Courseiva

CCNA Overview of PRINCE2 and the project environment Questions

65 of 140 questions · Page 2/2 · Overview of PRINCE2 and the project environment · Answers revealed

76
MCQhard

What is the primary purpose of the 'Manage by exception' principle?

A.To delegate authority to the Project Manager within agreed tolerances
B.To ensure the Project Manager is held accountable for all project decisions
C.To require the Project Board to approve all changes
D.To involve stakeholders at every stage of the project
AnswerA

Delegating authority within agreed tolerances is precisely what 'manage by exception' enables: the Project Board sets tolerances for time, cost, scope, quality, risk and benefit, then only intervenes when the Project Manager forecasts a breach. This satisfies the stem's focus on the principle's primary purpose — escalation by exception rather than routine reporting.

Why this answer

Manage by exception means that the Project Board only needs to be involved when tolerances are forecast to be exceeded. This frees them to focus on strategic decisions.

77
MCQmedium

A project manager is working within an organisation that applies PRINCE2. The organisation also runs a portfolio of strategic initiatives and a programme of related projects. The project manager needs to understand how the project fits into these wider structures. Which statement correctly describes the relationship between a PRINCE2 project, a programme and a portfolio?

A.A portfolio is a temporary structure that closes when its projects finish, while a programme is permanent and never closes
B.A programme is a temporary organisation created to deliver one or more business products, and a portfolio is a group of related projects managed together
C.Projects, programmes and portfolios are mutually exclusive and an initiative can only be classified as one of the three at any time
D.A project may be part of a programme, and a programme may be part of a portfolio, with the portfolio providing the organisation's overall investment direction
AnswerD

This correctly describes the hierarchy: a project can sit within a programme, and programmes and standalone projects sit within a portfolio that aligns change initiatives with strategic objectives. Understanding this helps the project manager see how the project's Business Case and governance connect to programme benefits and portfolio investment decisions.

Why this answer

PRINCE2 projects frequently sit within a programme, and programmes and standalone projects sit within a portfolio. The portfolio provides strategic investment direction and prioritisation, the programme coordinates related projects to deliver beneficial change, and the project delivers its products within that context. Recognising this nesting helps the project manager align governance and reporting appropriately.

Exam trap

The trap here is swapping the definitions of project and programme, or assuming the three structures are mutually exclusive when they can be nested.

78
MCQmedium

What is the difference between Project Assurance and Project Support?

A.Project Assurance is only required for large projects; Project Support is always required
B.There is no difference; they are the same role
C.Project Assurance provides an independent view; Project Support provides administrative services
D.Project Assurance is performed by the Project Manager; Project Support is performed by the Team Manager
AnswerC

Project Assurance provides an independent, objective check on the project's viability and compliance on behalf of the Project Board, while Project Support delivers administrative services such as configuration management and tooling. This satisfies the stem by contrasting independent scrutiny against administrative assistance.

Why this answer

PRINCE2 clearly distinguishes Project Assurance as an independent, objective check on the project's adherence to management controls and standards, while Project Support provides administrative and clerical services such as planning tools, filing, and information management. This separation ensures that assurance remains unbiased and not influenced by the day-to-day support activities.

Exam trap

The trap here is that candidates often confuse 'assurance' with 'support' because both sound like helping functions, but PRINCE2 specifically tests the independence of assurance versus the administrative nature of support.

How to eliminate wrong answers

Option A is wrong because Project Assurance is required on all PRINCE2 projects, not just large ones, and Project Support is optional, not always required. Option B is wrong because Project Assurance and Project Support are distinct roles with different responsibilities; they are not the same. Option D is wrong because Project Assurance is performed by someone independent of the Project Manager (often a senior stakeholder or a separate assurance team), not by the Project Manager, and Project Support is typically performed by a project support office or administrator, not by the Team Manager.

79
MCQmedium

A project manager is preparing to tailor PRINCE2 for a small, low-risk project to update a company's intranet content. The project board wants to ensure that the approach remains compliant with PRINCE2 principles. Which action best demonstrates the 'tailor to suit the project environment' principle?

A.Omitting the Business Case because the project is small and low-risk.
B.Combining the roles of Project Manager and Team Manager because the project has only one team.
C.Removing the 'manage by exception' principle because the project board meets weekly.
D.Reducing the number of management stages and simplifying the project documentation to match the project's scale.
AnswerD

Tailoring involves adapting PRINCE2 to the project's size, complexity, and risk. Reducing stages and simplifying documentation is a valid way to apply the principle while retaining essential controls. This keeps the method proportionate and still complies with PRINCE2 principles, making it the best example of tailoring.

Why this answer

The 'tailor to suit the project environment' principle requires adapting PRINCE2 to the project's scale, complexity, risk, and organizational context. Reducing management stages and simplifying documentation for a small, low-risk intranet update is a proportionate application that keeps essential controls while avoiding unnecessary overhead. Removing principles or compromising role separation does not constitute valid tailoring.

Exam trap

The trap here is confusing tailoring with the removal of PRINCE2 principles or essential roles, when tailoring only adjusts how the method is applied, not whether the principles are followed.

80
MCQmedium

A project manager is working on a PRINCE2 project to develop a new mobile banking app. The project is part of a larger programme that has its own governance and reporting requirements. The project manager needs to understand how PRINCE2 relates to the programme environment. Which statement best describes the relationship between a PRINCE2 project and a programme?

A.A programme is a temporary organisation created to deliver one or more business products, while a project is a group of related projects managed together.
B.A programme is always managed using PRINCE2, so the project manager must follow the programme's PRINCE2 processes instead of the project's own processes.
C.A programme is a temporary organisation that exists only for the duration of a single project, so the mobile banking app project cannot be part of a programme.
D.A programme is a group of related projects managed in a coordinated way to obtain benefits not available from managing them individually, and a PRINCE2 project may be one of those projects.
AnswerD

PRINCE2 recognises that projects may be part of a programme, which is a group of related projects and activities managed together to achieve benefits that would not be possible if they were managed separately. The mobile banking app project can be one project within that programme, and its business case should align with the programme's benefits. This option correctly describes the relationship and is the right answer.

Why this answer

A programme is a group of related projects managed in a coordinated way to achieve benefits that would not be available from managing them individually. A PRINCE2 project can sit within such a programme, and its business case and governance should align with the programme's objectives. The other options either reverse the definitions or incorrectly claim that programmes are always managed using PRINCE2.

Exam trap

The trap here is confusing the definitions of project and programme, or assuming that programme management must use PRINCE2, when PRINCE2 is a project management method.

81
MCQmedium

Which statement about the Project Assurance role is true?

A.Project Assurance is independent of the Project Manager and provides checks to the Project Board
B.Project Assurance is a full-time role on every project
C.Project Assurance is part of Project Support
D.Project Assurance is responsible for providing administrative support to the Project Manager
AnswerA

Project Assurance operates independently of the Project Manager, reporting directly to the Project Board on the project's viability against business, user and supplier interests. This independence satisfies the stem's requirement for objective oversight, since assurance must not be compromised by the Project Manager's delivery pressures.

Why this answer

The PRINCE2 methodology defines Project Assurance as an independent check on the project's progress, performed on behalf of the Project Board. It is separate from the Project Manager's day-to-day management and ensures that the project remains viable, compliant with standards, and aligned with business objectives. This independence is critical for objective oversight and is a core principle of PRINCE2's governance model.

Exam trap

The trap here is confusing Project Assurance with Project Support, as both roles involve oversight or assistance, but PRINCE2 explicitly separates them: Assurance is independent and reports to the Board, while Support is administrative and reports to the Project Manager.

