- A
Crash the schedule by adding more resources to both tasks.
Why wrong: Crashing adds cost and may not resolve the conflict if resources are specialized.
- B
Hire additional contractors to perform one of the tasks.
Why wrong: While possible, this may not be the first action and is not always feasible.
- C
Remove one task from the schedule to prioritize the other.
Why wrong: Removing tasks is a drastic measure; other options should be explored first.
- D
Adjust task dependencies to sequence the tasks if possible.
If the tasks can be performed sequentially, adjusting dependencies can resolve the conflict.
- E
Apply resource leveling to smooth the resource demand.
Resource leveling can shift tasks to resolve conflicts without adding resources.
Quick Answer
The answer is to apply resource leveling and adjust dependencies. Resource leveling is the correct first action because it directly addresses resource constraints by shifting the schedule to prevent over-allocation, smoothing demand for the specialized resource without adding new team members. Adjusting dependencies, such as adding finish-to-start relationships or lag time, then sequences the two critical tasks so they no longer run concurrently, resolving the conflict through schedule logic rather than cost. On the PMP exam, this tests your understanding of the Resource Management and Schedule Management knowledge areas, where the common trap is to immediately choose “add resources” or “fast track” without first considering schedule adjustments. A helpful memory tip is to think “Level first, then link”—level the resource load, then adjust dependency links to keep tasks from overlapping.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
You are managing a project that is experiencing resource constraints. Two critical tasks are scheduled concurrently but require the same specialized resource. Which TWO actions should the project manager consider to resolve this conflict?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Adjust task dependencies to sequence the tasks if possible.
Resource leveling adjusts the schedule to resolve resource over-allocation, and adjusting dependencies can help sequence tasks. Outsourcing or adding resources are alternative options, but the two best are resource leveling and adjusting dependencies.
Key principle: NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Crash the schedule by adding more resources to both tasks.
Why it's wrong here
Crashing adds cost and may not resolve the conflict if resources are specialized.
- ✗
Hire additional contractors to perform one of the tasks.
Why it's wrong here
While possible, this may not be the first action and is not always feasible.
- ✗
Remove one task from the schedule to prioritize the other.
Why it's wrong here
Removing tasks is a drastic measure; other options should be explored first.
- ✓
Adjust task dependencies to sequence the tasks if possible.
Why this is correct
If the tasks can be performed sequentially, adjusting dependencies can resolve the conflict.
Related concept
Static NAT maps one inside address to one outside address.
- ✓
Apply resource leveling to smooth the resource demand.
Why this is correct
Resource leveling can shift tasks to resolve conflicts without adding resources.
Related concept
Static NAT maps one inside address to one outside address.
Common exam traps
Common exam trap: NAT rules depend on direction and matching traffic
NAT is not only about the public address. The inside/outside interface roles and the ACL or rule that matches traffic are just as important.
Detailed technical explanation
How to think about this question
NAT questions usually test address translation, overload/PAT behaviour, static mappings and whether the right traffic is being translated. Read the interface direction and address terms carefully.
KKey Concepts to Remember
- Static NAT maps one inside address to one outside address.
- PAT allows many inside hosts to share one public address using ports.
- Inside local and inside global describe the private and translated addresses.
- NAT ACLs identify traffic for translation, not always security filtering.
TExam Day Tips
- Identify inside and outside interfaces first.
- Check whether the scenario needs static NAT, dynamic NAT or PAT.
- Do not confuse NAT matching ACLs with normal packet-filtering intent.
Key takeaway
NAT direction and interface roles matter as much as the IP address mapping. Inside/outside designation controls which traffic is translated.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Static NAT maps one inside address to one outside address..
What is the correct answer to this question?
The correct answer is: Adjust task dependencies to sequence the tasks if possible. — Resource leveling adjusts the schedule to resolve resource over-allocation, and adjusting dependencies can help sequence tasks. Outsourcing or adding resources are alternative options, but the two best are resource leveling and adjusting dependencies.
What should I do if I get this PMP question wrong?
Review the four NAT address types (inside local, inside global, outside local, outside global), PAT port overload, and static vs dynamic NAT use cases. Then practise related PMP NAT questions on configuration and troubleshooting.
What is the key concept behind this question?
Static NAT maps one inside address to one outside address.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PMP practice questions
- A project manager is leading a digital transformation initiative. Midway through the project, a new regulation is introd…
- Order the steps for closing a project or phase.
- Sequence the steps for performing a qualitative risk analysis.
- Arrange the steps for controlling project changes.
- Order the steps for performing project quality assurance.
- Order the steps for creating a Work Breakdown Structure (WBS).
Last reviewed: Jun 21, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.