Question 802 of 892
Process — Managing Technical AspectseasyMultiple ChoiceObjective-mapped

Quick Answer

The answer is to estimate activity resources. In the schedule development process order, after defining activities and sequencing them, you must determine what people, equipment, and materials are needed for each task before you can realistically estimate how long those tasks will take. This step is critical because resource availability directly constrains activity durations—without knowing who or what is available, any duration estimate is just a guess. On the PMP exam, this tests your understanding of the logical flow in the PMBOK Guide’s schedule management process, where a common trap is jumping straight to estimating durations or creating the schedule. Remember the mnemonic “D-S-R-D” for the core sequence: Define, Sequence, Resources, Durations. This order ensures your schedule is built on a foundation of known resource constraints, not wishful thinking.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is developing the project schedule. After defining activities and sequencing them, what is the next step in the schedule development process?

Question 1easymultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Estimate activity resources

In the schedule development process, after defining activities and sequencing them, the next step is to estimate the resources required for each activity (option A). This is because resource availability and constraints directly impact activity durations, and you must know what resources are available before you can estimate how long each activity will take. The PMBOK Guide's schedule management process follows the order: Plan Schedule Management → Define Activities → Sequence Activities → Estimate Activity Resources → Estimate Activity Durations → Develop Schedule.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Estimate activity resources

    Why this is correct

    Resource estimation is the logical next step after sequencing, per PMBOK process flow.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Estimate activity durations

    Why it's wrong here

    Duration estimation requires resource estimates first.

  • Estimate costs

    Why it's wrong here

    Cost estimation typically follows duration estimation.

  • Develop the schedule baseline

    Why it's wrong here

    The baseline is developed after duration estimates and schedule model analysis.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PMI often tests the order of processes in the schedule development sequence, and the trap here is that candidates mistakenly think duration estimation comes immediately after sequencing, overlooking the prerequisite resource estimation step.

Detailed technical explanation

How to think about this question

The Estimate Activity Resources process involves determining the type, quantity, and characteristics of resources (people, equipment, materials) needed for each activity. This is critical because resource calendars, availability, and skill levels directly influence duration estimates—for example, assigning a junior developer vs. a senior developer to the same task can change the duration estimate by 50% or more. In practice, resource leveling and resource smoothing techniques are applied later in the Develop Schedule process to resolve overallocation conflicts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Estimate activity resources — In the schedule development process, after defining activities and sequencing them, the next step is to estimate the resources required for each activity (option A). This is because resource availability and constraints directly impact activity durations, and you must know what resources are available before you can estimate how long each activity will take. The PMBOK Guide's schedule management process follows the order: Plan Schedule Management → Define Activities → Sequence Activities → Estimate Activity Resources → Estimate Activity Durations → Develop Schedule.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.