How to eliminate wrong answers

Option B is wrong because Project Assurance is not a full-time role on every project; it can be performed part-time or by multiple individuals, depending on the project's scale and complexity. Option C is wrong because Project Assurance is distinct from Project Support; Project Support provides administrative and clerical services, while Assurance provides independent oversight and checks. Option D is wrong because Project Assurance is not responsible for administrative support; that is the function of Project Support, which assists the Project Manager with tasks like filing, scheduling, and maintaining records.

82
MCQmedium

A project is using PRINCE2. The Senior User identifies a new requirement that was not in the original scope. What should the Project Manager do first?

A.Immediately update the Project Plan to include the new requirement
B.Ask the Senior User to raise a change request with the Change Authority
C.Log it as an issue and assess the impact on the project
D.Reject the requirement because it is out of scope
AnswerC

Any new requirement is an issue under PRINCE2, so the Project Manager must first capture it in the Issue Register and assess its impact before deciding whether it needs a formal change. Only after impact analysis can the appropriate authority decide.

Why this answer

In PRINCE2, any new requirement or change that was not in the original scope is treated as an issue (specifically a change issue) and must be captured in the Issue Register and assessed for impact before any decision is made. The Project Manager's first action is to log the issue and evaluate its effect on the project's business case, plans, risks, and scope. Only after impact assessment should the Change Authority decide whether to approve, reject, or defer the change.

Exam trap

The trap is jumping to the change request or rejection step — candidates forget that PRINCE2 requires the Project Manager to first log and assess the issue before any decision or escalation, so they pick 'raise a change request' or 'reject' prematurely.

How to eliminate wrong answers

Option A is wrong because immediately updating the Project Plan bypasses PRINCE2's change control process and assumes approval before impact assessment. Option B is wrong because while the Senior User may ultimately raise a change request, the Project Manager's first step is to log and assess the issue, not to redirect the user before understanding the impact. Option D is wrong because rejecting a requirement outright without assessment violates PRINCE2's principle of managing by exception and the issue management process — changes must be evaluated, not dismissed.

83
MCQhard

A project manager is tailoring PRINCE2 for a project using an agile delivery approach. The project board wants to ensure that the 'Learn from Experience' principle is applied effectively. Which action best demonstrates the application of this principle in this context?

A.Reviewing lessons from previous projects during initiation and establishing a lessons log that is updated throughout the project.
B.Conducting a lessons learned review only at the end of the project to capture final insights.
C.Delegating the responsibility for lessons learned to the Project Assurance role, as they are independent.
D.Documenting lessons only when a stage fails or an exception occurs, to avoid unnecessary bureaucracy.
AnswerA

This action demonstrates Learn from Experience by seeking lessons from similar past projects during initiation and maintaining a lessons log. The log is updated as new lessons emerge, and lessons are applied to improve the current project and inform future projects.

Why this answer

Learn from Experience means seeking lessons from previous projects during initiation, maintaining a lessons log, and updating it throughout the project. Lessons should be applied at each stage boundary and used to improve the current project as well as future ones.

Exam trap

The trap here is thinking lessons are only captured at the end of the project or only when something goes wrong, rather than continuously throughout.

84
MCQmedium

Which of the following is an integrated element of PRINCE2?

A.Risk, change, and progress
B.Tools, techniques, and templates
C.Roles, deliverables, and quality
D.Principles, practices, processes, and tailoring
AnswerD

PRINCE2's integrated elements comprise seven principles, seven practices, seven processes, and tailoring to the project environment. This option correctly names all four, satisfying the stem's requirement for the complete integrated framework rather than partial lists or unrelated components such as themes or roles.

Why this answer

D is correct because PRINCE2 is explicitly defined as an integrated framework consisting of four core elements: principles, practices (formerly themes), processes, and tailoring. These four components are interwoven throughout the methodology, ensuring that every project applies the principles via the practices and processes, adapted through tailoring to the specific project environment. The PRINCE2 Foundation syllabus and official manual (Managing Successful Projects with PRINCE2) state that these four elements are the integrated building blocks of the method.

Exam trap

The PRINCE2 Foundation exam often tests the distinction between the four integrated elements (principles, practices, processes, tailoring) and the individual components within those elements, such as risk or quality, which are practices, not the overarching integrated framework.

How to eliminate wrong answers

Option A is wrong because risk, change, and progress are individual management practices (themes) within PRINCE2, not the integrated elements that form the entire framework. Option B is wrong because tools, techniques, and templates are supporting products or optional aids, not the core integrated elements defined by PRINCE2. Option C is wrong because roles, deliverables, and quality are components of the practices and processes, but they are not the overarching integrated elements; roles are part of the organization practice, deliverables are outputs of processes, and quality is a practice.

85
Multi-Selecthard

Which THREE of the following are reasons why projects fail, which PRINCE2 aims to address?

Select 3 answers
A.Poor planning
B.Too much change control
C.Lack of HR policies
D.Insufficient stakeholder involvement
E.Lack of clear objectives
AnswersA, D, E

Poor planning is a recognised cause of project failure that PRINCE2 addresses through its Plans theme and product-based planning technique. This satisfies the stem by naming one of the three failure reasons the method is designed to counter.

Why this answer

PRINCE2 is explicitly designed to counter common causes of project failure, and poor planning (A) is one of them: the method addresses this through its Plans theme, which requires product-based planning, defined stages, and a Project Plan plus Stage Plans with tolerances. Insufficient stakeholder involvement (D) is also targeted, since PRINCE2's Organization theme defines roles and responsibilities (e.g., Executive, Senior User, Senior Supplier, Project Manager) and its Communications Management Approach ensures stakeholders are identified, engaged, and informed throughout the project. Lack of clear objectives (E) is addressed by the Business Case theme and the 'continued business justification' principle, which demand a documented, measurable justification with defined benefits, costs, risks, and success criteria that are reviewed at each stage boundary.

By contrast, too much change control (B) is not a recognized cause of failure that PRINCE2 aims to fix — PRINCE2 actually mandates change control via the Change theme and issue/change logs, so excessive control is not the problem being solved. Lack of HR policies (C) is an organizational/HR governance matter outside PRINCE2's scope, as the method covers project roles and tolerances rather than employment or personnel policies.

86
MCQhard

A project is being set up in a large organization. The project manager is defining the project management team structure and needs to ensure that the business, user, and supplier interests are all represented. Which PRINCE2 principle does this primarily support?

A.Focus on products
B.Defined roles and responsibilities
C.Manage by exception
D.Tailor to suit the project environment
AnswerB

Defined roles and responsibilities is a PRINCE2 principle that requires the project to have a clear organizational structure with defined roles. The project board must include the Executive, Senior User, and Senior Supplier to represent business, user, and supplier interests. This directly supports the project manager's need to ensure all three interests are represented in the team structure.

Why this answer

The principle of defined roles and responsibilities requires a clear project management team structure with defined roles. In PRINCE2, the project board must include the Executive, Senior User, and Senior Supplier to represent business, user, and supplier interests. This ensures that all key stakeholder perspectives are involved in decision-making.

The other principles address products, exception management, and tailoring, not the composition of the team.

Exam trap

The trap here is selecting tailoring because the scenario mentions setting up a project in a large organization, but the specific need to represent business, user, and supplier interests points to defined roles and responsibilities.

