice session above.
A project plan includes strict sustainability milestones to comply with new environmental regulations. During plan development, the Project Manager needs to ensure that dependencies between environmental audit checkpoints and procurement deliverables are accurately mapped. Which tool/technique supports this within product-based planning?
Hard2When applying product-based planning within the PRINCE2 Plans practice, which TWO of the following steps must be completed before estimating effort and scheduling activities?
Hard3A project manager is developing a Stage Plan using product-based planning. The project includes software development and strict environmental compliance documentation. During the creation of the Product Flow Diagram, the team realizes that the environmental compliance audit must be completed *before* software deployment can be signed off. How is this dependency represented?
Hard4In the PRINCE2 Risk practice, what is the primary difference between a risk and an issue?
Easy5In the PRINCE2 Plans practice, what is the name of the hierarchical structure that breaks down the project into its constituent products?
Easy6A project manager is analyzing a newly identified risk regarding potential supply chain disruption. After assessing its probability and impact, the project manager decides to engage with a key supplier to redesign the component to use locally sourced, sustainable materials instead. Which risk response category does this represent?
Medium7A Team Manager wants to establish how frequently team progress should be reported to the Project Manager. Which report should be set up for this purpose?
Medium8In the PRINCE2 Quality practice, what is the primary purpose of a quality review meeting?
Easy9A project is using agile delivery methods within a PRINCE2 framework. The Project Board wants to receive progress updates on product increments rather than lengthy narrative reports. Which PRINCE2 progress reporting product should be tailored to meet this need?
Hard10In the PRINCE2 Issues practice, what is the purpose of an Issue Report?
Easy11An issue has been raised concerning a disagreement between the Senior User and a Supplier regarding product acceptance criteria. What type of issue is this?
Easy12A project is incorporating ESG (Environmental, Social, and Governance) principles. In which practice is the overall sustainability strategy for the project's outputs and outcomes formally documented and justified?
Hard13A team member identifies a variance in project progress where a work package is running two weeks late. According to the Issues practice, what is the immediate first step the Project Manager should take?
Easy14A project has experienced an unforecasted external market shift that drastically reduces the expected financial return, causing the Business Case to become unviable. According to the Business Case practice, what is the proper protocol?
Hard15In the PRINCE2 Issues practice, what is the primary purpose of the Issue Register?
Easy16A newly appointed Project Manager finds that the project organization structure has combined the roles of the Executive and the Project Manager into a single individual to save costs. According to PRINCE2 7, what is the primary risk of this configuration?
Hard17In the PRINCE2 Quality practice, what is the purpose of a Product Description?
Easy18In the PRINCE2 Progress practice, what is the name of the report produced by a Team Manager to inform the Project Manager of team-level progress?
Easy19An organization applies PRINCE2 and uses rolling wave planning within the Plans practice. During Stage 2 execution, the Project Manager begins detailed planning for Stage 3. New environmental regulations come into light that require a complete redesign of Stage 3 deliverables. How should the Plans practice accommodate this?
Hard20In the PRINCE2 Risk practice, what is the name of the log used to capture and maintain information on all identified threats and opportunities?
Easy21Which TWO of the following are true regarding the Quality practice in PRINCE2 7? (Choose two)
Medium22A project manager is recording an uncertainty that could have a positive impact on the project schedule. Where should this uncertainty be logged?
Easy23In the PRINCE2 Quality practice, what is the term used for the specific characteristics that a product must possess to meet stakeholder expectations and standards?
Easy24During stage execution, a Team Manager realizes that a work package cannot be completed within the agreed time tolerance due to unexpected technical hurdles. What should the Team Manager do according to the Issues practice?
Easy25A project is nearing the end of a management stage. The Project Manager has drafted an End Stage Report. Who is responsible for reviewing and approving the End Stage Report?
Medium26A project is developing a new software system. The Project Manager discovers that one of the operational benefits listed in the Business Case will actually occur 12 months *after* the project has officially closed. How should this be handled under PRINCE2 7?
Medium27In PRINCE2, what is the primary purpose of the Progress practice?
Easy28A PRINCE2 project is conducting a formal quality review for a safety-critical engineering component. During the review, a minor defect is found that can be easily corrected within the planned stage time and cost. What is the correct procedure for handling this defect?
Medium29In the PRINCE2 Issues practice, what is the primary purpose of a Request for Change?
Easy30A PRINCE2 project is operating with a Team Manager who discovers that a work package cannot be completed within the agreed time tolerance due to unexpected technical complexity. According to PRINCE2, what is the Team Manager's immediate reporting duty?
