Courseiva

CCNA Overview of PRINCE2 and the project environment Questions

74 of 158 questions · Page 2/3 · Overview of PRINCE2 and the project environment · Answers revealed

76
MCQeasy

Which of the following is a characteristic of a project according to PRINCE2?

A.Repetitive activities
B.Ongoing operations
C.Temporary organization
D.Functional management
AnswerC
77
MCQhard

In PRINCE2, which role is responsible for providing independent assurance that the project is being managed correctly?

A.Project Assurance
B.Team Manager
C.Project Support
D.Project Manager
AnswerA

Project Assurance is independent and checks compliance.

Why this answer

Project Assurance is an independent role, separate from Project Support.

78
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To define the project scope and create the Project Initiation Documentation
B.To authorize the initiation of the project
C.To enable the Project Board to review the current stage's performance and approve the next Stage Plan
D.To control the day-to-day work of the project and manage issues
AnswerC

SB provides a control point between stages.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with the information needed to review the current stage's performance, approve the next Stage Plan, and update the Business Case and Project Plan. This ensures that the project remains viable and aligned with business objectives before committing further resources.

Exam trap

A common mistake in PRINCE2 is to confuse the Managing a Stage Boundary process (stage-end review and planning) with the Controlling a Stage process (day-to-day management), leading candidates to select an incorrect answer that describes day-to-day control.

How to eliminate wrong answers

Option A is wrong because defining the project scope and creating the Project Initiation Documentation is the purpose of the Initiating a Project process, not Managing a Stage Boundary. Option B is wrong because authorizing the initiation of the project is the purpose of the Directing a Project process, specifically the 'Authorize Initiation' activity. Option D is wrong because controlling the day-to-day work of the project and managing issues is the purpose of the Controlling a Stage process, which handles work packages and issue resolution within a stage.

79
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Assurance
B.Senior User
C.Project Manager
D.Executive (Senior Responsible Owner)
AnswerD
80
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To initiate the project
B.To close the project
C.To provide the Project Board with information to review the current stage and approve the next stage
D.To manage the day-to-day activities of the team
AnswerC

Correct.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve the next Stage Plan, and update the Business Case and Project Plan. It ensures that the project only proceeds to the next stage if it remains viable and aligned with business objectives.

Exam trap

A common mistake in the PRINCE2 Foundation exam is confusing the Managing a Stage Boundary process with Managing Product Delivery or Closing a Project. Candidates often think it involves day-to-day work or final closure, but its purpose is to review the current stage and obtain approval for the next.

How to eliminate wrong answers

Option A is wrong because initiating the project is the purpose of the Starting Up a Project and Initiating a Project processes, not Managing a Stage Boundary. Option B is wrong because closing the project is the purpose of the Closing a Project process, which handles project handover and post-project review. Option D is wrong because managing day-to-day team activities is the responsibility of the Managing Product Delivery process, which focuses on work package acceptance, execution, and delivery.

81
MCQmedium

A project is forecast to exceed its cost tolerance at the project level. What should the Project Manager do first?

A.Escalate to the Programme Manager
B.Revise the Project Plan and continue
C.Raise an Exception Report to the Project Board
D.Close the project
AnswerC

This is the correct action per PRINCE2's management by exception.

Why this answer

When a project is forecast to exceed its cost tolerance at the project level, the Project Manager must first escalate the deviation to the Project Board by raising an Exception Report. This is because the Project Board holds the authority to approve changes to tolerances or authorize corrective actions, and the Project Manager cannot unilaterally revise the plan or close the project. The Exception Report provides the Board with the necessary information to make an informed decision on how to proceed.

Exam trap

The trap here is that candidates often confuse escalation to the Programme Manager (Option A) with the correct escalation to the Project Board, or mistakenly believe the Project Manager can autonomously revise the plan (Option B) when the forecast breach requires Board-level decision-making.

How to eliminate wrong answers

Option A is wrong because the Project Manager escalates to the Project Board, not the Programme Manager; the Programme Manager would only be involved if the project is part of a programme and the Board decides to escalate further. Option B is wrong because revising the Project Plan and continuing without Board approval violates the management by exception principle; the Project Manager must first report the forecast deviation before any plan changes. Option D is wrong because closing the project is a premature action; the Project Board must decide whether to close, continue with revised tolerances, or take other corrective measures based on the Exception Report.

82
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Stage Plan
B.Business Case
C.Project Initiation Documentation
D.Project Brief
AnswerC

The Initiating a Project process produces the Project Initiation Documentation (PID) as its mandated output, satisfying the question’s requirement for the key deliverable that formally defines the project’s scope, business justification, and management controls before proceeding. The PID consolidates the Project Brief, Business Case, and detailed plans into a single baseline, which the process explicitly requires to obtain authorisation from the Project Board.

Why this answer

The PID is the key output that provides the basis for managing the project.

83
Multi-Selectmedium

Which TWO of the following are characteristics of a project as defined by PRINCE2?

Select 2 answers
A.It delivers unique products
B.It delivers business as usual
C.It is temporary
D.It has no defined end date
E.It involves a permanent team
AnswersA, C

Correct. Projects create unique outputs.

Why this answer

PRINCE2 defines a project as a temporary organization created to deliver one or more business products according to an agreed business case. The key characteristic is that the products delivered are unique—meaning they are not routine or repetitive outputs—which distinguishes a project from ongoing operations. This uniqueness applies to the product itself, the context, or the team composition, even if similar products have been built before.

Exam trap

The trap here is that candidates confuse 'project' characteristics with 'operational' characteristics, especially by thinking a project can have a permanent team or no end date, which PRINCE2 explicitly rejects in favor of temporary structures and defined timelines.

84
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To plan the next project stage
B.To provide the Project Board with information to assess the viability of the project
C.To authorize work packages
D.To close the project
AnswerB

Correct; it enables the Board to decide whether to continue.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information—such as the Stage Plan for the next stage, an updated Business Case, and a Lessons Report—to assess whether the project remains viable and should proceed. This process occurs at the end of each management stage (except the final one) and enables the board to make a informed 'go/no-go' decision based on current performance and forecasts.

Exam trap

PRINCE2 often tests the distinction between the activities within a process and the overall purpose of that process, so candidates mistakenly choose 'plan the next stage' because it is a visible activity, but the core purpose is to enable the Project Board's viability assessment.

How to eliminate wrong answers

Option A is wrong because planning the next project stage is a key activity within the Managing a Stage Boundary process, but it is not the purpose; the purpose is to enable the Project Board to assess viability. Option C is wrong because authorizing work packages is the responsibility of the Managing Product Delivery process, not the Managing a Stage Boundary process. Option D is wrong because closing the project is the purpose of the Closing a Project process, which occurs after the final stage, not during stage boundaries.

