- A
Review the project resource management plan and update the staffing requirements.
The plan outlines roles and requirements, guiding the search.
- B
Immediately hire a replacement with similar skills.
Why wrong: Hiring without analysis may result in a poor fit.
- C
Escalate the issue to the project sponsor for approval to hire.
Why wrong: The project manager typically has authority to hire within budget.
- D
Ask the team to redistribute the workload.
Why wrong: This is a temporary measure; a replacement is needed.
Quick Answer
The answer is to review the project resource management plan and update the staffing requirements. This is the correct first step because the resource management plan is the foundational document that outlines how team members are acquired, developed, and replaced; it contains pre-defined staffing requirements, role descriptions, and acquisition methods such as hiring or internal reassignment. On the PMP exam, this scenario tests your understanding of the Plan Resource Management process and the importance of following documented procedures rather than jumping to ad-hoc solutions like immediately posting a job or reassigning work—a common trap where candidates confuse urgency with process. When a key team member resigns, the project manager must first consult the plan to ensure any replacement aligns with the project’s budget, schedule, and skill needs, avoiding disruption to technical execution. Memory tip: think “Plan before you act”—the resource management plan is your roadmap for staffing changes, so always check it first.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
During project execution, a key team member resigns. The project manager needs to fill the position quickly. What is the FIRST step the project manager should take?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Review the project resource management plan and update the staffing requirements.
The project resource management plan contains the procedures for acquiring, developing, and managing the project team. When a key team member resigns, the first step is to review this plan to identify the pre-defined staffing requirements, roles, and acquisition methods (e.g., hiring, reassignment) before taking any action. This ensures alignment with the project's resource constraints and avoids ad-hoc decisions that could disrupt the project's technical execution.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Review the project resource management plan and update the staffing requirements.
Why this is correct
The plan outlines roles and requirements, guiding the search.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Immediately hire a replacement with similar skills.
Why it's wrong here
Hiring without analysis may result in a poor fit.
- ✗
Escalate the issue to the project sponsor for approval to hire.
Why it's wrong here
The project manager typically has authority to hire within budget.
- ✗
Ask the team to redistribute the workload.
Why it's wrong here
This is a temporary measure; a replacement is needed.
Common exam traps
Common exam trap: answer the scenario, not the keyword
PMI often tests the misconception that the project manager should immediately escalate or take reactive action (like hiring or redistributing work) rather than first consulting the project management plan, which is the authoritative source for process-driven decisions.
Detailed technical explanation
How to think about this question
The project resource management plan is a component of the project management plan that details how resources are estimated, acquired, managed, and controlled. It includes resource calendars, roles and responsibilities (via a RACI matrix), and staffing management procedures such as pre-approval for hires or use of contingent staff. In practice, a project manager should first check if the plan allows for backfilling from a pre-qualified pool or if a change request is needed to adjust the staffing requirements, ensuring compliance with organizational process assets and enterprise environmental factors.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Review the project resource management plan and update the staffing requirements. — The project resource management plan contains the procedures for acquiring, developing, and managing the project team. When a key team member resigns, the first step is to review this plan to identify the pre-defined staffing requirements, roles, and acquisition methods (e.g., hiring, reassignment) before taking any action. This ensures alignment with the project's resource constraints and avoids ad-hoc decisions that could disrupt the project's technical execution.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PMP practice questions
- A project manager is leading a digital transformation initiative. Midway through the project, a new regulation is introd…
- Order the steps for closing a project or phase.
- Sequence the steps for performing a qualitative risk analysis.
- Arrange the steps for controlling project changes.
- Order the steps for performing project quality assurance.
- Order the steps for creating a Work Breakdown Structure (WBS).
Last reviewed: Jun 30, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.