Hard31A PRINCE2 project is executing a stage when an unexpected risk event occurs. The risk was previously identified and evaluated as having a medium impact, and a contingency reserve was set aside. The risk materializes, and the contingency reserve is used. How should this be recorded in the Risk Register?
Medium32A project manager wants to ensure that all changes to project baselines are formally controlled. Under which practice is change control managed?
Easy33A PRINCE2 project is implementing an AI system. The risk management team identifies an ethical risk regarding biased algorithmic outputs. The project team decides to implement continuous algorithmic auditing and diverse training datasets. Which risk response is being applied?
Hard34During a PRINCE2 project stage, the Project Manager forecasts that the stage cost will exceed the upper cost tolerance by 5%. According to the Progress practice, what is the mandatory action the Project Manager must take?
Medium35Which TWO of the following reports are used in the Progress practice to communicate status between different levels of management? (Choose two)
Medium36A PRINCE2 project is implementing an enterprise-wide software system. The Project Manager wants to ensure that all business units affected by the change are adequately represented in decision-making and requirements-gathering. Which PRINCE2 practice and governance structure addresses this?
Hard37A project team is implementing an agile delivery approach. The Project Manager is configuring the Plans practice to support iterative product delivery. How should the plans be structured to ensure PRINCE2 governance while allowing agile flexibility?
Hard38A project manager is developing a Business Case and needs to account for the operational costs that will occur after the project is completed and handed over to operations. What PRINCE2 term describes these ongoing costs?
Medium39A PRINCE2 project is executing a stage. The Project Manager discovers that due to an unexpected supply chain bottleneck, the stage will finish 3 weeks late, which breaches the stage time tolerance. The Project Manager prepares an Exception Report and an Exception Plan. Who has the authority to approve the Exception Plan?
Medium40A PRINCE2 project is adopting agile delivery. The Project Board is concerned that product quality might be compromised due to rapid, iterative coding cycles. Which PRINCE2 practice and tool combination should the Project Manager emphasize to reassure the Board?
Hard41A project manager is setting up the project organization. The project involves highly specialized nuclear engineering. The Senior Supplier wants to delegate technical oversight to an external subcontractor. According to PRINCE2, who remains ultimately accountable for the supplier's delivery performance on the Project Board?
Medium42In the PRINCE2 Plans practice, what is the primary purpose of a Project Plan?
Easy43A project risk has been identified regarding potential supply chain delays for sustainable materials. The Project Manager wants to assign ownership for investigating and monitoring this specific risk. Who should be assigned as the risk owner?
Medium44A project is using an agile delivery method within a PRINCE2 governance framework. The Project Board wants to ensure that delivery increments are meeting quality standards before acceptance. Who is responsible for formally accepting completed products on behalf of the user community?
Hard45In the PRINCE2 Quality practice, what is the purpose of establishing a Quality Register?
Easy46A PRINCE2 project is structured with multiple delivery teams operating under different Team Managers. One Team Manager consistently fails to provide Checkpoint Reports on time, blinding the Project Manager to potential schedule slippages. According to the Progress practice, what is the best governance remedy?
Hard47Which TWO of the following statements correctly describe the relationship between tolerances and reporting in the PRINCE2 Progress practice?
Hard48In the Quality practice, who is responsible for approving the Quality Management Approach and setting overall quality expectations?
Easy49A PRINCE2 project is closing. The Project Manager is preparing the End Project Report and must decide what to include about the project's products. Which statement correctly describes the content required for the End Project Report?
Medium50A project is implementing product-based planning. The Project Manager has created a Product Breakdown Structure. What is the next logical step in product-based planning?
Medium51A project introduces a risk where a new software tool might fail to comply with upcoming environmental electronic waste regulations (ESG integration). The Project Manager wants to apply a response that transfers the financial impact of this risk. Which response is best suited?
Hard52A PRINCE2 project includes an environmental sustainability risk: excessive waste during manufacturing. The project team identifies an opportunity: partnering with a local recycling startup could turn this waste into a secondary revenue stream. Which risk response is most appropriate for this opportunity?
Hard53A project manager is preparing a stage plan. To ensure that quality reviews are properly scheduled, what must be integrated into the schedule alongside technical task activities?
Medium54An organization is executing a multi-year transformation project under PRINCE2 7. The corporate strategy shifts, placing a massive new emphasis on net-zero carbon targets. The Executive reviews the project's Business Case and realizes the project's outputs no longer align with the new strategic mandate, although the project is on time and under budget. What is the mandatory PRINCE2 action?