85
Multi-Selecthard

Which THREE of the following are characteristics of a project according to PRINCE2?

Select 3 answers
A.It creates a unique product
B.It is a temporary organization
C.It involves a mix of business, user, and supplier stakeholders
D.It produces repetitive outputs
E.It must be delivered within a fixed budget
AnswersA, B, C

The output of a project is unique.

Why this answer

PRINCE2 defines a project as a temporary organization created to deliver one or more business products according to an agreed business case. The uniqueness of the product is a core characteristic, meaning the output is not a routine or repetitive item but something new or different, which distinguishes a project from ongoing operations.

Exam trap

PeopleCert often tests the misconception that a project must have a fixed budget, but PRINCE2 uses tolerances to allow controlled flexibility, so candidates should not confuse a project's constraints with rigid limits.

86
MCQhard

What is the primary purpose of the 'Manage by exception' principle?

A.To delegate authority to the Project Manager within agreed tolerances
B.To ensure the Project Manager is held accountable for all project decisions
C.To require the Project Board to approve all changes
D.To involve stakeholders at every stage of the project
AnswerA

Correct. It sets tolerances and escalates only when breached.

Why this answer

Manage by exception means that the Project Board only needs to be involved when tolerances are forecast to be exceeded. This frees them to focus on strategic decisions.

87
MCQmedium

What is the difference between Project Assurance and Project Support?

A.Project Assurance is only required for large projects; Project Support is always required
B.There is no difference; they are the same role
C.Project Assurance provides an independent view; Project Support provides administrative services
D.Project Assurance is performed by the Project Manager; Project Support is performed by the Team Manager
AnswerC

Correct. Assurance is independent; Support is administrative.

Why this answer

PRINCE2 clearly distinguishes Project Assurance as an independent, objective check on the project's adherence to management controls and standards, while Project Support provides administrative and clerical services such as planning tools, filing, and information management. This separation ensures that assurance remains unbiased and not influenced by the day-to-day support activities.

Exam trap

The trap here is that candidates often confuse 'assurance' with 'support' because both sound like helping functions, but PRINCE2 specifically tests the independence of assurance versus the administrative nature of support.

How to eliminate wrong answers

Option A is wrong because Project Assurance is required on all PRINCE2 projects, not just large ones, and Project Support is optional, not always required. Option B is wrong because Project Assurance and Project Support are distinct roles with different responsibilities; they are not the same. Option D is wrong because Project Assurance is performed by someone independent of the Project Manager (often a senior stakeholder or a separate assurance team), not by the Project Manager, and Project Support is typically performed by a project support office or administrator, not by the Team Manager.

88
MCQeasy

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is always approved; an Off-specification is always rejected
B.An Off-specification is raised by the Project Board; a Request for Change is raised by the Project Manager
C.A Request for Change is for a proposed modification; an Off-specification is a product that does not meet its specification
D.They are the same thing
AnswerC
89
MCQmedium

Which statement about the Project Assurance role is true?

A.Project Assurance is independent of the Project Manager and provides checks to the Project Board
B.Project Assurance is a full-time role on every project
C.Project Assurance is part of Project Support
D.Project Assurance is responsible for providing administrative support to the Project Manager
AnswerA

Project Assurance is independent and reports to the Project Board.

Why this answer

The PRINCE2 methodology defines Project Assurance as an independent check on the project's progress, performed on behalf of the Project Board. It is separate from the Project Manager's day-to-day management and ensures that the project remains viable, compliant with standards, and aligned with business objectives. This independence is critical for objective oversight and is a core principle of PRINCE2's governance model.

Exam trap

The trap here is confusing Project Assurance with Project Support, as both roles involve oversight or assistance, but PRINCE2 explicitly separates them: Assurance is independent and reports to the Board, while Support is administrative and reports to the Project Manager.

How to eliminate wrong answers

Option B is wrong because Project Assurance is not a full-time role on every project; it can be performed part-time or by multiple individuals, depending on the project's scale and complexity. Option C is wrong because Project Assurance is distinct from Project Support; Project Support provides administrative and clerical services, while Assurance provides independent oversight and checks. Option D is wrong because Project Assurance is not responsible for administrative support; that is the function of Project Support, which assists the Project Manager with tasks like filing, scheduling, and maintaining records.

90
MCQhard

What is the difference between tailoring and embedding PRINCE2?

A.Tailoring adapts PRINCE2 to the project; embedding integrates PRINCE2 into the organization
B.Tailoring is done by the Project Board; embedding is done by the Project Manager
C.Tailoring is used for large projects; embedding is for small projects
D.There is no difference; the terms are interchangeable
AnswerA

Correct distinction.

Why this answer

Tailoring adapts PRINCE2 to the project's environment; embedding is integrating it into the organization's culture.

91
MCQmedium

A project is using PRINCE2. The Senior User identifies a new requirement that was not in the original scope. What should the Project Manager do first?

A.Immediately update the Project Plan to include the new requirement
B.Ask the Senior User to raise a change request with the Change Authority
C.Log it as an issue and assess the impact on the project
D.Reject the requirement because it is out of scope
AnswerC

All requests for change are logged as issues initially.

Why this answer

The Project Manager should log the new requirement as an issue (which includes change requests) and then assess its impact on the project objectives, scope, and tolerances. Only after this assessment can a decision be made on how to proceed. Option C is correct because it follows the PRINCE2 principle of managing by stages and the recommended issue handling procedure.

Option A is incorrect because immediately updating the Project Plan without impact assessment violates controlled management. Option B is premature because the change authority is not involved until the issue is assessed and escalated if necessary. Option D is incorrect because rejecting out-of-hand ignores the requirement without due process.

92
Multi-Selecthard

Which THREE of the following are reasons why projects fail, which PRINCE2 aims to address?

Select 3 answers
A.Poor planning
B.Too much change control
C.Lack of HR policies
D.Insufficient stakeholder involvement
E.Lack of clear objectives
AnswersA, D, E

PRINCE2 provides structured planning processes.

Why this answer

PRINCE2 addresses common project failure reasons such as lack of clear objectives, insufficient stakeholder involvement, and poor planning. Options A, D, and E are correct. Option B (too much change control) is not a typical failure reason; PRINCE2 includes change control to manage changes effectively.

Option C (lack of HR policies) is not a focus of PRINCE2.

93
Multi-Selectmedium

Which TWO of the following are benefits of adopting PRINCE2?

