POPM Iteration Execution Practice Question
A Product Owner is preparing for the Iteration Review and wants to ensure the team demonstrates real progress to stakeholders. Which TWO actions best support this goal during Iteration Execution? (Choose two.)
⚠ Common exam trap
A common mix-up: candidates confuse the Iteration Review with a status meeting, which leads to slide decks and delayed demos instead of a working increment and stakeholder feedback.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Invite key stakeholders to the Iteration Review so they can provide feedback on the demonstrated increment.
The Iteration Review is most valuable when the team demonstrates a working increment that meets the Definition of Done and when stakeholders are present to give feedback. Slide decks, delayed reviews, and Product Owner-only presentations all weaken the inspect-and-adapt purpose. The Product Owner should facilitate the event so the right people see real progress and can help adapt the Team Backlog.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Ask the team to prepare a slide deck summarizing the iteration's velocity and defect trends instead of demonstrating the increment.
Why it's wrong here
The Iteration Review centers on demonstrating a working increment, not on slide-based reporting. Velocity and defect trends can be useful context, but they do not replace a live or recorded demonstration of the product. Replacing the demo with slides reduces transparency and stakeholder engagement. The Product Owner should keep the focus on the actual product behavior.
- ✗
Delay the Iteration Review until all committed stories are complete, even if it extends past the end of the iteration.
Why it's wrong here
Iteration Reviews occur at the end of the iteration on a regular cadence. Delaying the event until every story is complete undermines the inspect-and-adapt rhythm and can hide impediments. If some stories are incomplete, the team should still hold the review, show what is done, and discuss what was not completed. Regular cadence is more important than perfect completion.
- ✓
Invite key stakeholders to the Iteration Review so they can provide feedback on the demonstrated increment.
Why this is correct
Stakeholder feedback during the Iteration Review is essential for validating that the team is building the right thing. The Product Owner should invite the right participants so that feedback can inform backlog adaptation. This aligns with the purpose of the Iteration Review: to demonstrate the increment, gather feedback, and adjust the Team Backlog as needed.
- ✗
Have the Product Owner present the team's work alone so the team can continue development during the review.
Why it's wrong here
The team should present its own work so stakeholders can ask technical and functional questions directly to the people who built it. The Product Owner facilitates the review and connects feedback to the backlog, but does not replace the team's demonstration. Keeping the team in development during the review reduces transparency and misses valuable stakeholder interaction.
- ✓
Ensure each story meets the team's Definition of Done before it is presented in the Iteration Review.
Why this is correct
The Iteration Review is an inspect-and-adapt event for the working increment, so stories should meet the Definition of Done before they are shown. This gives stakeholders an honest view of progress and avoids presenting partially completed work as finished. The Product Owner supports this by clarifying acceptance criteria and confirming that the team's work is truly complete.
About these practice questions
Courseiva writes every POPM question from scratch — 336 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint
This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.