A Product Owner on an Agile Release Train (ART) notices that the team's backlog contains many small, technical items that do not clearly connect to any Feature. During Backlog Refinement, the team struggles to explain how these items deliver value to the customer. What is the most appropriate action for the Product Owner to take?

⚠ Common exam trap

The trap here is assuming that technical items must be removed or escalated, when the real issue is traceability to Features or Enablers.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Work with the team to map each backlog item to a Feature or an Enabler, ensuring traceability to program priorities.

The correct action is to link backlog items to Features or Enablers so that all work traces to program priorities. This preserves necessary technical work while making its value transparent. It also enables the Product Owner to prioritize based on business value and helps the team understand the purpose of each item.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Ask the Release Train Engineer to reassign the technical items to a separate system team.

    Why it's wrong here

    Reassigning items to a system team does not address the root cause: lack of traceability to Features. The Product Owner owns backlog content and should first clarify how each item supports program priorities. Involving the Release Train Engineer may be useful later, but it is not the immediate corrective action.

  • ✗

    Remove all technical items from the backlog and replace them with customer-facing Features.

    Why it's wrong here

    Removing all technical items is too extreme; enablers are legitimate backlog items that support future delivery. The problem is not their existence but their lack of connection to Features and value. The Product Owner should instead ensure each item is linked to a Feature or a clear enabler need, not eliminate them wholesale.

  • ✗

    Escalate to the Product Management team to rewrite all technical items as user stories.

    Why it's wrong here

    Escalation is unnecessary because the Product Owner is accountable for backlog clarity. Rewriting technical items as user stories may not be appropriate; some work is better expressed as Enablers. The Product Owner should facilitate mapping to Features or Enablers rather than shifting responsibility upward.

  • ✓

    Work with the team to map each backlog item to a Feature or an Enabler, ensuring traceability to program priorities.

    Why this is correct

    Mapping items to Features or Enablers restores alignment with program priorities and makes value explicit. It helps the team understand why the work matters and allows the Product Owner to prioritize based on business value. This approach keeps necessary technical work while ensuring it supports ART objectives.

About these practice questions

One of 336 original POPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.