Select 2 answers
A.Improved communication and control
B.Increased visibility of the project
C.Eliminates the need for change control
D.Guarantees project success
E.Reduces project duration
AnswersA, B

PRINCE2 defines roles and reporting.

Why this answer

PRINCE2 provides a structured framework with defined roles, responsibilities, and management products (e.g., Highlight Reports, Issue Reports) that standardize communication channels and enable better control through stage-gate approvals and exception management. This reduces ambiguity and ensures stakeholders receive timely, relevant information.

Exam trap

The trap here is that candidates often confuse ‘improved control’ with ‘guaranteed success’ or assume PRINCE2’s prescriptive nature eliminates all project risks, when in fact it only provides a disciplined framework to manage them.

94
MCQhard

What is the difference between the Starting Up a Project process and the Initiating a Project process?

A.Initiating a Project is done by the Project Board; Starting Up a Project is done by the Project Manager
B.They are the same process
C.Starting Up a Project is done before the project is authorized; Initiating a Project is after
D.Starting Up a Project is about creating the PID; Initiating a Project is about creating the Project Brief
AnswerC
95
Multi-Selecthard

Which THREE of the following are integrated elements of the PRINCE2 methodology?

Select 3 answers
A.Practices
B.Processes
C.Roles
D.Templates
E.Principles
AnswersA, B, E

Correct. Practices (themes) are one of the integrated elements.

Why this answer

The PRINCE2 framework consists of 7 principles, 7 practices (themes), and 7 processes. Tailoring is also an element but is not listed here.

96
MCQmedium

Which PRINCE2 principle ensures that a project remains viable by requiring continuous justification of the project's objectives against the benefits?

A.Manage by stages
B.Continued business justification
C.Focus on products
D.Tailor to suit the project environment
AnswerB

This principle requires that the project's business justification is maintained and reviewed throughout, ensuring the project remains viable.

Why this answer

The 'continued business justification' principle requires that the business justification for the project is reviewed and updated throughout the project to ensure ongoing viability. Option A (Manage by stages) focuses on planning and control, not justification. Option C (Focus on products) emphasizes defining and delivering products.

Option D (Tailor to suit the project environment) is indeed a PRINCE2 principle, but it addresses adapting the method, not viability. Therefore, only option B correctly ensures continuous justification of objectives against benefits.

97
MCQeasy

Which of the following is NOT covered by PRINCE2?

A.Quality management
B.Human resource management
C.Change control
D.Risk management
AnswerB

PRINCE2 does not cover HR.

Why this answer

PRINCE2 does not cover HR management; it focuses on project management processes.

98
MCQmedium

What is the purpose of the Managing a Stage Boundary (SB) process?

A.To produce the Project Plan and Business Case
B.To enable the Project Board to approve completion of the current stage and authorize the next
C.To close the project and hand over the product
D.To plan the activities for the current stage in detail
AnswerB

Correct. The SB process produces a Stage Plan for the next stage and an updated Business Case for Project Board decision.

Why this answer

The SB process provides the Project Board with information needed to review the current stage, approve the next stage Plan, and assess the continued viability of the project.

99
Multi-Selecthard

Which TWO of the following are correct statements about tailoring PRINCE2?

Select 2 answers
A.Tailoring may involve simplifying processes and documentation
B.Tailoring is only allowed for projects over a certain budget
C.Tailoring should consider the project's size, complexity, and risk
D.Tailoring is the same as embedding PRINCE2 into the organization
E.Tailoring allows removing PRINCE2 principles that are not relevant
AnswersA, C

Simplification is a common tailoring activity.

Why this answer

PRINCE2 explicitly allows tailoring to simplify processes and documentation to suit the project's needs, ensuring the method remains scalable and practical. This is a core concept of PRINCE2's flexibility, not a deviation from the framework.

Exam trap

PeopleCert often tests the misconception that tailoring allows removing PRINCE2 principles, which is false because principles are mandatory and cannot be tailored away, unlike processes and documentation.

100
MCQmedium

According to PRINCE2, what is the relationship between the principles, practices, and processes?

A.Principles are applied through practices and processes
B.Practices are optional, principles are mandatory
C.Processes replace principles in small projects
D.They are independent and can be used separately
AnswerA

The principles are embedded in the practices and processes.

Why this answer

In PRINCE2, the principles are the guiding obligations that must be followed for the methodology to be considered PRINCE2. These principles are applied through the practices (the 'what' of management) and the processes (the 'how' of management). Option A is correct because it captures this integrated, layered relationship: principles provide the foundation, and they are operationalized via practices and processes.

Exam trap

The trap here is that candidates often confuse the roles of principles and practices, mistakenly thinking practices are optional or that processes can override principles in smaller projects, when in reality all three components are mandatory and interdependent.

How to eliminate wrong answers

Option B is wrong because in PRINCE2, both principles and practices are mandatory; practices are not optional. Option C is wrong because processes do not replace principles in small projects; all seven principles must be applied regardless of project scale, though they can be tailored. Option D is wrong because principles, practices, and processes are not independent; they are tightly integrated and must be used together to form the PRINCE2 methodology.

101
MCQhard

What is the difference between a Request for Change (RFC) and an Off-Specification (Off-spec)?

A.An RFC is raised by the Project Manager; an Off-spec is raised by the Team Manager
B.An RFC is used in the Managing Product Delivery process; an Off-spec is used in the Controlling a Stage process
C.An RFC always requires approval; an Off-spec never requires approval
D.An RFC requests a change to a product; an Off-spec indicates a product does not meet its specification
AnswerD

Correct distinction.

Why this answer

A Request for Change (RFC) is a formal proposal to modify a product baseline, while an Off-Specification (Off-spec) is a notification that a product does not meet its agreed specification. In PRINCE2, an RFC seeks approval for a change, whereas an Off-spec identifies a deviation that must be resolved, often via a concession or corrective action. This distinction is fundamental to PRINCE2's change control approach, ensuring that changes and deviations are managed separately.

Exam trap

A common pitfall in PRINCE2 exams is confusing the purpose of an RFC and an Off-specification. Candidates often associate RFCs with specific roles (e.g., Project Manager) or processes (e.g., Managing Product Delivery), but the fundamental difference is that an RFC proposes a change to an approved product baseline, while an Off-spec reports that a product does not meet its specification. The approval process for RFCs is through Change Control, whereas Off-specs may be resolved by concessions or corrective actions without necessarily requiring a formal change.