Hard55A PRINCE2 project is applying the Quality practice. The Project Manager is defining the quality approach for a project that will deliver a new software system. The Project Manager must ensure that quality activities are properly planned and controlled. Which action best reflects the Quality practice?
Medium56A PRINCE2 project is executing a stage. The Project Manager discovers that a supplier has delivered software that contains undocumented open-source components, violating corporate security and licensing standards. How should this be classified and handled?
Medium57Under the PRINCE2 Organizing practice, which role represents the interests of those who will use the project's outputs, operate the resulting solution, or realize the benefits?
Easy58A PRINCE2 project is executing a stage. The Project Manager wants to establish how frequently Highlight Reports will be submitted to the Project Board. Where should this reporting frequency be formally defined?
Medium59Which TWO of the following describe valid aspects of the Issues practice in PRINCE2 7? (Choose two)
Medium60A PRINCE2 project is operating with decentralized agile delivery teams. An issue arises where two teams have conflicting dependencies on a shared database component, threatening the stage schedule. The Team Managers cannot resolve it between themselves. What is the correct escalation path under PRINCE2?
Hard61When implementing the Risk practice in a PRINCE2 7 project, which THREE of the following steps are part of the risk management procedure? (Choose three)
Hard62Which THREE of the following management products are part of the PRINCE2 Quality practice framework?
Hard63Which PRINCE2 practice focuses on defining *how*, *when*, and *by whom* a project's products will be created, verified, and controlled?
Easy64A PRINCE2 project is executing its final stage. During the Closing a Project process, the Project Manager prepares the End Project Report. A key stakeholder demands that the project remain open for another three months to support post-project user adoption. According to PRINCE2, how should this be handled?
Hard65A PRINCE2 project is operating with time and cost tolerances set at +/- 5%. Halfway through Stage 2, a major disruption occurs. The Project Manager forecasts a cost overrun of 8% and a schedule delay of 10%. What governance procedure is triggered?
Hard66A project manager receives an urgent request from a Senior User to add a new feature that was not in the original Project Product Description. The feature requires minor effort and fits within the stage cost tolerance. How should this request be handled?
Medium67When establishing project roles in the Organizing practice, why is it recommended that the Executive and the Project Manager roles not be held by the same person?
Easy68A project is subject to strict ESG reporting requirements. The Project Board needs assurance that the project's sustainability benefits are being accurately measured and reported. Who should provide independent assurance of these benefits?
Hard69A PRINCE2 project is implementing a sustainable manufacturing plant. The Project Manager needs to ensure that the project's progress tracking mechanisms include metrics for both financial expenditure and environmental resource consumption. How should the Progress practice be tailored?
Medium70A PRINCE2 project is subject to strict environmental regulations. The Quality Manager wants to ensure that all deliverables undergo regulatory compliance testing before being presented to the user. Where should these regulatory testing requirements be documented?
Medium71In the PRINCE2 Business Case practice, what term describes the measurable improvement resulting from an outcome perceived as an advantage by one or more stakeholders?
Easy72A PRINCE2 project is utilizing a stage-gate approach. At the end of Stage 2, the Project Board meets to review the End Stage Report and the updated Business Case before authorizing Stage 3. What PRINCE2 principle is primarily demonstrated by this activity?
Medium73Which TWO of the following statements correctly describe the purpose and content of the Benefits Management Approach?
Medium74A project manager is configuring the Progress practice for a high-risk project. The Project Board wants to ensure that management by exception is fully operational. Which parameter must be explicitly agreed upon between the Project Board and Corporate Management to establish the Project Board's authority?
Hard75During risk identification in a PRINCE2 project, the team identifies a risk where a key supplier might fail to meet sustainability targets, leading to reputational damage. The team decides to establish joint monitoring committees and share best practices with the supplier to help them succeed. Which risk response category is this?
Hard76Which document is created during the Initiating a Project process to define the mechanisms for measuring whether the project's expected outcomes have been achieved post-project?
Easy77In the PRINCE2 Organizing practice, what is the purpose of the Project Brief?
Easy78During a project stage, a major regulatory change occurs that mandates an immediate alteration to the project's design standards to meet new environmental laws (ESG). The Project Manager assesses that this will breach cost and time stage tolerances. What should the Project Manager do?
Hard79An organization is applying PRINCE2 7 to a complex transformation program. The Executive realizes that the project's benefits realization schedule has drifted by 6 months due to operational delays in adopting the new systems. Who is accountable for ensuring that the Benefits Management Approach is executed post-project?
