A Project Board delegates day-to-day control of a project stage to the Project Manager, stepping in only when agreed limits for cost and time are forecast to be exceeded. Which PRINCE2 principle does this governance model represent?
Trap 1: Defined roles and responsibilities
Defined roles and responsibilities describes who is accountable for what, not the tolerance-based delegation of authority. It tempts because the Board and Project Manager roles are named, but the principle governing management by exception within agreed tolerances is manage by exception.
Trap 2: Tailor to suit the project
Tailoring concerns adapting PRINCE2's themes, processes and roles to the project's scale, environment and complexity; it does not describe delegated tolerance-based control. It would be the right principle when justifying why documentation, stage structure or role allocation is scaled down for a small project.
Trap 3: Manage by stages
Manage by Stages divides the project into manageable chunks with decision points, but the stem's defining feature is the Project Board setting tolerances and delegating within them, which is Manage by Exception. Manage by Stages would be correct if the question asked how the project is broken into reviewable sections.
- A
Defined roles and responsibilities
Why it fails: Defined roles and responsibilities describes who is accountable for what, not the tolerance-based delegation of authority. It tempts because the Board and Project Manager roles are named, but the principle governing management by exception within agreed tolerances is manage by exception.
- B
Tailor to suit the project
Why it fails: Tailoring concerns adapting PRINCE2's themes, processes and roles to the project's scale, environment and complexity; it does not describe delegated tolerance-based control. It would be the right principle when justifying why documentation, stage structure or role allocation is scaled down for a small project.
- C
Manage by exception
Manage by exception defines tolerances for cost and time, within which the Project Manager runs the stage without Board intervention; escalation occurs only when a forecast breach is imminent. This matches the stem's delegated day-to-day control with agreed limits, satisfying the principle's requirement for pre-defined boundaries and defined escalation points.
- D
Manage by stages
Why it fails: Manage by Stages divides the project into manageable chunks with decision points, but the stem's defining feature is the Project Board setting tolerances and delegating within them, which is Manage by Exception. Manage by Stages would be correct if the question asked how the project is broken into reviewable sections.