How to eliminate wrong answers

Option A is wrong because both RFCs and Off-specs can be raised by any role, not exclusively by the Project Manager or Team Manager; the PRINCE2 guidance states that anyone can raise an issue, including an RFC or Off-spec. Option B is wrong because RFCs and Off-specs are not tied to specific processes; they are used across multiple processes, including Managing Product Delivery and Controlling a Stage, depending on when the issue arises. Option C is wrong because an Off-spec may require approval if it leads to a concession or change, and not all RFCs require approval (e.g., urgent changes may be pre-approved via delegated authority).

102
MCQeasy

What does PRINCE2 NOT cover?

A.Human resource management
B.Risk management
C.Change control
D.Quality management
AnswerA

Correct.

Why this answer

PRINCE2 is a process-based project management methodology that focuses on business justification, defined roles, and product-based planning. It explicitly excludes detailed human resource management techniques such as team motivation, conflict resolution, and performance appraisals, which are typically covered by general management disciplines. Therefore, human resource management is not covered by PRINCE2.

Exam trap

The trap here is that candidates often assume PRINCE2 covers all aspects of project management, including people management, but the exam specifically tests that PRINCE2 excludes detailed human resource management techniques.

How to eliminate wrong answers

Option B is wrong because risk management is a core PRINCE2 theme (the Risk theme) that defines how to identify, assess, and control risks throughout the project. Option C is wrong because change control is a key part of the Change theme in PRINCE2, which manages issues, changes, and configuration items. Option D is wrong because quality management is addressed by the Quality theme, which ensures that the project's products meet defined quality criteria and acceptance standards.

103
Multi-Selectmedium

Which TWO of the following are benefits of adopting PRINCE2?

Select 2 answers
A.Encourages consistency of project delivery
B.Guarantees project success
C.Provides a common language across projects
D.Ensures lower project costs
E.Eliminates the need for change control
AnswersA, C

Standard processes promote consistency.

Why this answer

PRINCE2 provides a structured framework with defined processes, roles, and management products, which encourages consistency in how projects are delivered across an organization. This standardization reduces variability in project execution and improves repeatability of successful practices.

Exam trap

The trap here is that candidates may assume PRINCE2 guarantees success or reduces costs because it is a best-practice framework, but the exam tests that it only provides a structured approach, not absolute outcomes.

104
MCQeasy

Which PRINCE2 process is triggered by the authorization of an Exception Plan?

A.Managing Product Delivery
B.Directing a Project
C.Controlling a Stage
D.Managing a Stage Boundary
AnswerC

Correct. After an Exception Plan is approved, the Project Manager executes it within Controlling a Stage.

Why this answer

An Exception Plan is approved by the Project Board, and the project then returns to the Controlling a Stage process to execute the plan.

105
Multi-Selecthard

Which THREE of the following are integrated elements of PRINCE2?

Select 3 answers
A.Principles
B.Project Mandate
C.Tailoring
D.Practices (Themes)
E.Processes
AnswersA, D, E

Correct. The 7 principles are a core element.

Why this answer

The integrated elements are the principles, practices (themes), and processes. Tailoring is how they adapt, but it is not an element itself. The project mandate is an input.

106
Multi-Selectmedium

Which ONE of the following is an output of the Closing a Project process?

Select 1 answer
A.End Project Report
B.Project Product Description
C.Benefits Management Approach
D.Lessons Log
E.Project Plan
AnswersA

Correct. The End Project Report is a formal output of the Closing a Project process, summarizing the project's achievements and lessons learned.

Why this answer

The Closing a Project process produces the End Project Report, which provides a summary of the project's performance and lessons learned. The Project Product Description is an input to the Closing a Project process, not an output. The other options (Benefits Management Approach, Lessons Log, Project Plan) are also inputs or earlier outputs, not deliverables of the Closing a Project process.

107
MCQmedium

During the Starting Up a Project process, what is the role of the Project Manager?

A.To assist the Executive in developing the Project Brief and preparing for initiation
B.To create the Project Initiation Documentation
C.To assign work packages to the team
D.To produce the Project Plan
AnswerA

Correct. The PM supports the Executive in Starting Up a Project.

Why this answer

The Project Manager assists the Executive in preparing the Project Brief and other initiation documentation.

108
MCQhard

A project is forecast to exceed its cost tolerance. According to PRINCE2, what should the Project Manager do?

A.Raise an Exception Report to the Project Board and await their direction before proceeding
B.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
C.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
D.Close the project immediately as the Business Case is no longer viable
AnswerA

Escalation via Exception Report is required when a tolerance is forecast to be breached.

Why this answer

According to PRINCE2, when a tolerance (cost, time, scope, or risk) is forecast to be exceeded, the Project Manager must escalate the issue to the Project Board via an Exception Report. The Project Board then decides on corrective action. Option A correctly reflects this escalation procedure.

Options B, C, and D are incorrect because the Project Manager cannot unilaterally increase the budget, should not continue without reporting the forecast deviation, and should not close the project immediately without board assessment.

109
Multi-Selectmedium

Which TWO of the following are PRINCE2 principles?

Select 2 answers
A.Business Case
B.Manage by Exception
C.Risk Management
D.Tailor to suit the project environment
E.Project Support
AnswersB, D

One of the seven PRINCE2 principles.

Why this answer

The two correct PRINCE2 principles are 'Manage by Exception' (B) and 'Tailor to suit the project environment' (D). Options A (Business Case) and C (Risk Management) are PRINCE2 themes, not principles. Option E (Project Support) is not a PRINCE2 principle.

110
MCQmedium

In PRINCE2, what is the difference between Project Assurance and Project Support?

A.Project Assurance focuses on quality; Project Support focuses on planning
B.Project Assurance is done by the Project Manager; Project Support is done by the team
C.Project Assurance provides independent oversight; Project Support provides administrative help
D.Project Assurance is optional; Project Support is mandatory
AnswerC

Correct.

Why this answer

PRINCE2 defines Project Assurance as an independent oversight function that monitors compliance with the project's management stages, while Project Support provides administrative and clerical help to the Project Manager and team. This distinction is fundamental to PRINCE2's separation of assurance from management and support roles.

Exam trap

The trap here is that candidates often confuse 'assurance' with 'quality' or think 'support' means planning, when PRINCE2 specifically defines Project Assurance as independent oversight across all performance targets and Project Support as administrative assistance.

How to eliminate wrong answers

Option A is wrong because Project Assurance covers all aspects of the project (business, user, supplier), not just quality, and Project Support handles administrative tasks, not planning specifically. Option B is wrong because Project Assurance is performed by individuals independent of the Project Manager (e.g., from corporate/programme management or external auditors), not by the Project Manager themselves. Option D is wrong because both Project Assurance and Project Support are mandatory roles in PRINCE2; neither is optional.

