During PI Planning, a Scrum Master reports that their team's draft plan includes several dependencies on another ART that is not present at the event. The team is unsure how to proceed. As a SAFe Product Manager, which TWO actions should you take to help the team? (Choose two.)
Documenting dependencies as program risks with clear owners is a core SAFe practice. It makes the issue visible, ensures accountability, and provides a mechanism for tracking resolution after the event. The owner can coordinate with the other ART, escalate if needed, and keep the team informed. This approach maintains transparency and increases the likelihood of timely resolution.
Why this answer
When dependencies involve an absent ART, the team should first document them as program risks with owners and, if a representative is available, coordinate directly to agree on a resolution. These actions maintain visibility, accountability, and collaboration, which are essential for managing cross-ART dependencies in SAFe.
Exam trap
The trap here is thinking that dependencies can be ignored or unilaterally rescheduled, when in fact they must be made visible and actively managed with the other party.