87
MCQmedium

A project manager is leading a project to implement a new customer relationship management (CRM) system. During the 'Starting up a Project' process, the project manager is appointing the project team and creating the Project Brief. Which of the following is a key output of the 'Starting up a Project' process?

A.Project Brief
B.Benefits Review Plan
C.End Project Report
D.Project Initiation Documentation
AnswerA

The Project Brief is a key output of the Starting up a Project process. It provides a foundation for the project, outlining the project definition, outline business case, and project approach. In this scenario, the project manager creates the Project Brief to present to the Project Board for authorization to initiate the project.

Why this answer

The Project Brief is the primary output of the Starting up a Project process. It contains the outline business case, project definition, and project approach, providing enough information for the Project Board to decide whether to initiate the project. The other documents are outputs of later processes.

Exam trap

The trap here is confusing the Project Brief with the Project Initiation Documentation, as both are key documents but are produced in different processes.

88
Multi-Selecthard

Which THREE of the following are integrated elements of the PRINCE2 methodology?

Select 3 answers
A.Practices
B.Processes
C.Roles
D.Templates
E.Principles
AnswersA, B, E

Practices form one of the three integrated elements of PRINCE2, alongside principles and processes. They describe the aspects of project management that must be applied consistently, such as business case and risk, satisfying the stem's requirement for a genuine integrated element.

Why this answer

PRINCE2 is built on four integrated elements, and three of them are listed here: Principles (E), which are the seven universal, mandatory guiding obligations such as continued business justification and manage by exception; Processes (B), which are the seven activity-based stages from Starting up a Project through Closing a Project that describe what must be done; and Practices (A), the seven themes (e.g., Business Case, Organization, Plans, Risk, Quality, Change, Progress) that are applied continuously throughout the processes. These three, together with the fourth element (Tailoring to the project environment), form the integrated framework that makes PRINCE2 adaptable and scalable. Roles (C) is not a separate integrated element — organizational responsibilities are covered within the Organization practice, not as a standalone element.

Templates (D) is also not an integrated element; PRINCE2 provides product descriptions and example management products, but templates are optional supporting tools rather than a core element of the methodology.

89
MCQhard

A project is developing a new medical device. The project manager is reviewing the project's organization structure. The project board has three roles: Executive, Senior User, and Senior Supplier. The Executive is concerned about ensuring that the project delivers value for money. Which role is responsible for ensuring that the project delivers the required benefits as defined in the Business Case?

A.Executive
B.Project Manager
C.Senior Supplier
D.Senior User
AnswerD

The Senior User is responsible for specifying the needs of those who will use the project's products and for ensuring that the solution will deliver the expected benefits. This role provides the user perspective and confirms that the benefits defined in the Business Case are realized through the project's outputs.

Why this answer

In PRINCE2, the Senior User is accountable for ensuring that the project's products will deliver the benefits defined in the Business Case. This role represents the user community and is responsible for specifying user needs and confirming that the solution meets those needs and realizes the expected benefits.

Exam trap

The trap here is assuming that the Executive, who owns the Business Case, is also responsible for ensuring benefits delivery, but that responsibility is delegated to the Senior User.

90
MCQmedium

Which PRINCE2 principle ensures that a project remains viable by requiring continuous justification of the project's objectives against the benefits?

A.Manage by stages
B.Continued business justification
C.Focus on products
D.Tailor to suit the project environment
AnswerB

Continued business justification demands that a project's business case is reviewed and revalidated at every stage and end stage assessment, so funding stops once benefits no longer outweigh costs. This directly maintains viability, the constraint the stem specifies.

Why this answer

Continued business justification is the PRINCE2 principle that requires the project's business case to be reviewed and re-validated at every stage boundary and whenever a major change occurs. It ensures the project remains aligned with the organization's objectives and that the benefits still outweigh the costs and risks. If justification is lost, PRINCE2 mandates that the project be stopped rather than continued by inertia.

Exam trap

PRINCE2F often tests the confusion between principles that sound similar in purpose — candidates may pick 'Manage by stages' because it involves decision points, but the specific trigger is continuous justification of benefits, not stage boundaries.

How to eliminate wrong answers

Option A is wrong because 'Manage by stages' is a principle about dividing the project into manageable chunks with decision points, not about continuously justifying the project's viability. Option C is wrong because 'Focus on products' is about defining and delivering products that meet requirements, not about validating business benefits. Option D is wrong because 'Tailor to suit the project environment' is about adapting PRINCE2 to the project's size, complexity, and context, not about ongoing justification.

91
MCQmedium

What is the purpose of the Managing a Stage Boundary (SB) process?

A.To produce the Project Plan and Business Case
B.To enable the Project Board to approve completion of the current stage and authorize the next
C.To close the project and hand over the product
D.To plan the activities for the current stage in detail
AnswerB

The SB process produces the End Stage Report and Next Stage Plan, which the Project Board reviews to confirm the current stage delivered as agreed and to authorise the following stage, maintaining control at each boundary.

Why this answer

The SB process provides the Project Board with information needed to review the current stage, approve the next stage Plan, and assess the continued viability of the project.

92
Multi-Selecthard

Which TWO of the following are correct statements about tailoring PRINCE2?

Select 2 answers
A.Tailoring may involve simplifying processes and documentation
B.Tailoring is only allowed for projects over a certain budget
C.Tailoring should consider the project's size, complexity, and risk
D.Tailoring is the same as embedding PRINCE2 into the organization
E.Tailoring allows removing PRINCE2 principles that are not relevant
AnswersA, C

Tailoring scales PRINCE2 to the project's context, which includes simplifying or combining processes, roles and management products where full rigour adds no value. This satisfies the stem by confirming tailoring can reduce, not only add to, the method's standard documentation and process set.

Why this answer

Option A is correct because tailoring PRINCE2 explicitly permits adapting the method's processes, themes, and management products to the project's needs, which includes simplifying processes and reducing documentation to a level proportionate to the project. Option C is correct because the PRINCE2 tailoring guidance states that the approach must reflect the project's size, complexity, importance, capability, and risk, so these factors directly drive how the method is adapted. Options B, D, and E are incorrect: tailoring is not restricted by budget thresholds, embedding refers to adopting PRINCE2 as the organization's standard approach (a different concept from tailoring a specific project), and the seven PRINCE2 principles must always be applied and can never be removed.

Exam trap

PeopleCert often tests the misconception that tailoring allows removing PRINCE2 principles, which is false because principles are mandatory and cannot be tailored away, unlike processes and documentation.

93
MCQhard

A project manager is leading a project to implement a new IT system for a client. The project is part of a programme, and the programme manager has asked the project manager to ensure that the project aligns with the programme's objectives. The project manager is also responsible for delivering the project's products. Which PRINCE2 principle is being applied when the project manager ensures that the project has a clear and agreed Business Case that is linked to the programme's benefits?

A.Defined roles and responsibilities
B.Tailor to suit the project environment
C.Manage by stages
D.Continued business justification
AnswerD

This principle ensures that a project has a justified Business Case that is aligned with strategic objectives and remains valid throughout. By linking the project's Business Case to the programme's benefits, the project manager applies this principle, ensuring the project contributes to the programme's goals and remains viable.

Why this answer

Continued business justification is applied when the project manager ensures the project has a clear and agreed Business Case linked to the programme's benefits. This principle ensures the project remains aligned with strategic objectives and justifies its existence throughout its lifecycle, which is critical when the project is part of a larger programme.

Exam trap

The trap here is confusing continued business justification with manage by stages, but the scenario is about justifying the project in relation to the programme, not about stage division.