111
MCQmedium

Which role is responsible for maintaining the Business Case throughout the project?

A.Senior Supplier
B.Senior User
C.Executive
D.Project Manager
AnswerC

The Executive owns and maintains the Business Case.

Why this answer

The Executive (Senior Responsible Owner) owns the Business Case and is responsible for its maintenance.

112
MCQeasy

A project manager is assigned to a new project. The project's business case has been approved, and the project board has authorized the initiation stage. According to PRINCE2, what is the first step the project manager should take?

A.Update the Risk Register
B.Appoint the project board
C.Review the Business Case
D.Create the Project Plan
AnswerD

The Project Plan is the first plan to be created in the initiation stage.

Why this answer

In PRINCE2, once the business case is approved and the initiation stage is authorized, the project manager's first step is to create the Project Plan. This is because the Project Plan provides the detailed schedule, costs, and resource allocations needed to manage the initiation stage effectively, and it is a mandatory management product for the Initiating a Project process. Without the Project Plan, the project manager cannot proceed with other activities like updating the Risk Register or reviewing the Business Case in a structured way.

Exam trap

The trap here is that candidates often confuse the order of activities in the Initiating a Project process, mistakenly thinking that updating the Risk Register or reviewing the Business Case should come first, when PRINCE2 explicitly requires the Project Plan to be created as the initial step after authorization.

How to eliminate wrong answers

Option A is wrong because updating the Risk Register occurs after the Project Plan is created, as risks are identified and assessed during planning, not as the first step. Option B is wrong because the project board is appointed by the project executive before the initiation stage begins, not by the project manager after authorization. Option C is wrong because the Business Case is already approved before the initiation stage is authorized, so reviewing it again is not the first step; the project manager should focus on creating the Project Plan to detail how the stage will be executed.

113
MCQeasy

Which role provides an independent view of the project's progress, ensuring that it is carried out correctly?

A.Project Manager
B.Project Assurance
C.Project Support
D.Team Manager
AnswerB

Correct. Project Assurance is independent and reports to the Project Board.

Why this answer

Project Assurance is independent of the Project Manager and provides oversight to the Project Board. Project Support is administrative and not independent.

114
MCQmedium

In PRINCE2, which process is triggered by a request from the Project Manager to the Team Manager to deliver a product?

A.Starting Up a Project
B.Managing Product Delivery
C.Directing a Project
D.Controlling a Stage
AnswerB

MP is the process for Team Managers to deliver work packages.

Why this answer

The Managing Product Delivery process covers the acceptance and delivery of work packages. Option B is correct. CS includes the request but MP is the Team Manager's process.

DP is for the Project Board. SU is for starting up.

115
MCQmedium

Which document defines the authority and responsibility of the Project Manager?

A.The Project Initiation Documentation
B.The Stage Plan
C.The Work Package
D.The Project Brief
AnswerD

The Project Brief includes the Project Manager's authority and is approved by the Project Board.

Why this answer

The Project Brief defines the authority and responsibility of the Project Manager because it is created during the Starting Up a Project process and includes the project mandate, which outlines the Project Manager's role, authority levels, and accountability. PRINCE2 explicitly states that the Project Brief contains the project management team structure and role descriptions, making it the definitive document for the Project Manager's authority and responsibility.

Exam trap

PeopleCert often tests the misconception that the Project Initiation Documentation (PID) defines the Project Manager's authority, but the PID is a later, more detailed document that builds on the Project Brief, which actually establishes that authority first.

How to eliminate wrong answers

Option A is wrong because the Project Initiation Documentation (PID) is created during the Initiating a Project process and provides a comprehensive baseline for the project, but it does not define the Project Manager's authority and responsibility; that is established earlier in the Project Brief. Option B is wrong because the Stage Plan details the work, costs, and resources for a specific management stage, not the authority or responsibility of the Project Manager. Option C is wrong because the Work Package is a set of information authorizing work to a Team Manager or team member, defining their authority and responsibility, not the Project Manager's.

116
MCQhard

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Continue and report in the next Highlight Report
B.Raise an Exception Report to the Project Board
C.Close the project
D.Increase the stage budget and continue
AnswerB

Correct.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

117
MCQmedium

In PRINCE2, what is the purpose of the 'Directing a Project' process?

A.To plan and schedule the next stage
B.To manage the day-to-day activities of the project team
C.To create the project's products
D.To enable the Project Board to make key decisions and exercise overall control
AnswerD

Correct. The Project Board directs the project.

Why this answer

The 'Directing a Project' process in PRINCE2 is designed for the Project Board, not the project manager or team. Its purpose is to empower the Board to make key decisions (e.g., stage boundary approvals, exception plans) and exercise overall control from project initiation through closure, ensuring governance without involvement in day-to-day management.

Exam trap

PeopleCert often tests the misconception that 'Directing a Project' is about tactical management or product creation, when in fact it is exclusively about high-level governance and decision-making by the Project Board.

How to eliminate wrong answers

Option A is wrong because planning and scheduling the next stage is the responsibility of the 'Managing a Stage Boundary' process, not 'Directing a Project'. Option B is wrong because managing day-to-day activities is the purpose of the 'Managing Product Delivery' process, handled by the team manager. Option C is wrong because creating the project's products is the work of the 'Managing Product Delivery' process, executed by the project team, not the Project Board.

118
MCQmedium

What is NOT covered by PRINCE2?

A.Risk management
B.Business Case management
C.Quality management
D.Human resource management
AnswerD

Correct; PRINCE2 does not cover HR.

Why this answer

PRINCE2 is a process-based project management methodology that focuses on business justification, defined roles, and product-based planning. It explicitly covers risk management, business case management, and quality management as core themes, but it does not prescribe detailed human resource management practices; instead, it defines roles and responsibilities within the project management team.

Exam trap

The trap here is that candidates may assume PRINCE2 covers all aspects of project management, including human resource management, because it defines roles and responsibilities, but the exam specifically tests that PRINCE2 does not include detailed HR processes such as staff recruitment, training, or performance management.

How to eliminate wrong answers

Option A is wrong because PRINCE2 includes a dedicated 'Risk' theme that provides a systematic approach to identifying, assessing, and controlling risks throughout the project. Option B is wrong because the 'Business Case' theme is central to PRINCE2, ensuring the project remains viable and aligned with organizational objectives. Option C is wrong because the 'Quality' theme in PRINCE2 defines how quality is planned, controlled, and verified, including product-based quality criteria and quality registers.

119
MCQmedium

Which issue type is used to record a request for a new product or a change to an existing product that has been baselined?

