- A
Crash the schedule by adding resources to the dependent task.
Why wrong: This may not be effective without understanding the full impact.
- B
Escalate to the project management office for resource reallocation.
Why wrong: First attempt to resolve at the project level.
- C
Ask the team to find a workaround to bypass the dependency.
Why wrong: Workarounds may not be feasible; first analyze the situation.
- D
Add the dependency to the issue log, assess the impact on the schedule, and engage the other project manager.
Documentation and collaboration are key to resolving cross-project dependencies.
Quick Answer
The answer is to add the dependency to the issue log, assess the impact on the schedule, and engage the other project manager. This is correct because when an unidentified dependency issue surfaces during a sprint, the project manager must first formally log it as an issue and perform a thorough impact analysis on the critical path before taking any corrective action. On the PMP exam, this scenario tests your ability to apply the issue management process within a hybrid framework, where unplanned dependencies demand immediate documentation and stakeholder coordination rather than reactive escalation or premature solutioning. A common trap is jumping to a risk response or assuming the dependency can be managed without cross-project communication, but the correct sequence always begins with logging and analysis. Remember the mnemonic: Log, Analyze, Engage—never skip the impact assessment when facing an unidentified dependency.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
Your project is using a hybrid approach. During a sprint, the team realizes that a critical dependency from another project will not be ready on time, impacting the critical path. The dependency was not identified in the risk register. What is the BEST action?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"best"Why it matters: Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Add the dependency to the issue log, assess the impact on the schedule, and engage the other project manager.
The PM must first assess the impact and then manage the issue. Option A is correct because updating the issue log and analyzing impact is the proper first step. Option B is reactive; Option C assumes a solution without analysis; Option D ignores governance.
Key principle: NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Crash the schedule by adding resources to the dependent task.
Why it's wrong here
This may not be effective without understanding the full impact.
- ✗
Escalate to the project management office for resource reallocation.
Why it's wrong here
First attempt to resolve at the project level.
- ✗
Ask the team to find a workaround to bypass the dependency.
Why it's wrong here
Workarounds may not be feasible; first analyze the situation.
- ✓
Add the dependency to the issue log, assess the impact on the schedule, and engage the other project manager.
Why this is correct
Documentation and collaboration are key to resolving cross-project dependencies.
Clue confirmation
The clue word "best" in the question point toward this answer.
Related concept
Static NAT maps one inside address to one outside address.
Common exam traps
Common exam trap: NAT rules depend on direction and matching traffic
NAT is not only about the public address. The inside/outside interface roles and the ACL or rule that matches traffic are just as important.
Trap categories for this question
Scenario analysis trap
Workarounds may not be feasible; first analyze the situation.
Detailed technical explanation
How to think about this question
NAT questions usually test address translation, overload/PAT behaviour, static mappings and whether the right traffic is being translated. Read the interface direction and address terms carefully.
KKey Concepts to Remember
- Static NAT maps one inside address to one outside address.
- PAT allows many inside hosts to share one public address using ports.
- Inside local and inside global describe the private and translated addresses.
- NAT ACLs identify traffic for translation, not always security filtering.
TExam Day Tips
- Identify inside and outside interfaces first.
- Check whether the scenario needs static NAT, dynamic NAT or PAT.
- Do not confuse NAT matching ACLs with normal packet-filtering intent.
Key takeaway
NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Static NAT maps one inside address to one outside address..
What is the correct answer to this question?
The correct answer is: Add the dependency to the issue log, assess the impact on the schedule, and engage the other project manager. — The PM must first assess the impact and then manage the issue. Option A is correct because updating the issue log and analyzing impact is the proper first step. Option B is reactive; Option C assumes a solution without analysis; Option D ignores governance.
What should I do if I get this PMP question wrong?
Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.
Are there clue words in this question I should notice?
Yes — watch for: "best". Signals that multiple options may be partially correct. Choose the option that most directly solves the exact problem described, not the one that sounds most complete.
What is the key concept behind this question?
Static NAT maps one inside address to one outside address.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PMP practice questions
- A project manager is leading a digital transformation initiative. Midway through the project, a new regulation is introd…
- Order the steps for closing a project or phase.
- Sequence the steps for performing a qualitative risk analysis.
- Arrange the steps for controlling project changes.
- Order the steps for performing project quality assurance.
- Order the steps for creating a Work Breakdown Structure (WBS).
Last reviewed: Jun 21, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.