A Project Manager in Controlling a Stage needs to handle a situation where a Work Package is forecasted to exceed its time tolerance. What is the immediate action the Project Manager should take regarding the Team Manager?
Trap 1: Issue an Exception Report directly to the Project Board
Team Managers and Project Managers do not raise Exception Reports directly to the Project Board; only the Project Manager raises Project-level Exception Reports to the Board.
Trap 2: Terminate the Work Package immediately
Tolerances are designed for management escalation, not automatic termination.
Trap 3: Adjust the Project Board's stage tolerances
The Project Manager has no authority to adjust Project Board tolerances.
- A
Instruct the Team Manager to submit an Exception Report
If a Work Package is forecast to exceed its tolerance, the Team Manager must raise an Exception Report to the Project Manager.
- B
Issue an Exception Report directly to the Project Board
Why wrong: Team Managers and Project Managers do not raise Exception Reports directly to the Project Board; only the Project Manager raises Project-level Exception Reports to the Board.
- C
Terminate the Work Package immediately
Why wrong: Tolerances are designed for management escalation, not automatic termination.
- D
Adjust the Project Board's stage tolerances
Why wrong: The Project Manager has no authority to adjust Project Board tolerances.