A.Risk
B.Request for Change
C.Problem/Concern
D.Off-specification
AnswerB

An RFC proposes a change to a baselined product.

Why this answer

In PRINCE2, a Request for Change (RFC) is the correct issue type for recording a proposal for a new product or a modification to a product that has already been baselined (i.e., approved and placed under configuration management). This aligns with the PRINCE2 principle of 'Manage by Stages' and the Change Control approach, where any change to a baselined product must be formally captured as an RFC before being assessed and potentially approved via the change authority.

Exam trap

PeopleCert often tests the distinction between 'Request for Change' and 'Off-specification' by presenting a scenario where a product is already baselined and a modification is needed, leading candidates to mistakenly choose Off-specification because they confuse a change request with a defect report.

How to eliminate wrong answers

Option A (Risk) is wrong because a risk is an uncertain event that could affect the project's objectives, not a formal request to alter a baselined product. Option C (Problem/Concern) is wrong because this issue type is used to record a situation that has occurred and requires management attention, but it is not specifically for requesting a change to a baselined product; it could be a general issue or query. Option D (Off-specification) is wrong because an off-specification records a situation where a product does not meet its specification (a defect or non-conformance), not a request to change an already-approved baseline.

120
Multi-Selectmedium

Which TWO of the following are PRINCE2 principles?

Select 2 answers
A.Define deliverables
B.Manage by stages
C.Tailor to suit the project environment
D.Manage by objectives
E.Use product-based planning
AnswersB, C
121
MCQhard

During which process is the Project Plan created?

A.Initiating a Project
B.Managing a Stage Boundary
C.Starting Up a Project
D.Directing a Project
AnswerA

IP produces the PID, which includes the Project Plan.

Why this answer

The Project Plan is created during Initiating a Project.

122
MCQmedium

Which of the following distinguishes a Highlight Report from a Checkpoint Report?

A.The Checkpoint Report is produced by the Project Manager, while the Highlight Report is produced by the Team Manager
B.The Highlight Report is produced at the end of each stage, while the Checkpoint Report is produced monthly
C.The Highlight Report includes a summary of risks, while the Checkpoint Report does not
D.The Highlight Report is sent to the Project Board, while the Checkpoint Report is sent to the Project Manager
AnswerD

This is the main distinction in terms of audience.

Why this answer

In PRINCE2, the Highlight Report is a formal report from the Project Manager to the Project Board, providing a summary of progress, risks, and issues at predefined intervals during a stage. The Checkpoint Report is produced by the Team Manager for the Project Manager, detailing progress against the Work Package. This distinction in audience and purpose is a core PRINCE2 principle.

Exam trap

PeopleCert often tests the confusion between the producer and recipient of these reports, especially the misconception that the Checkpoint Report goes to the Project Board or that the Highlight Report is produced by the Team Manager.

How to eliminate wrong answers

Option A is wrong because it reverses the roles: the Checkpoint Report is produced by the Team Manager, while the Highlight Report is produced by the Project Manager. Option B is wrong because the Highlight Report is produced at intervals defined in the stage plan (not necessarily at the end of each stage), and the Checkpoint Report frequency is also defined in the Work Package (not necessarily monthly). Option C is wrong because both reports can include a summary of risks and issues; the Highlight Report always includes a risk summary, but the Checkpoint Report may also include risks relevant to the Work Package.

123
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To direct the work of the project team
B.To ensure that the project remains viable by reviewing the Business Case
C.To capture lessons throughout the project
D.To authorize the initiation of the project
AnswerB
124
MCQhard

Which PRINCE2 principle is being applied when the Project Manager escalates a forecast tolerance deviation to the Project Board?

A.Defined Roles and Responsibilities
B.Learn from Experience
C.Manage by Exception
D.Continued Business Justification
AnswerC

This principle sets tolerances and escalates when they are forecast to be exceeded.

Why this answer

The 'Manage by Exception' principle is applied when the Project Manager escalates a forecast tolerance deviation to the Project Board. This principle delegates decision-making authority within defined tolerances; only when a deviation is forecast to exceed those tolerances does the Project Manager escalate to the Project Board for a decision. The escalation triggers exception management, ensuring the board retains control at key decision points without micromanaging day-to-day activities.

Exam trap

The trap here is that candidates confuse 'Manage by Exception' with 'Defined Roles and Responsibilities', because escalation involves roles, but the principle specifically governing tolerance-based escalation is 'Manage by Exception', not role definition.

How to eliminate wrong answers

Option A is wrong because 'Defined Roles and Responsibilities' ensures each team member knows their duties and authority levels, but it does not specifically address the escalation of tolerance deviations; that is the function of 'Manage by Exception'. Option B is wrong because 'Learn from Experience' focuses on capturing and applying lessons throughout the project, not on the escalation mechanism for tolerance breaches. Option D is wrong because 'Continued Business Justification' requires ongoing validation that the project remains viable, but it does not prescribe the escalation process for tolerance deviations; that is handled by 'Manage by Exception'.

125
MCQmedium

During the Managing a Stage Boundary process, the Project Manager produces a revised Stage Plan for the next stage. What else must be produced as part of this process?

A.End Project Report
B.Highlight Report
C.Exception Report
D.End Stage Report
AnswerD

Correct. The End Stage Report is a mandatory output of Managing a Stage Boundary.

Why this answer

During the Managing a Stage Boundary process, the Project Manager must produce an End Stage Report to summarize the current stage's performance against its plan, along with the revised Stage Plan for the next stage. The End Stage Report provides the Project Board with the information needed to assess whether to authorize the next stage, as defined in PRINCE2's process model.

Exam trap

The trap here is that candidates often confuse the End Stage Report with the Highlight Report or Exception Report, but PRINCE2 explicitly mandates the End Stage Report as the key management product for stage boundary reviews, not periodic updates or exception triggers.

How to eliminate wrong answers

Option A is wrong because the End Project Report is produced during the Closing a Project process, not during Managing a Stage Boundary. Option B is wrong because the Highlight Report is a periodic report produced during the Controlling a Stage process to inform the Project Board of progress, not at stage boundaries. Option C is wrong because the Exception Report is produced when a stage is forecast to exceed tolerance thresholds, triggering an exception plan, and is not a mandatory output of the Managing a Stage Boundary process.

126
Multi-Selecthard

Which THREE of the following are benefits of adopting PRINCE2?

Select 3 answers
A.Eliminates all project risks
B.Guarantees faster project delivery
C.Provides a common language for all stakeholders
D.Enables controlled management of change
E.Improves communication between team and management
AnswersC, D, E

PRINCE2 standardizes terminology.