94
Multi-Selectmedium

Which THREE of the following are common reasons why projects fail, which PRINCE2 addresses?

Select 3 answers
A.Unclear project objectives
B.Lack of stakeholder engagement
C.Insufficient planning
D.Budget overrun due to inflation
E.Technology failure
AnswersA, B, C

PRINCE2 requires a clear Business Case.

Why this answer

PRINCE2 mandates clear, measurable project objectives through its Business Case and Project Product Description management products. Unclear objectives are a leading cause of project failure, as they prevent effective planning and control. PRINCE2's focus on continued business justification ensures objectives remain aligned with organizational goals.

Exam trap

PRINCE2 often tests the distinction between generic project risks (like inflation or technology failure) and the specific root causes PRINCE2 is designed to mitigate, such as unclear objectives, lack of stakeholder engagement, and insufficient planning.

95
MCQmedium

A Project Manager is tailoring PRINCE2 for a small, low-risk project. He decides to combine the 'Starting up a Project' and 'Initiating a Project' processes into a single process, and to reduce the number of stage boundaries. Which principle is he applying?

A.Manage by stages
B.Focus on products
C.Tailor to suit the project environment
D.Learn from experience
AnswerC

Tailoring involves adapting PRINCE2 to the size, complexity, and risk of the project. Combining processes and reducing stage boundaries for a small, low-risk project is a direct application of this principle. PRINCE2 is designed to be tailored, and this scenario describes exactly that. The principle ensures that the method is not applied rigidly but is scaled appropriately.

Why this answer

The PRINCE2 principle 'tailor to suit the project environment' requires that the method is adapted to the project's size, complexity, risk, and other factors. Combining processes and reducing stage boundaries for a small, low-risk project is a clear example of tailoring. This principle ensures that PRINCE2 is not applied in a one-size-fits-all manner but is scaled appropriately to add value without unnecessary overhead.

Exam trap

The trap here is thinking that combining processes violates manage by stages, when in fact tailoring allows such adaptations as long as the principles are still applied.

96
MCQeasy

A new Project Manager is reviewing the PRINCE2 principles. She wants to ensure that the project's organisation structure includes clear accountability for the three primary stakeholder interests: business, user, and supplier. Which principle is she applying?

A.Focus on products
B.Continued business justification
C.Defined roles and responsibilities
D.Manage by stages
AnswerC

Defined roles and responsibilities ensures that the project has a clear organisational structure with defined roles, including the three primary stakeholder interests: business, user, and supplier. This principle requires that these interests are represented in the Project Board and that roles are clearly defined. The scenario directly describes the need for clear accountability for these interests, which is the essence of this principle.

Why this answer

The principle of defined roles and responsibilities requires that a PRINCE2 project has a clear organisational structure that includes the three primary stakeholder interests: business, user, and supplier. This ensures that the project is accountable to these interests and that decisions are made with their input. The scenario describes exactly this need, making defined roles and responsibilities the correct principle.

Exam trap

The trap here is confusing the representation of stakeholder interests with continued business justification, which is about project viability, not organisational structure.

97
MCQeasy

What does PRINCE2 NOT cover?

A.Human resource management
B.Risk management
C.Change control
D.Quality management
AnswerA

PRINCE2 deliberately excludes human resource management; it addresses roles, responsibilities and organisation structure, but line management of people, appraisals and team welfare sit outside its scope. This is the documented exclusion, so it correctly answers what the method does not cover.

Why this answer

PRINCE2 is a process-based project management methodology that focuses on business justification, defined roles, and product-based planning. It explicitly excludes detailed human resource management techniques such as team motivation, conflict resolution, and performance appraisals, which are typically covered by general management disciplines. Therefore, human resource management is not covered by PRINCE2.

Exam trap

The trap here is that candidates often assume PRINCE2 covers all aspects of project management, including people management, but the exam specifically tests that PRINCE2 excludes detailed human resource management techniques.

How to eliminate wrong answers

Option B is wrong because risk management is a core PRINCE2 theme (the Risk theme) that defines how to identify, assess, and control risks throughout the project. Option C is wrong because change control is a key part of the Change theme in PRINCE2, which manages issues, changes, and configuration items. Option D is wrong because quality management is addressed by the Quality theme, which ensures that the project's products meet defined quality criteria and acceptance standards.

98
MCQmedium

A project is nearing the end of a stage. The project manager is preparing for the next stage and needs to ensure that the project remains aligned with the business objectives. Which PRINCE2 principle is being applied by reviewing the Business Case at the end of each stage?

A.Learn from experience
B.Continued business justification
C.Focus on products
D.Manage by stages
AnswerB

Continued business justification is the PRINCE2 principle that requires the project to have a valid Business Case at the start and to remain justified throughout. Reviewing the Business Case at the end of each stage is a direct application of this principle, as it ensures the project is still aligned with business objectives and should continue. This is the correct principle being applied.

Why this answer

Reviewing the Business Case at the end of each stage is a direct application of the continued business justification principle. This principle requires that the project has a valid Business Case at the start and that it remains valid throughout, with reviews at stage boundaries to confirm alignment with business objectives. The other principles address product focus, stage control, and learning, not the ongoing justification of the project.

Exam trap

The trap here is associating stage-end reviews with manage by stages, but the specific action of reviewing the Business Case is mandated by continued business justification.

99
MCQmedium

A Project Manager is leading a project to develop a new mobile application. The Project Board has defined tolerances for time and cost. During a stage, the Project Manager forecasts that the stage will exceed the time tolerance. According to PRINCE2, what should the Project Manager do?

A.Wait until the end of the stage to include the variance in the End Stage Report.
B.Adjust the stage plan to reflect the new forecast and continue without escalation.
C.Immediately escalate the forecast exception to the Project Board by producing an Exception Report.
D.Take corrective action to bring the stage back within tolerance without informing the Project Board.
AnswerC

When a forecast breach of stage tolerances occurs, the Project Manager must escalate it by producing an Exception Report and referring it to the Project Board. This triggers the 'directing a project' process to decide how to proceed. Escalating promptly maintains the manage by exception principle and allows the Board to take corrective action.

Why this answer

Under PRINCE2's manage by exception principle, the Project Manager is delegated tolerances by the Project Board. If a forecast indicates a breach of those tolerances, the Project Manager must escalate by producing an Exception Report so the Project Board can decide on corrective action. Taking unilateral action or delaying escalation would violate the principle and could lead to loss of control.

Exam trap

The trap here is assuming the Project Manager should try to fix the issue first and only escalate if unsuccessful, when in fact any forecast breach of tolerances must be escalated immediately.

100
MCQhard

A project is forecast to exceed its cost tolerance. According to PRINCE2, what should the Project Manager do?

A.Raise an Exception Report to the Project Board and await their direction before proceeding
B.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
C.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
D.Close the project immediately as the Business Case is no longer viable
AnswerA

Exceeding cost tolerance breaches the tolerance delegated to the Project Manager, so the matter must escalate to the Project Board via an Exception Report, which presents options and awaits direction. Proceeding without approval would violate the manage by exception principle governing stage-level authority.

Why this answer

In PRINCE2, cost tolerance is defined at the stage and project levels within the Business Case and Project Plan. When a forecast indicates the stage or project will exceed its cost tolerance, this constitutes an exception, and the Project Manager must produce an Exception Report and escalate to the Project Board, which decides whether to approve a revised plan, change scope, or stop the project. The Project Manager cannot unilaterally increase budget or continue past tolerance.