Hard80When integrating sustainability and ESG into the PRINCE2 Organizing and Plans practices, which TWO of the following practices must be tailored to ensure compliance?
Hard81A PRINCE2 project is evaluating a risk where a critical raw material might become unavailable due to geopolitical tensions. The project team identifies an alternative recycled material that eliminates the dependency on the imported material. Which risk response category is this?
Medium82Which THREE of the following are categorized as formal 'issues' under the PRINCE2 Issues practice?
Medium83Which TWO of the following statements correctly describe the role of Project Assurance in PRINCE2?
Easy84In the PRINCE2 Issues practice, what is the name of the log used to record all informal day-to-day notes, thoughts, and events by the Project Manager?
Easy85Which THREE of the following roles are mandatory members of the Project Board in PRINCE2 7? (Choose three)
Hard86During a management stage, actual costs are tracking close to the cost tolerance limit. The Project Manager wants to understand how progress is reported and controlled. Which report does the Project Manager submit periodically to the Project Board to summarize progress against tolerances?
Medium87During a stage, a supplier identifies an opportunity to deliver a component faster by using a modular pre-fabrication method that also reduces construction waste on site (ESG). How should this opportunity be evaluated and managed?
Medium88A project manager is drafting the initial Business Case for a sustainable energy transition project. According to PRINCE2 7th Edition, which role is primarily accountable for ensuring that the Business Case remains viable throughout the project lifecycle?
Easy89A PRINCE2 project is executing its final management stage. The Project Manager is preparing the End Stage Report and notices that cumulative stage tolerances were slightly exceeded, but an Exception Plan was already approved by the Project Board for this final stage. How should the End Stage Report reflect this?
Medium90Which THREE of the following elements are typically documented within a Product Description in PRINCE2?
Medium91During project monitoring, the Project Manager notes that cumulative expenditure is trending outside the stage cost tolerance. According to the Progress practice, what action must the Project Manager take immediately?
Medium92A project is initiating, and the Project Manager needs to document how risks will be identified, assessed, and controlled throughout the project lifecycle. Which document should be created?
Easy93A project is experiencing severe scope creep and resource shortages. The Project Board wants to ensure that the project management team is properly structured to maintain accountability. According to the Organizing practice in PRINCE2 7, which role is specifically accountable for designing and appointing the project management team?
Medium94When integrating sustainability and ESG into the Business Case practice, which THREE of the following factors should typically be evaluated? (Choose three)
Hard95In the PRINCE2 Organizing practice, what is the primary role of Project Assurance?
Easy96Which THREE of the following management products are produced during the Managing a Stage Boundary process to support progress governance?
Medium97A project is utilizing an iterative delivery approach. The Project Manager is establishing plans for the upcoming management stage. How should product dependencies be documented when planning iterative increments?
Hard98A PRINCE2 project is running its first delivery stage. The Project Manager is preparing the Work Package for a team manager to build a new customer portal. The Project Manager wants to include a checkpoint to monitor progress and quality of the portal's build, and must decide what to put in the Work Package. Which action should the Project Manager take?
Medium99In the PRINCE2 Business Case practice, what is the document that records the justification for undertaking a project based on estimated costs, benefits, risks, and ESG impacts?
Easy100In the PRINCE2 Progress practice, what mechanism is used to establish the limits of authority delegated by the Project Board to the Project Manager?
Easy101A project manager is preparing the Business Case for a public infrastructure project. In accordance with PRINCE2 7, the organization mandates that all projects evaluate the 'Governance' (G) pillar of ESG. Which element should be included in the Business Case to satisfy this requirement?
Medium102Which THREE of the following elements are typically contained within a well-constructed Product Description in PRINCE2 7? (Choose three)
Hard103In the PRINCE2 Quality practice, what is the name of the management product that specifies the quality techniques, standards, responsibilities, and control mechanisms to be applied across the project?
Easy104Which THREE of the following are recognized risk response categories for threats in PRINCE2 7? (Choose three)
Hard105A project is implementing a sustainable energy grid. During execution, a major risk event occurs where a key supplier goes bankrupt. The Project Manager reviews the Risk Register and finds that no response was planned for this severe threat. According to PRINCE2 7, what immediate action should be taken regarding risk management?
Hard106When integrating sustainability and ESG into the PRINCE2 Business Case practice, which factor represents the 'Social' (S) pillar?