Why this answer

PRINCE2 provides a standardized framework with defined roles, responsibilities, and terminology, which ensures all stakeholders (including project board, team managers, and suppliers) share a common language. This reduces misunderstandings and aligns communication across the project lifecycle, directly supporting the principle of 'continued business justification' and 'manage by stages'.

Exam trap

PeopleCert often tests the misconception that PRINCE2 is a silver bullet for speed or risk elimination, but the exam expects candidates to recognize that PRINCE2 is a process-based method for governance and control, not a guarantee of outcomes.

127
MCQeasy

What is the definition of a project according to PRINCE2?

A.A process for managing day-to-day activities
B.A temporary organization that is created for the purpose of delivering one or more business products according to an agreed Business Case
C.A permanent organizational structure that performs ongoing operations
D.A team that works on repetitive tasks
AnswerB

This is the official PRINCE2 definition.

Why this answer

PRINCE2 defines a project as a temporary organization created to deliver one or more business products according to an agreed Business Case. This definition emphasizes the temporary nature of a project, its focus on outputs (products), and the necessity of a validated Business Case to justify the investment. It distinguishes projects from ongoing operations by highlighting the unique, time-limited structure and the governance provided by the Business Case.

Exam trap

The trap here is that candidates confuse a project with ongoing operations or repetitive tasks, failing to recognize that PRINCE2's core distinction is the temporary, product-focused, and Business Case-driven nature of a project versus the permanent, process-driven nature of operations.

How to eliminate wrong answers

Option A is wrong because it describes a process for managing day-to-day activities, which is characteristic of operations or business-as-usual, not a project. Option C is wrong because it describes a permanent organizational structure that performs ongoing operations, which is the opposite of the temporary organization defined for a project. Option D is wrong because it describes a team that works on repetitive tasks, which aligns with operational work or functional teams, not the unique, temporary, and product-focused nature of a project.

128
Multi-Selectmedium

Which TWO of the following are PRINCE2 principles?

Select 2 answers
A.Use of Agile
B.Waterfall Development
C.Continued Business Justification
D.Daily Stand-ups
E.Manage by Stages
AnswersC, E

Correct.

Why this answer

The seven principles include Manage by Stages and Continued Business Justification. 'Use of Agile' is not a principle.

129
MCQhard

In PRINCE2, what is the difference between a Request for Change and an Off-specification?

A.A Request for Change is a proposal for a change to a product that has been agreed, while an Off-specification is a product that does not meet its specification
B.An Off-specification is a type of issue, while a Request for Change is not
C.A Request for Change is a change to the scope, while an Off-specification is a change to the plan
D.An Off-specification does not require a change budget, while a Request for Change does
AnswerA

This is the correct distinction.

Why this answer

In PRINCE2, a Request for Change (RFC) is a proposal for a change to a product that has already been agreed (baselined), whereas an Off-specification (Off-spec) identifies a product that does not meet its specification, either because it is missing or incorrect. Therefore, option A correctly describes this difference. Option B is incorrect because both RFCs and Off-specs are types of issue.

Option C is incorrect because an Off-spec is not a change to the plan; it relates to product deviations. Option D is incorrect because both RFCs and Off-specs require a change budget if they are approved.

130
MCQmedium

Which PRINCE2 principle emphasizes that the project must remain desirable, viable, and achievable throughout its life?

A.Manage by Stages
B.Defined Roles and Responsibilities
C.Continued Business Justification
D.Learn from Experience
AnswerC

Ensures the project remains justified.

Why this answer

The principle 'Continued Business Justification' requires that the business justification (Business Case) is maintained and reviewed throughout the project to ensure it remains desirable, viable, and achievable. Option C is correct. Option A, 'Manage by Stages,' focuses on dividing the project into stages for better control.

Option B, 'Defined Roles and Responsibilities,' ensures clear assignment of roles. Option D, 'Learn from Experience,' emphasizes using lessons learned.

131
MCQmedium

Which PRINCE2 principle emphasizes focusing on the justification for the project?

A.Manage by stages
B.Tailor to suit the project environment
C.Learn from experience
D.Continued business justification
AnswerD
132
MCQhard

A project is in the Initiating a Project process. Which document describes the products to be delivered and the resources required to deliver them?

A.Business Case
B.Project Plan
C.Stage Plan
D.Project Initiation Documentation
AnswerB

The Project Plan describes the products and resources required for the entire project.

Why this answer

The Project Plan is created during the Initiating a Project process and describes the products to be delivered and the resources required to deliver them. Option B is correct. The Project Initiation Documentation is a collection of documents that includes the Project Plan but is not itself a plan.

The Stage Plan is for a specific stage, not the entire project. The Business Case provides justification, not the delivery details.

133
MCQmedium

Who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Senior User
C.Executive
D.Project Support
AnswerC

The Executive is responsible for the Business Case.

Why this answer

The Senior User represents the users and is responsible for ensuring the project delivers the required benefits; however, the Executive (Senior Responsible Owner) owns the Business Case. In PRINCE2, the Executive is ultimately accountable for the Business Case, but the Senior User provides input on benefits. The question asks who maintains it, and the correct answer is the Executive.

134
MCQmedium

A Project Board is considering whether to authorize the initiation of a project. Which document should they review?

A.Project Brief
B.Business Case
C.Stage Plan
D.Project Initiation Documentation
AnswerA

Correct. The Project Brief is produced in SU and used by the Project Board to decide on initiating.

Why this answer

The Project Brief contains the outline Business Case, project approach, and other information needed for the Project Board to decide whether to proceed to initiation.

135
Multi-Selectmedium

Which TWO of the following are PRINCE2 principles?

Select 2 answers
A.Progress
B.Learn from Experience
C.Risk
D.Focus on Products
E.Directing a Project
AnswersB, D

This is one of the seven PRINCE2 principles.

Why this answer

The PRINCE2 methodology is built on seven core principles that guide project management. 'Learn from Experience' (B) is a principle that requires the project team to actively seek and apply lessons learned from previous projects and throughout the current project's lifecycle. 'Focus on Products' (D) is another principle, emphasizing that a project is only successful if it delivers the defined products that meet the agreed-upon quality criteria, shifting the focus from activities to outputs.

Exam trap

The trap here is that PRINCE2 uses specific terminology where 'themes' and 'processes' are distinct from 'principles,' and candidates often confuse the names of themes (like 'Progress' or 'Risk') or processes (like 'Directing a Project') with the seven core principles.

136
MCQeasy

Which of the following is a characteristic of a project according to PRINCE2?