Exam trap

PRINCE2F often tests the misconception that the Project Manager can adjust budget or continue within a stage despite a forecast tolerance breach — the exam expects recognition that any forecast exception must be escalated to the Project Board via an Exception Report.

How to eliminate wrong answers

Option B is wrong because the Project Manager has no authority to increase the project budget — budget changes require Project Board approval via the Exception Report and possibly a revised Business Case. Option C is wrong because continuing past a forecast tolerance breach without escalation violates the 'manage by exception' principle; Highlight Reports are for routine progress, not tolerance breaches. Option D is wrong because closing the project is a Project Board decision based on Business Case viability, not an automatic action by the Project Manager upon a cost forecast.

101
MCQmedium

In PRINCE2, what is the difference between Project Assurance and Project Support?

A.Project Assurance focuses on quality; Project Support focuses on planning
B.Project Assurance is done by the Project Manager; Project Support is done by the team
C.Project Assurance provides independent oversight; Project Support provides administrative help
D.Project Assurance is optional; Project Support is mandatory
AnswerC

Project Assurance is the Project Board's independent check on the project's viability, separate from the Project Manager, whereas Project Support is a non-decision-making administrative role. The option correctly separates independent oversight from administrative help, matching the accountability split PRINCE2 defines.

Why this answer

PRINCE2 defines Project Assurance as an independent oversight function that monitors compliance with the project's management stages, while Project Support provides administrative and clerical help to the Project Manager and team. This distinction is fundamental to PRINCE2's separation of assurance from management and support roles.

Exam trap

The trap here is that candidates often confuse 'assurance' with 'quality' or think 'support' means planning, when PRINCE2 specifically defines Project Assurance as independent oversight across all performance targets and Project Support as administrative assistance.

How to eliminate wrong answers

Option A is wrong because Project Assurance covers all aspects of the project (business, user, supplier), not just quality, and Project Support handles administrative tasks, not planning specifically. Option B is wrong because Project Assurance is performed by individuals independent of the Project Manager (e.g., from corporate/programme management or external auditors), not by the Project Manager themselves. Option D is wrong because both Project Assurance and Project Support are mandatory roles in PRINCE2; neither is optional.

102
MCQeasy

A project manager is assigned to a new project. The project's business case has been approved, and the project board has authorized the initiation stage. According to PRINCE2, what is the first step the project manager should take?

A.Update the Risk Register
B.Appoint the project board
C.Review the Business Case
D.Create the Project Plan
AnswerD

The Project Plan is the first plan to be created in the initiation stage.

Why this answer

In PRINCE2, once the business case is approved and the initiation stage is authorized, the project manager's first step is to create the Project Plan. This is because the Project Plan provides the detailed schedule, costs, and resource allocations needed to manage the initiation stage effectively, and it is a mandatory management product for the Initiating a Project process. Without the Project Plan, the project manager cannot proceed with other activities like updating the Risk Register or reviewing the Business Case in a structured way.

Exam trap

The trap here is that candidates often confuse the order of activities in the Initiating a Project process, mistakenly thinking that updating the Risk Register or reviewing the Business Case should come first, when PRINCE2 explicitly requires the Project Plan to be created as the initial step after authorization.

How to eliminate wrong answers

Option A is wrong because updating the Risk Register occurs after the Project Plan is created, as risks are identified and assessed during planning, not as the first step. Option B is wrong because the project board is appointed by the project executive before the initiation stage begins, not by the project manager after authorization. Option C is wrong because the Business Case is already approved before the initiation stage is authorized, so reviewing it again is not the first step; the project manager should focus on creating the Project Plan to detail how the stage will be executed.

103
MCQeasy

Which role provides an independent view of the project's progress, ensuring that it is carried out correctly?

A.Project Manager
B.Project Assurance
C.Project Support
D.Team Manager
AnswerB

Project Assurance monitors the project independently of the Project Manager, checking that all seven principles, themes and processes are applied correctly. Its independence from the delivery role satisfies the stem's requirement for an impartial view of progress.

Why this answer

Project Assurance is independent of the Project Manager and provides oversight to the Project Board. Project Support is administrative and not independent.

104
MCQmedium

A project manager is preparing the 'initiating a project' documentation for a new PRINCE2 project to replace a legacy payroll system. The project board wants to understand the difference between a project and business as usual. Which statement best explains why the payroll replacement is a project rather than business as usual?

A.It is a project because payroll processing is a recurring operational activity that continues indefinitely after go-live.
B.It is a project because it will be managed using PRINCE2, and any PRINCE2-managed work is by definition a project.
C.It is a project because it will be delivered by a temporary organisation created for the purpose of delivering the payroll replacement.
D.It is a project because it involves a large budget and many stakeholders, which automatically makes any work a project.
AnswerC

PRINCE2 defines a project as a temporary organisation created for the purpose of delivering one or more business products according to an agreed business case. The payroll replacement is a temporary organisation with a defined start and end, created specifically to deliver the new system. This characteristic distinguishes it from business as usual, which is ongoing and permanent. Therefore, this option correctly explains why the work is a project.

Why this answer

PRINCE2 distinguishes projects from business as usual primarily through their temporary nature and the creation of a temporary organisation to deliver specific business products against an agreed business case. The payroll replacement fits this because it has a defined start and end and a dedicated team, whereas payroll processing itself is ongoing operations. The other options either describe business as usual or rely on size or method use, which are not defining characteristics.

Exam trap

The trap here is equating project status with size, budget or use of PRINCE2, rather than recognising the temporary organisation and unique business products as the defining features.

105
MCQhard

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Continue and report in the next Highlight Report
B.Raise an Exception Report to the Project Board
C.Close the project
D.Increase the stage budget and continue
AnswerB

Breaching stage cost tolerance exceeds the Project Manager's delegated authority, so the deviation must be escalated. An Exception Report informs the Project Board of the forecast breach, enabling it to decide on corrective action, satisfying the stem's requirement for handling tolerance exceedance.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

106
MCQmedium

In PRINCE2, what is the purpose of the 'Directing a Project' process?

A.To plan and schedule the next stage
B.To manage the day-to-day activities of the project team
C.To create the project's products
D.To enable the Project Board to make key decisions and exercise overall control
AnswerD

'Directing a Project' enables the Project Board to be accountable for the project's success by making key decisions and exercising overall control, rather than performing day-to-day management. This satisfies the stem's requirement to identify the process's purpose: providing the decision-making and control layer that sits above the Managing a Stage Boundary and Controlling a Stage processes.

Why this answer

The 'Directing a Project' process in PRINCE2 is designed for the Project Board, not the project manager or team. Its purpose is to empower the Board to make key decisions (e.g., stage boundary approvals, exception plans) and exercise overall control from project initiation through closure, ensuring governance without involvement in day-to-day management.

Exam trap

PeopleCert often tests the misconception that 'Directing a Project' is about tactical management or product creation, when in fact it is exclusively about high-level governance and decision-making by the Project Board.

How to eliminate wrong answers

Option A is wrong because planning and scheduling the next stage is the responsibility of the 'Managing a Stage Boundary' process, not 'Directing a Project'. Option B is wrong because managing day-to-day activities is the purpose of the 'Managing Product Delivery' process, handled by the team manager. Option C is wrong because creating the project's products is the work of the 'Managing Product Delivery' process, executed by the project team, not the Project Board.

107
MCQmedium

What is NOT covered by PRINCE2?

A.Risk management
B.Business Case management
C.Quality management
D.Human resource management
AnswerD

Human resource management covers line-management matters such as recruitment, contracts and appraisals, which PRINCE2 excludes. PRINCE2 addresses the organisation structure and role responsibilities for the project, but not the wider HR discipline, satisfying the stem's NOT requirement.

