A Project Board in a high-risk construction project discovers that project tolerances for time are projected to be breached due to supply chain delays. The Project Manager immediately escalates this to the Board using an Exception Report. Which principle is being adhered to by the Project Board when they decide whether to set a new stage plan?
Trap 1: Focus on products
Focus on products centers on product descriptions and quality expectations, not tolerance escalation.
Trap 2: Defined roles and responsibilities
Although roles dictate who escalates, the actual governance mechanism of setting tolerances and thresholds belongs to manage by exception.
Trap 3: Continued business justification
While tolerance breaches may ultimately impact the business case, the immediate handling of breaches via escalation is managed by exception.
- A
Focus on products
Why it fails: Focus on products centers on product descriptions and quality expectations, not tolerance escalation.
- B
Defined roles and responsibilities
Why it fails: Although roles dictate who escalates, the actual governance mechanism of setting tolerances and thresholds belongs to manage by exception.
- C
Continued business justification
Why it fails: While tolerance breaches may ultimately impact the business case, the immediate handling of breaches via escalation is managed by exception.
- D
Manage by exception
The Board pre-agreed time tolerances and receives an Exception Report only once they are forecast to be breached, then decides on the response. Delegating authority within tolerances and escalating beyond them is precisely the Manage by exception principle in action.