A Product Manager is preparing the Program Backlog for an upcoming PI Planning event. They want to ensure that features are ready for team estimation and planning. Which two actions should the Product Manager take to meet SAFe's feature readiness criteria? (Choose two.)
A clear benefit hypothesis is a core SAFe feature readiness criterion. It describes the expected business outcome and helps teams understand the value of the feature. Without it, teams may struggle to prioritize or may build something that doesn't deliver value. The Product Manager is responsible for defining the benefit hypothesis, which guides the ART's decisions during PI Planning and execution.
Why this answer
SAFe feature readiness requires a benefit hypothesis and acceptance criteria. These elements provide enough clarity for teams to estimate and understand value without over-specifying the solution. Assigning teams, pre-decomposing into stories, or requiring single-team completion are not readiness criteria and can undermine team autonomy and the collaborative nature of PI Planning.
Exam trap
The trap here is assuming that detailed decomposition or team assignment is part of feature readiness, when SAFe places those activities within PI Planning itself.