Why this answer

PRINCE2 is a process-based project management methodology that focuses on business justification, defined roles, and product-based planning. It explicitly covers risk management, business case management, and quality management as core themes, but it does not prescribe detailed human resource management practices; instead, it defines roles and responsibilities within the project management team.

Exam trap

The trap here is that candidates may assume PRINCE2 covers all aspects of project management, including human resource management, because it defines roles and responsibilities, but the exam specifically tests that PRINCE2 does not include detailed HR processes such as staff recruitment, training, or performance management.

How to eliminate wrong answers

Option A is wrong because PRINCE2 includes a dedicated 'Risk' theme that provides a systematic approach to identifying, assessing, and controlling risks throughout the project. Option B is wrong because the 'Business Case' theme is central to PRINCE2, ensuring the project remains viable and aligned with organizational objectives. Option C is wrong because the 'Quality' theme in PRINCE2 defines how quality is planned, controlled, and verified, including product-based quality criteria and quality registers.

108
MCQhard

During which process is the Project Plan created?

A.Initiating a Project
B.Managing a Stage Boundary
C.Starting Up a Project
D.Directing a Project
AnswerA

The Project Plan is produced during Initiating a Project, where the Project Initiation Documentation is assembled and the Project Board authorises the project. This satisfies the stem's question by distinguishing the project-level plan from the Stage Plan created later at Managing a Stage Boundary.

Why this answer

The Project Plan is created during Initiating a Project.

109
MCQmedium

A programme manager is setting up a new PRINCE2 project to develop a mobile banking app. The project will use a supplier to build the app, and the programme manager wants to ensure that the project has the right level of direction and management. Which PRINCE2 principle is being applied when the project is established with a defined organization structure that includes a Project Board with clear roles and responsibilities?

A.Defined roles and responsibilities
B.Manage by exception
C.Focus on products
D.Tailor to suit the project environment
AnswerA

This principle ensures that every project has a clear organizational structure with defined roles, such as the Project Board, Project Manager, and Team Manager. In this scenario, establishing a Project Board with clear roles directly applies this principle, ensuring accountability and direction for the mobile banking app project.

Why this answer

The defined roles and responsibilities principle ensures that projects have a clear organizational structure with defined roles, such as the Project Board, Project Manager, and Team Manager. By establishing a Project Board with clear roles, the programme manager applies this principle to provide direction and management for the mobile banking app project.

Exam trap

The trap here is confusing the defined roles and responsibilities principle with manage by exception, which is about tolerances and delegation, not about establishing roles.

110
MCQmedium

Which of the following distinguishes a Highlight Report from a Checkpoint Report?

A.The Checkpoint Report is produced by the Project Manager, while the Highlight Report is produced by the Team Manager
B.The Highlight Report is produced at the end of each stage, while the Checkpoint Report is produced monthly
C.The Highlight Report includes a summary of risks, while the Checkpoint Report does not
D.The Highlight Report is sent to the Project Board, while the Checkpoint Report is sent to the Project Manager
AnswerD

Highlight Reports flow to the Project Board, satisfying the stem's requirement to distinguish the two by audience. Checkpoint Reports travel from Team Manager to Project Manager, covering work package progress at agreed frequencies. This recipient axis — Board versus Project Manager — is the defining difference, not content, timing or authorship.

Why this answer

In PRINCE2, the Highlight Report is a formal report from the Project Manager to the Project Board, providing a summary of progress, risks, and issues at predefined intervals during a stage. The Checkpoint Report is produced by the Team Manager for the Project Manager, detailing progress against the Work Package. This distinction in audience and purpose is a core PRINCE2 principle.

Exam trap

PeopleCert often tests the confusion between the producer and recipient of these reports, especially the misconception that the Checkpoint Report goes to the Project Board or that the Highlight Report is produced by the Team Manager.

How to eliminate wrong answers

Option A is wrong because it reverses the roles: the Checkpoint Report is produced by the Team Manager, while the Highlight Report is produced by the Project Manager. Option B is wrong because the Highlight Report is produced at intervals defined in the stage plan (not necessarily at the end of each stage), and the Checkpoint Report frequency is also defined in the Work Package (not necessarily monthly). Option C is wrong because both reports can include a summary of risks and issues; the Highlight Report always includes a risk summary, but the Checkpoint Report may also include risks relevant to the Work Package.

111
MCQhard

Which PRINCE2 principle is being applied when the Project Manager escalates a forecast tolerance deviation to the Project Board?

A.Defined Roles and Responsibilities
B.Learn from Experience
C.Manage by Exception
D.Continued Business Justification
AnswerC

Manage by Exception defines tolerances for time, cost, scope, quality, risk and benefits, empowering the Project Board to set boundaries and requiring the Project Manager to escalate only when a forecast breach exceeds delegated authority.

Why this answer

The 'Manage by Exception' principle is applied when the Project Manager escalates a forecast tolerance deviation to the Project Board. This principle delegates decision-making authority within defined tolerances; only when a deviation is forecast to exceed those tolerances does the Project Manager escalate to the Project Board for a decision. The escalation triggers exception management, ensuring the board retains control at key decision points without micromanaging day-to-day activities.

Exam trap

The trap here is that candidates confuse 'Manage by Exception' with 'Defined Roles and Responsibilities', because escalation involves roles, but the principle specifically governing tolerance-based escalation is 'Manage by Exception', not role definition.

How to eliminate wrong answers

Option A is wrong because 'Defined Roles and Responsibilities' ensures each team member knows their duties and authority levels, but it does not specifically address the escalation of tolerance deviations; that is the function of 'Manage by Exception'. Option B is wrong because 'Learn from Experience' focuses on capturing and applying lessons throughout the project, not on the escalation mechanism for tolerance breaches. Option D is wrong because 'Continued Business Justification' requires ongoing validation that the project remains viable, but it does not prescribe the escalation process for tolerance deviations; that is handled by 'Manage by Exception'.

112
MCQmedium

During the Managing a Stage Boundary process, the Project Manager produces a revised Stage Plan for the next stage. What else must be produced as part of this process?

A.End Project Report
B.Highlight Report
C.Exception Report
D.End Stage Report
AnswerD

Alongside the revised next Stage Plan, the Managing a Stage Boundary process requires an End Stage Report summarising performance against the current Stage Plan, plus an updated Business Case and risk information, so the Project Board can authorise continuation.

Why this answer

During the Managing a Stage Boundary process, the Project Manager must produce an End Stage Report to summarize the current stage's performance against its plan, along with the revised Stage Plan for the next stage. The End Stage Report provides the Project Board with the information needed to assess whether to authorize the next stage, as defined in PRINCE2's process model.

Exam trap

The trap here is that candidates often confuse the End Stage Report with the Highlight Report or Exception Report, but PRINCE2 explicitly mandates the End Stage Report as the key management product for stage boundary reviews, not periodic updates or exception triggers.

How to eliminate wrong answers

Option A is wrong because the End Project Report is produced during the Closing a Project process, not during Managing a Stage Boundary. Option B is wrong because the Highlight Report is a periodic report produced during the Controlling a Stage process to inform the Project Board of progress, not at stage boundaries. Option C is wrong because the Exception Report is produced when a stage is forecast to exceed tolerance thresholds, triggering an exception plan, and is not a mandatory output of the Managing a Stage Boundary process.

