During a complex software integration project, key stakeholders from the operations department are resisting the proposed changes, citing fear of increased workloads. Following PRINCE2 7 stakeholder engagement guidance, what is the best initial action for the Project Manager?
Trap 1: Escalate the resistance immediately to the Project Board for…
Escalation should be a last resort; understanding and resolving resistance locally is preferred.
Trap 2: Remove the operations department representatives from the…
Removing key stakeholders creates a blind spot and guarantees future implementation failure.
Trap 3: Issue a formal directive reminding stakeholders of their…
Relying on contractual directives often entrenches resistance rather than building commitment.
- A
Escalate the resistance immediately to the Project Board for disciplinary review.
Why it fails: Escalation should be a last resort; understanding and resolving resistance locally is preferred.
- B
Remove the operations department representatives from the stakeholder register to prevent project delays.
Why it fails: Removing key stakeholders creates a blind spot and guarantees future implementation failure.
- C
Conduct targeted empathy and impact discussions to identify specific concerns and co-design mitigation strategies.
Co-designing solutions and addressing specific impact concerns builds genuine stakeholder commitment.
- D
Issue a formal directive reminding stakeholders of their contractual obligations to support the project.
Why it fails: Relying on contractual directives often entrenches resistance rather than building commitment.