A project is in the Starting up a Project (SU) process. The Project Manager has appointed the management team, prepared the project brief, and is now planning the initiation stage. What is the final activity the Project Manager must perform in SU before submitting the request to initiate the project to the Project Board?
Trap 1: Approving the detailed Stage Plans for the entire project life…
Detailed Stage Plans for the whole life cycle are not produced in Starting up a Project; only the initiation stage plan is prepared. The option is tempting because planning is an SU activity, but full stage plans are created later during Managing a Stage Boundary, not before the project is even initiated.
Trap 2: Authorizing the Project Management Plan.
The Project Management Plan is authorised by the Project Board during Initiating a Project, not in Starting up a Project. The option is tempting because the Project Manager does draft it, but SU ends with the project brief and request to initiate; authorisation of the plan follows the initiation stage.
Trap 3: Conducting a formal End Project Evaluation.
End Project Evaluation belongs to Closing a Project, so it cannot occur during Starting up a Project. It is tempting because SU does assess whether the project is worthwhile, but that judgement is captured in the Project Brief and the initiation request, not a closure-stage evaluation.
- A
Approving the detailed Stage Plans for the entire project life cycle.
Why it fails: Detailed Stage Plans for the whole life cycle are not produced in Starting up a Project; only the initiation stage plan is prepared. The option is tempting because planning is an SU activity, but full stage plans are created later during Managing a Stage Boundary, not before the project is even initiated.
- B
Planning the initiation and requesting authorization to initiate the project.
Planning the initiation stage and requesting project initiation authorisation is the final SU activity, producing the initiation stage plan and the request to the Project Board. It follows appointing the team and preparing the Project Brief.
- C
Authorizing the Project Management Plan.
Why it fails: The Project Management Plan is authorised by the Project Board during Initiating a Project, not in Starting up a Project. The option is tempting because the Project Manager does draft it, but SU ends with the project brief and request to initiate; authorisation of the plan follows the initiation stage.
- D
Conducting a formal End Project Evaluation.
Why it fails: End Project Evaluation belongs to Closing a Project, so it cannot occur during Starting up a Project. It is tempting because SU does assess whether the project is worthwhile, but that judgement is captured in the Project Brief and the initiation request, not a closure-stage evaluation.