Iteration Execution →hardMultiple Choice

POPM Iteration Execution Practice Question

Exhibit

PI Objective: Increase API throughput by 20%.
Story A (High Value): Optimize database query (8 story points).
Story B (Low Value): Refactor logging service (3 story points).
Team Velocity: 12 points.
Constraint: Database server upgrade delayed by 2 weeks.

Given the exhibit, what is the best strategy for the PO to manage the iteration?

⚠ Common exam trap

Candidates often try to force the original plan by waiting for the dependency, rather than adapting the backlog to maintain velocity and deliver value despite the external constraint.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Replace Story A with new, smaller tasks that do not rely on the upgrade.

The PO must adjust the plan based on the external constraint. Since the database upgrade is delayed, focusing on Story A may be impossible. By reprioritizing the backlog to focus on tasks that do not depend on the upgrade, the team maintains velocity and contributes to the PI objective. This highlights the importance of managing dependencies and adjusting plans dynamically during execution to maintain flow.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Keep Story A in the iteration and hope the server upgrade happens early.

    Why it's wrong here

    Ignoring a known constraint is a recipe for failure. Relying on hope rather than data leads to blocked work and reduced team morale. The PO should adapt the plan based on the reality of the situation to ensure the team can actually deliver value within the current sprint.

  • ✓

    Replace Story A with new, smaller tasks that do not rely on the upgrade.

    Why this is correct

    Replacing blocked work with achievable, high-value tasks is the core of effective iteration management. This ensures the team remains productive and continues to move toward PI objectives despite external blockers. It demonstrates the agility required to pivot when environmental factors prevent the completion of planned high-priority user stories.

  • ✗

    Ask the team to work on Story B and wait for the upgrade to start Story A.

    Why it's wrong here

    Focusing on low-value items while waiting for blockers leads to waste. The PO should instead look for other high-value items in the backlog that can be delivered independently. This ensures that the team’s effort is always aligned with the most important business goals during the iteration timeframe.

  • ✗

    Declare the iteration failed and start planning for the next one immediately.

    Why it's wrong here

    One blocked story does not mean an entire iteration failure. SAFe teams are expected to adapt. Declaring failure prematurely wastes valuable time that could be used for productive work. The PO should lead the team in re-planning the current iteration to salvage as much value as possible.

About these practice questions

Courseiva writes every POPM question from scratch — 336 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.