A.It is managed by a single functional department
B.It is ongoing and repetitive
C.It is a temporary organization created to deliver one or more business products
D.It has no defined start or end
AnswerC

This is the PRINCE2 definition of a project.

Why this answer

PRINCE2 defines a project as a temporary organization that creates a unique product. Business as usual is ongoing and repetitive, not temporary.

137
Drag & Dropmedium

Drag and drop the steps to manage a risk in PRINCE2 into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4

Why this order

The PRINCE2 risk management procedure follows: identify, assess, plan responses, implement, and monitor.

138
Multi-Selecthard

Which TWO of the following statements about the Executive role are correct?

Select 2 answers
A.The Executive chairs the Project Board
B.The Executive approves all Work Packages
C.The Executive manages the project on a day-to-day basis
D.The Executive is responsible for the Business Case
E.The Executive is appointed after the project brief is approved
AnswersA, D

The Executive chairs the Project Board.

Why this answer

The Executive role in PRINCE2 is the chair of the Project Board. The Executive is the ultimate decision-maker for the project, responsible for ensuring the project remains viable and aligned with business objectives. Chairing the Project Board means the Executive leads board meetings, sets the agenda, and ensures decisions are made to authorize key stages and changes.

Exam trap

PeopleCert often tests the distinction between the Executive's strategic accountability and the Project Manager's operational responsibility, leading candidates to confuse who approves Work Packages or manages daily tasks.

139
MCQeasy

Which of the following is a characteristic of a project according to PRINCE2?

A.It is a permanent endeavor
B.It operates within a single function
C.It has a defined start and end date
D.It produces repetitive outputs
AnswerC

Temporary nature with clear start and end.

Why this answer

PRINCE2 defines a project as a temporary organization with a defined start and end date, unique output, and cross-functional teams. Option C is correct because it directly reflects the temporary nature of a project. Option A is incorrect because projects are temporary, not permanent.

Option B is incorrect because projects involve multiple functions, not a single function. Option D is incorrect because projects produce unique outputs, not repetitive outputs.

140
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Project Plan
B.Project Initiation Documentation
C.Project Brief
D.Business Case
AnswerB

The PID is the comprehensive document that consolidates all initiation information.

Why this answer

The Project Initiation Documentation (PID) is the key output of Initiating a Project.

141
MCQmedium

During the Initiating a Project (IP) process, which document is created to define how the project will be executed, monitored, and controlled?

A.Project Initiation Documentation
B.Project Brief
C.Project Plan
D.Business Case
AnswerA

Correct. The PID contains the Project Plan, Business Case, and other key information.

Why this answer

The Project Initiation Documentation (PID) is the definitive document created during the Initiating a Project (IP) process. It consolidates all key information—including the Business Case, Project Plan, and controls—into a single source that defines how the project will be executed, monitored, and controlled throughout its lifecycle.

Exam trap

PRINCE2 often tests the distinction between documents created in different processes, and the trap here is confusing the Project Brief (from SU) with the Project Initiation Documentation (from IP), as both contain high-level project information but serve different purposes and are created at different stages.

How to eliminate wrong answers

Option B (Project Brief) is wrong because the Project Brief is created during the Starting Up a Project (SU) process as a preliminary outline of the project, not during IP, and it lacks the detailed execution and control definitions found in the PID. Option C (Project Plan) is wrong because the Project Plan is a component within the PID that focuses specifically on the schedule and resources, not the overarching governance, monitoring, and control mechanisms. Option D (Business Case) is wrong because the Business Case justifies the project's viability and is also a component of the PID, but it does not define how the project will be executed, monitored, and controlled.

142
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Continue and report in the next Highlight Report
B.Raise an Exception Report to the Project Board
C.Increase the budget to cover the overrun
D.Close the project immediately
AnswerB

Correct; this triggers management by exception.

Why this answer

According to the management by exception principle, exceeding tolerance must be escalated to the Project Board via an Exception Report.

143
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do first?

A.Issue an Exception Report to the Project Board
B.Update the Business Case to reflect the new cost
C.Close the project as it is no longer viable
D.Approve additional budget using contingency
AnswerA

Correct escalation procedure.

Why this answer

According to PRINCE2's management by exception, when a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

144
MCQhard

Which of the following is a characteristic of a project, as defined by PRINCE2?

A.It is a permanent organization with ongoing operations
B.It introduces no change to the organization
C.It is part of business as usual
D.It produces a unique product, service, or result
AnswerD

Correct. A project creates a unique output.

Why this answer

A project is defined as a temporary organization that produces a unique output, with cross-functional teams. The Business Case provides the business justification. 'Derived from business as usual' is not a defining characteristic; projects are temporary and unique.

145
Multi-Selecthard

Which THREE of the following are characteristics of a project according to PRINCE2?

Select 3 answers
A.Permanent organization
B.Repetitive processes
C.Cross-functional teams
D.Temporary
E.Unique output
AnswersC, D, E

Projects involve people from different functions.

Why this answer

Projects are temporary, have a unique output, and involve cross-functional teams. These are key characteristics according to PRINCE2. Options A (permanent organization) and B (repetitive processes) are characteristics of business as usual, not projects.

146
Multi-Selectmedium

Which THREE of the following are PRINCE2 practices (themes)?

Select 3 answers
A.Waterfall
B.Risk
C.Sprint Planning
D.Quality
E.Business Case
AnswersB, D, E

Correct.

Why this answer

Business Case, Risk, and Quality are themes. PRINCE2 has seven themes.

147
MCQeasy

Which of the following is NOT a PRINCE2 principle?

A.Manage by risks
B.Manage by stages
C.Focus on products
D.Continued business justification
AnswerA

Risk management is a theme, not a principle.

Why this answer

The seven principles are: Continued business justification, Learn from experience, Defined roles and responsibilities, Manage by stages, Manage by exception, Focus on products, Tailor to suit the project environment.

148
Multi-Selectmedium

Which TWO of the following are PRINCE2 practices (themes)?

Select 2 answers
A.Managing a Stage Boundary
B.Directing a Project
C.Starting Up a Project
D.Risk
E.Business Case
AnswersD, E

Risk is a theme.

Why this answer

The seven themes are: Business Case, Organization, Quality, Plans, Risk, Change, Progress.

149
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Close the project
B.Continue and report later
C.Raise an Exception Report
D.Increase the project budget
AnswerC

The PM must escalate to the Project Board.

Why this answer

The PM must escalate via an Exception Report to the Project Board.

← PreviousPage 2 of 3 · 158 questions totalNext →

Ready to test yourself?

Try a timed practice session using only Overview of PRINCE2 and the project environment questions.