Question 811 of 892
Process — Managing Technical AspectshardMultiple SelectObjective-mapped

Quick Answer

The answer is stakeholder feedback, along with regulatory changes and scope errors, as three of the most common causes of project change requests. Stakeholder feedback drives changes because evolving needs, new insights, or overlooked requirements from clients or sponsors often surface after the project baseline is set, forcing adjustments to deliverables or priorities. Regulatory changes, such as new GDPR or HIPAA compliance mandates, are equally common because external laws can require immediate scope modifications to avoid legal penalties. On the PMP exam, this concept tests your understanding of the integrated change control process and how change requests originate from both internal and external sources. A common trap is assuming only technical issues trigger changes, but the exam emphasizes that stakeholder input and legal shifts are frequent, legitimate triggers. Memory tip: think “SRS” for Stakeholder feedback, Regulatory shifts, and Scope creep—the three silent disruptors that always demand a formal change request.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Match the stated requirement to the specific cloud service, access model, or configuration option — many options are valid in isolation but not for this scenario. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which THREE of the following are common causes of project change requests?

Question 1hardmulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Regulatory changes

Regulatory changes are a common cause of project change requests because new laws or compliance requirements (e.g., GDPR, HIPAA, or PCI DSS) can mandate modifications to project scope, deliverables, or processes. These external mandates often require immediate adjustments to avoid legal penalties, making them a frequent trigger for formal change requests in technology projects.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Regulatory changes

    Why this is correct

    New regulations may require changes to project deliverables.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Team member vacation

    Why it's wrong here

    Vacations are planned and do not typically result in change requests.

  • Budget surplus

    Why it's wrong here

    A surplus may allow changes but is not a direct cause.

  • Scope creep

    Why this is correct

    Uncontrolled additions to scope often trigger change requests.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Stakeholder feedback

    Why this is correct

    Stakeholder input often leads to change requests.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may confuse operational issues like team member vacation or budget surplus with legitimate triggers for formal change requests, but the PMP exam emphasizes that change requests must stem from external or internal factors that alter the project baseline, not routine resource or financial adjustments.

Detailed technical explanation

How to think about this question

In project management, change requests are formal proposals to modify baselines (scope, schedule, cost). Regulatory changes often require updates to system architecture or data handling procedures, such as implementing encryption standards (e.g., AES-256) or access controls (e.g., RBAC) to meet new compliance rules. Scope creep, another common cause, occurs when uncontrolled additions to requirements are made without formal change control, often due to vague initial specifications or evolving stakeholder needs.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Regulatory changes — Regulatory changes are a common cause of project change requests because new laws or compliance requirements (e.g., GDPR, HIPAA, or PCI DSS) can mandate modifications to project scope, deliverables, or processes. These external mandates often require immediate adjustments to avoid legal penalties, making them a frequent trigger for formal change requests in technology projects.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.