Easy107During planning, the Project Manager is breaking down the product deliverables using product-based planning. Which PRINCE2 7 product-based planning step identifies the dependencies between products?
Medium108A PRINCE2 project is planning a complex engineering stage. The Project Manager needs to estimate the effort and resource requirements for creating each product. Which practice and planning technique should be utilized?
Medium109A PRINCE2 project is being set up in a matrix organization where resources are shared across multiple operational lines. The Project Manager needs to negotiate resource availability with functional managers. Where should the authority and channels for this negotiation be established?
Medium110Which TWO of the following roles form the core representation on a PRINCE2 Project Board alongside the Executive?
Easy111An organization requires all projects to apply the PRINCE2 Plans practice. A project manager is developing a Stage Plan for a complex software release. The project uses agile delivery for development but traditional gating for governance. How should the Plans practice be tailored?
Hard112A project manager is evaluating a risk with a high probability and severe negative impact on the project schedule. The organization decides to take out a specialized completion guarantee insurance policy with a third party. Which risk response is being applied?
Medium113In the PRINCE2 Issues practice, what are the three types of issues recognized by the method?
Easy114During project initiation, the Project Manager discovers that the Business Case benefits are not aligned with the corporate sustainability policy, which mandates a reduction in carbon emissions. What is the most appropriate action according to PRINCE2 7?
Easy115In the PRINCE2 Progress practice, what is the primary purpose of a Highlight Report?
Easy116In the Quality practice, who is responsible for defining the customer's quality expectations and acceptance criteria?
Easy117A PRINCE2 project is executing a stage plan. The Project Manager wants to schedule a quality review for a critical deliverable. According to the Quality practice, who should normally chair the quality review meeting?
Medium118A PRINCE2 project is applying the Plans practice. The Project Manager is tailoring the plans for a small, low-risk project and must decide which elements of the Plans practice to adapt. Which TWO of the following are appropriate tailoring actions for the Plans practice? (Choose two.)
Hard119Which TWO of the following statements about tolerances in the Progress practice are correct? (Choose two)
Medium120When establishing the Business Case practice in PRINCE2 7, what is the primary purpose of the 'Return on Investment' (ROI) calculation?
Easy121A project is implementing a major organizational transformation. The risk management team identifies a severe cultural resistance threat from middle management. The organization decides to appoint change champions across all departments and redesign performance incentives to align with the new vision. Which risk response is being implemented?
Hard122A project is subjected to a quality audit. The auditor notes that a product was signed off without checking one of the mandatory quality criteria specified in its Product Description. According to the Quality practice, what is the appropriate corrective action?
Hard123A PRINCE2 project includes a high-risk vendor supplying critical software modules. The Project Manager wants to ensure that the vendor's quality management processes align with the project's quality approach. Where should this integration be formally documented and controlled?
Hard124A project is operating under a commercial contract where the supplier is incentivized to deliver early. However, early delivery increases environmental resource consumption (ESG trade-off). The Project Board needs to evaluate this trade-off. Which practice is primarily responsible for balancing benefits, dis-benefits, and costs?
Hard125During project execution, an issue arises regarding a conflict between two functional managers over resource availability. The Project Manager logs the issue, analyzes its impact, and realizes it breaches the stage cost tolerance due to contractor overtime required to make up for lost time. What is the correct governance action?
Hard126During a quality audit, it is discovered that a product was accepted by the Senior User despite failing one of its quality criteria due to an oversight. How should this be handled within the Quality practice?
Medium127An organization is executing a high-risk engineering project under PRINCE2 7. The Executive wants to bypass the stage boundary reviews to speed up delivery, arguing that the Business Case is solid. According to PRINCE2, what is the impact of removing management stages?
HardOther domains
All PRINCE2-PRACTITIONER exam domains
Frequently asked questions
- What does the Practices domain cover on the PRINCE2-PRACTITIONER exam?
- You must be able to choose the right PRINCE2 practice output or role action for a scenario, not just define it. The single most important thing is to justify each decision against the principles and the project's tolerances and tailoring.
- How many questions are in this domain?
- This page lists all 127 Practices questions in the PRINCE2-PRACTITIONER question bank. The actual exam draws from this domain proportionally to its weighting in the official exam blueprint.
- What is the best way to practise this domain?
- Start with a short focused session (10 questions) to identify gaps, then work through explanations. Repeat with a longer session once the weak areas feel solid.
- Can I practise only Practices questions?
- Yes — the session launcher on this page filters questions to this domain only. Choose any session length for inline explanations and scoring.