Courseiva
PI Execution →easyMultiple Choice

POPM PI Execution Practice Question

A Product Owner is preparing for the Iteration Review at the end of Iteration 4. The team has completed several stories that were not originally planned but add value to the current PI Objective. What is the most appropriate action for the Product Owner to take during the review?

⚠ Common exam trap

The trap here is believing that only planned stories should be demonstrated in the Iteration Review, when in fact all completed work that adds value should be shown.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Demonstrate the completed stories to stakeholders and explain how they contribute to the PI Objective, adjusting the team backlog as needed.

The Product Owner should demonstrate all completed stories during the Iteration Review, highlighting their contribution to the PI Objective. This transparency allows stakeholders to provide feedback and helps the team adjust the backlog. Excluding or postponing the demonstration would undermine the review's purpose of inspecting and adapting.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Ask the team to revert the unplanned stories to maintain adherence to the original iteration plan.

    Why it's wrong here

    Reverting completed work is wasteful and demotivating. The team likely completed the stories because they added value. The Product Owner should embrace the emergent work and assess its impact, not discard it to stick to a plan that may no longer be optimal.

  • ✗

    Postpone the demonstration of the unplanned stories to the System Demo to keep the Iteration Review focused on the iteration plan.

    Why it's wrong here

    The Iteration Review is the appropriate venue for demonstrating all completed stories from the iteration. Postponing to the System Demo delays feedback and may disrupt the demo's agenda. The Product Owner should use the Iteration Review to inspect and adapt immediately.

  • ✓

    Demonstrate the completed stories to stakeholders and explain how they contribute to the PI Objective, adjusting the team backlog as needed.

    Why this is correct

    The Iteration Review is an opportunity to showcase completed work and gather feedback. Demonstrating the unplanned stories and linking them to the PI Objective maintains transparency and allows stakeholders to assess value. The Product Owner can then adjust the backlog based on feedback, ensuring continued alignment.

  • ✗

    Only demonstrate the originally planned stories and exclude the unplanned ones to avoid confusing stakeholders.

    Why it's wrong here

    Excluding completed work from the review hides valuable progress and contradicts the principle of transparency. Stakeholders should see all completed stories, especially those that contribute to the PI Objective. Omitting them could lead to misinformed decisions and missed feedback opportunities.

About these practice questions

This POPM question is part of Courseiva's 336-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.