113
MCQmedium

A programme manager is establishing a new PRINCE2 project to deliver a regulatory compliance system. The organisation already runs a portfolio of change initiatives and has a Programme Office that sets governance standards. Which PRINCE2 principle should the project manager apply when designing the project's management approaches so they align with existing corporate governance and programme controls?

A.Manage by exception
B.Learn from experience
C.Continued business justification
D.Tailor to suit the project environment
AnswerD

This principle requires the PRINCE2 method to be adapted to the project's size, complexity, importance, capability and risk. Because the organisation has a Programme Office setting governance standards, the project's approaches must be tailored to align with those existing controls rather than applied in a generic, unmodified way, ensuring the method fits the wider organisational environment.

Why this answer

Tailoring is the principle that the method must be adapted to the project's environment, rather than applied rigidly. Here the Programme Office imposes governance standards, so the project's management approaches must be shaped to fit those standards. The other principles address escalation, viability or lessons, none of which directly answers how the method is adapted to the wider organisational context.

Exam trap

The trap here is confusing governance alignment with manage by exception, when it is tailoring that adapts the method to the organisation's existing standards.

114
Multi-Selecthard

Which THREE of the following are benefits of adopting PRINCE2?

Select 3 answers
A.Eliminates all project risks
B.Guarantees faster project delivery
C.Provides a common language for all stakeholders
D.Enables controlled management of change
E.Improves communication between team and management
AnswersC, D, E

PRINCE2 supplies a defined vocabulary and role structure, so all stakeholders share consistent terminology for products, roles and processes. This common language reduces misunderstanding across organisational and disciplinary boundaries, satisfying the benefit of shared communication the question seeks.

Why this answer

Option C is correct because PRINCE2 supplies a shared vocabulary and defined roles, processes, and management products (such as the Project Initiation Documentation and Highlight Reports) that give all stakeholders a common language for discussing and governing the project. Option D is correct because PRINCE2's change control approach, together with the issue and change control procedure and the configuration management strategy, provides controlled management of change rather than ad hoc handling. Option E is correct because PRINCE2's defined roles (Project Board, Project Manager, Team Manager) and regular management products such as Checkpoint, Highlight, and End Stage Reports create structured, planned communication between the team and management.

Option A is wrong because no method can eliminate all project risks; PRINCE2 only provides a risk management approach to identify, assess, and control them. Option B is wrong because PRINCE2 is a governance and management framework, not a schedule accelerator, and it does not guarantee faster delivery.

Exam trap

PeopleCert often tests the misconception that PRINCE2 is a silver bullet for speed or risk elimination, but the exam expects candidates to recognize that PRINCE2 is a process-based method for governance and control, not a guarantee of outcomes.

115
MCQhard

In PRINCE2, what is the difference between a Request for Change and an Off-specification?

A.A Request for Change is a proposal for a change to a product that has been agreed, while an Off-specification is a product that does not meet its specification
B.An Off-specification is a type of issue, while a Request for Change is not
C.A Request for Change is a change to the scope, while an Off-specification is a change to the plan
D.An Off-specification does not require a change budget, while a Request for Change does
AnswerA

A Request for Change proposes altering a product already agreed and baselined, whereas an Off-specification records a product that fails to meet its agreed specification. This distinction satisfies the stem's requirement by separating a proactive change proposal from a reported non-conformance, matching PRINCE2's change and quality terminology precisely.

Why this answer

In PRINCE2, a Request for Change (RFC) is a proposal to change a product that has already been baselined or agreed, while an Off-specification describes a product that currently does not meet its agreed specification. Both are types of Issue, but they capture different situations: RFCs are proactive change requests, and Off-specifications are reactive statements of non-conformance. Option A captures this distinction precisely.

Exam trap

PRINCE2F often tests the confusion that Off-specifications are somehow outside the Issue register or don't require change control, when in fact both are Issues handled through the same procedure.

How to eliminate wrong answers

Option B is wrong because both a Request for Change and an Off-specification are types of Issue in PRINCE2 — the statement that one is an issue and the other is not is false. Option C is wrong because an Off-specification is not a change to the plan; it is a product that fails to meet its specification, and a Request for Change is not limited to scope changes. Option D is wrong because change budgets and the handling of issues are governed by the same change control approach; there is no rule that Off-specifications bypass the change budget while RFCs require it.

116
MCQmedium

Which PRINCE2 principle emphasizes that the project must remain desirable, viable, and achievable throughout its life?

A.Manage by Stages
B.Defined Roles and Responsibilities
C.Continued Business Justification
D.Learn from Experience
AnswerC

Continued Business Justification requires the Business Case to be reviewed and confirmed viable, desirable and achievable at every stage, justifying continued investment. This satisfies the stem's emphasis on ongoing desirability, viability and achievability throughout the project's life.

Why this answer

The PRINCE2 principle 'Continued Business Justification' states that a project must have a valid Business Case and remain desirable, viable, and achievable throughout its life. This principle ensures that the project is not continued simply because it was started, but because it continues to deliver value. It is one of the seven core principles that must be applied for a project to be considered PRINCE2-compliant.

Exam trap

PRINCE2F often tests the confusion between principles, themes, and processes, and candidates may pick 'Manage by Stages' or 'Learn from Experience' when the question specifically describes the ongoing viability of the Business Case.

How to eliminate wrong answers

Option A is wrong because 'Manage by Stages' is about breaking the project into manageable stages with decision points, not about ongoing viability. Option B is wrong because 'Defined Roles and Responsibilities' is about establishing a clear organizational structure, not about the Business Case. Option D is wrong because 'Learn from Experience' is about capturing and applying lessons, not about maintaining business justification.

117
MCQmedium

A project is delivering a new payroll system. During the 'Managing a Stage Boundary' process, the project manager is preparing the End Stage Report for the project board. Which input to this process provides the board with the current status of the project's business justification?

A.Lessons Log
B.Business Case
C.End Stage Report
D.Benefits Review Plan
AnswerB

The Business Case is a key input to the 'Managing a Stage Boundary' process and provides the current status of the project's justification. It is reviewed and updated at each stage boundary to ensure the project remains viable. The project board uses it to decide whether to continue, and it directly addresses the question about the status of the business justification.

Why this answer

The Business Case is the document that contains the current justification for the project and is a required input to the 'Managing a Stage Boundary' process. It is reviewed and updated at each stage boundary, enabling the project board to assess whether the project remains desirable, viable, and achievable. This directly answers the question about the status of the business justification.

Exam trap

The trap here is confusing the End Stage Report, which is an output, with the Business Case, which is an input that provides the justification status.

118
MCQmedium

Which PRINCE2 principle emphasizes focusing on the justification for the project?

A.Manage by stages
B.Tailor to suit the project environment
C.Learn from experience
D.Continued business justification
AnswerD

Continued business justification requires the business case to remain valid throughout the project, not merely at initiation. It satisfies the principle that investment is re-evaluated at each stage boundary, and the project stops if justification lapses.

119
MCQhard

A project is in the Initiating a Project process. Which document describes the products to be delivered and the resources required to deliver them?

A.Business Case
B.Project Plan
C.Stage Plan
D.Project Initiation Documentation
AnswerB

The Project Plan documents the products to be delivered and the resources and activities needed to deliver them, satisfying the Initiating a Project requirement. It provides the baseline against which progress is monitored, distinct from the Business Case, which justifies the investment.

Why this answer

The Project Plan in PRINCE2 describes the products to be delivered by the project and the resources required to deliver them. It is created during Initiating a Project and provides the baseline for progress monitoring.

