- A
Accept the change and update the project management plan
Why wrong: Accepting without formal approval violates change control procedures.
- B
Reject the change because it is out of scope
Why wrong: Rejection should be done by the CCB, not the project manager alone.
- C
Analyze alternatives to minimize the impact
Why wrong: Analysis should be part of the change request evaluation, not the first step.
- D
Submit a change request to the change control board
A formal change request is required to evaluate and approve the change.
Quick Answer
The answer is to submit a change request to the change control board. This is the correct first step because the PMBOK Guide’s integrated change control process mandates that any change impacting scope, schedule, and cost must be formally documented and evaluated by the CCB before implementation. The project manager’s role is to assess the impact and then submit the request, not to approve or reject it unilaterally. On the PMP exam, this scenario tests your understanding of the change control process and the project manager’s authority boundaries; a common trap is choosing to “reject the change” or “negotiate with the stakeholder” first, which bypasses the governance framework. Remember the memory tip: “Document before you decide”—always log the change request before any other action, even if the impact seems clear.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
During project execution, a key stakeholder requests a new feature that is not in the scope. The project manager determines that the change will impact the schedule by 3 weeks and increase costs by $50,000. What should the project manager do first?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Submit a change request to the change control board
The correct first step when a change request impacts scope, schedule, and cost is to submit a formal change request to the change control board (CCB) for evaluation. This aligns with the PMBOK Guide's integrated change control process, which requires all changes to be documented and reviewed before any action is taken. The project manager must not accept or reject the change unilaterally, as that would bypass the established governance framework.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Accept the change and update the project management plan
Why it's wrong here
Accepting without formal approval violates change control procedures.
- ✗
Reject the change because it is out of scope
Why it's wrong here
Rejection should be done by the CCB, not the project manager alone.
- ✗
Analyze alternatives to minimize the impact
Why it's wrong here
Analysis should be part of the change request evaluation, not the first step.
- ✓
Submit a change request to the change control board
Why this is correct
A formal change request is required to evaluate and approve the change.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often think the project manager should immediately analyze alternatives (Option C) to minimize impact, but the PMP exam emphasizes that the first step is always to submit a formal change request to the CCB, not to preemptively analyze or decide on the change.
Detailed technical explanation
How to think about this question
In the PMBOK Guide, the Perform Integrated Change Control process requires that all change requests be documented in a change log and reviewed by the CCB, which has the authority to approve or reject changes that impact baselines. The project manager's role is to facilitate the process, not to make unilateral decisions on scope changes. A real-world scenario where this matters is when a key stakeholder requests a feature that could be implemented via a workaround; the CCB might approve a less impactful alternative after formal review, but the project manager must first submit the request to initiate that analysis.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Submit a change request to the change control board — The correct first step when a change request impacts scope, schedule, and cost is to submit a formal change request to the change control board (CCB) for evaluation. This aligns with the PMBOK Guide's integrated change control process, which requires all changes to be documented and reviewed before any action is taken. The project manager must not accept or reject the change unilaterally, as that would bypass the established governance framework.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PMP practice questions
- A project manager is leading a digital transformation initiative. Midway through the project, a new regulation is introd…
- Order the steps for closing a project or phase.
- Sequence the steps for performing a qualitative risk analysis.
- Arrange the steps for controlling project changes.
- Order the steps for performing project quality assurance.
- Order the steps for creating a Work Breakdown Structure (WBS).
Last reviewed: Jun 11, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.