A stakeholder demands an urgent, unplanned feature be added to the current iteration. What should the Product Owner do?
⚠ Common exam trap
Candidates often choose 'immediately say no' or 'immediately add it to the iteration,' failing to perform the necessary impact analysis and team consultation required for agile planning.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Evaluate the impact and discuss with the team if they can accommodate it.
The PO must protect the iteration commitment while balancing business needs. By reviewing the potential impact on the current PI objectives, the PO can determine if the request is truly urgent and if it necessitates dropping other work. This ensures that the trade-offs are understood and intentional, maintaining the integrity of the team's plan while remaining responsive to the needs of the business and key stakeholders.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Agree to the request immediately to maintain good stakeholder relations.
Why it's wrong here
Agreeing without assessing the impact disrupts the team's flow and undermines the iteration commitment. This leads to a loss of predictability and trust. The PO must always perform a trade-off analysis before committing to new work, ensuring that all stakeholders are aware of the potential consequences to existing plans.
- ✗
Reject the request outright to ensure the iteration plan is never changed.
Why it's wrong here
Rigid adherence to a plan is contrary to Agile principles. The PO must be flexible and responsive to real business needs. If a request is truly critical, the PO should find a way to accommodate it by reprioritizing the backlog, while being transparent about the trade-offs involved.
- ✓
Evaluate the impact and discuss with the team if they can accommodate it.
Why this is correct
Evaluation is the professional way to handle change. By involving the team, the PO ensures that any changes to the iteration plan are realistic and achievable. This collaborative process allows for an informed decision that balances stakeholder value with the team's ability to maintain their current commitments.
- ✗
Direct the stakeholder to the Scrum Master to manage the change.
Why it's wrong here
The PO is responsible for the backlog and the product. Shifting this responsibility to the Scrum Master is an abdication of the PO's role. The PO must own the decision-making process for product priorities, as they are the bridge between the stakeholder's needs and the team's execution.
About these practice questions
One of 336 original POPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint
This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.