Exam trap

PRINCE2F often tests the confusion between the Project Plan and the Project Initiation Documentation — candidates may pick PID because it sounds comprehensive, but the question asks for the specific document describing products and resources.

How to eliminate wrong answers

Option A is wrong because the Business Case justifies the project and documents costs and benefits, not the products and resources. Option C is wrong because a Stage Plan covers a single stage, not the entire project's products and resources. Option D is wrong because the Project Initiation Documentation is the collection of documents including the Project Plan, Business Case, and others — it is the container, not the specific document describing products and resources.

120
MCQmedium

A project manager is working on a project to develop a new software product. The Project Board has set tolerances for time and cost, and the project manager is managing the project within these tolerances. The project manager needs to escalate an issue to the Project Board because the project is forecast to exceed the time tolerance. Which PRINCE2 principle is being applied when the project manager escalates the issue to the Project Board?

A.Continued business justification
B.Focus on products
C.Manage by exception
D.Learn from experience
AnswerC

Manage by exception involves setting tolerances and delegating authority to the Project Manager to manage within those tolerances. When the project is forecast to exceed the time tolerance, the Project Manager must escalate to the Project Board, which is exactly what this principle prescribes. This ensures that the Project Board is only involved when necessary.

Why this answer

Manage by exception is applied when the Project Manager escalates an issue to the Project Board because the project is forecast to exceed the time tolerance. This principle establishes tolerances and delegates authority, ensuring that the Project Board is only involved when exceptions occur, allowing for efficient project management.

Exam trap

The trap here is thinking that continued business justification is the reason for escalation, but escalation due to tolerance breach is specifically about manage by exception.

121
MCQmedium

A Project Board is considering whether to authorize the initiation of a project. Which document should they review?

A.Project Brief
B.Business Case
C.Stage Plan
D.Project Initiation Documentation
AnswerA

The Project Brief is the output of Starting Up a Project and contains the outline Business Case, project definition and approach. The Project Board reviews it to decide whether to authorise initiation, which then produces the Project Initiation Documentation.

Why this answer

The Project Brief contains the outline Business Case, project approach, and other information needed for the Project Board to decide whether to proceed to initiation.

122
Drag & Dropmedium

Drag and drop the steps to manage a risk in PRINCE2 into the correct order.

Drag or tap steps into the slots.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4

Why this order

The PRINCE2 risk management procedure follows: identify, assess, plan responses, implement, and monitor.

123
Multi-Selecthard

A project is being initiated to develop a new customer relationship management (CRM) system. The Project Manager is applying the PRINCE2 principle 'learn from experience'. Which two actions should she take to ensure this principle is applied effectively? (Choose two.)

Select 2 answers
A.Review the lessons log from previous projects to identify relevant lessons that could affect the CRM project.
B.Include a lesson learned in the End Stage Report about the effectiveness of the risk management approach used during the stage.
C.Ensure that the project's Business Case is updated at each stage boundary with actual progress and revised forecasts.
D.Delegate authority to the Project Manager to manage the stage within agreed tolerances.
E.Define the quality criteria for the CRM system's key products in the Product Descriptions.
AnswersA, B

Reviewing the lessons log from previous projects is a key action for applying the learn from experience principle. It ensures that the project benefits from past successes and failures, avoiding repeated mistakes and leveraging proven practices. This is a direct application of the principle, as it involves seeking out and using lessons from similar projects to inform the current project's approach.

Why this answer

The learn from experience principle requires that lessons are sought, recorded, and acted upon throughout the project. Reviewing lessons logs from previous projects ensures that relevant knowledge is considered from the start. Including a lesson learned in the End Stage Report captures current experience for future use.

These two actions directly apply the principle, whereas updating the Business Case, delegating authority, and defining quality criteria relate to other principles.

Exam trap

The trap here is selecting actions that are important in PRINCE2 but belong to other principles, such as continued business justification or focus on products, instead of actions that specifically capture and apply lessons.

124
Multi-Selecthard

Which TWO of the following statements about the Executive role are correct?

Select 2 answers
A.The Executive chairs the Project Board
B.The Executive approves all Work Packages
C.The Executive manages the project on a day-to-day basis
D.The Executive is responsible for the Business Case
E.The Executive is appointed after the project brief is approved
AnswersA, D

The Executive chairs the Project Board, owning the Business Case and holding ultimate accountability for the project's success. As chair, the Executive drives decision-making and represents the business interest, ensuring the project remains justified and aligned with corporate strategy.

Why this answer

Option A is correct because in PRINCE2 the Executive is the senior responsible owner who chairs the Project Board, owning the 'business' perspective and being accountable for the project's success. Option D is correct because the Executive is specifically accountable for the Business Case, ensuring it demonstrates continuing business justification and viability throughout the project. Option B is incorrect because approving Work Packages is delegated to the Project Manager, not the Executive.

Option C is incorrect because day-to-day management is the Project Manager's responsibility, not the Executive's. Option E is incorrect because the Executive is appointed by the commissioning organization before the project starts, during the Starting up a Project process, not after the Project Brief is approved.

Exam trap

PeopleCert often tests the distinction between the Executive's strategic accountability and the Project Manager's operational responsibility, leading candidates to confuse who approves Work Packages or manages daily tasks.

125
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Project Plan
B.Project Initiation Documentation
C.Project Brief
D.Business Case
AnswerB

The Project Initiation Documentation is the key output of Initiating a Project, consolidating the Business Case, Project Plan, and approach documents. It satisfies the process's purpose of establishing a firm baseline before the Project Board authorises the project to proceed.

Why this answer

The Project Initiation Documentation (PID) is the key output of Initiating a Project.

126
MCQmedium

During the Initiating a Project (IP) process, which document is created to define how the project will be executed, monitored, and controlled?

A.Project Initiation Documentation
B.Project Brief
C.Project Plan
D.Business Case
AnswerA

The Project Initiation Documentation is assembled during Initiating a Project, containing the Project Plan, Business Case, risk and quality approaches. It satisfies the requirement to define how the project will be executed, monitored and controlled before the Project Board authorises the project.

Why this answer

The Project Initiation Documentation (PID) is the definitive document created during the Initiating a Project (IP) process. It consolidates all key information—including the Business Case, Project Plan, and controls—into a single source that defines how the project will be executed, monitored, and controlled throughout its lifecycle.

Exam trap

PRINCE2 often tests the distinction between documents created in different processes, and the trap here is confusing the Project Brief (from SU) with the Project Initiation Documentation (from IP), as both contain high-level project information but serve different purposes and are created at different stages.

How to eliminate wrong answers

Option B (Project Brief) is wrong because the Project Brief is created during the Starting Up a Project (SU) process as a preliminary outline of the project, not during IP, and it lacks the detailed execution and control definitions found in the PID. Option C (Project Plan) is wrong because the Project Plan is a component within the PID that focuses specifically on the schedule and resources, not the overarching governance, monitoring, and control mechanisms. Option D (Business Case) is wrong because the Business Case justifies the project's viability and is also a component of the PID, but it does not define how the project will be executed, monitored, and controlled.

127
MCQmedium

A programme manager has assigned a project manager to deliver a new customer portal. The programme manager will define the project mandate, but the project manager must create the project brief. According to PRINCE2, what is the primary purpose of the project brief?

A.It authorizes the project manager to start the first delivery stage and commit resources.
B.It serves as the contract between the supplier and the customer, defining the acceptance criteria and payment terms.
C.It documents the detailed business case, including benefits, costs, and risks, that will be baselined at the end of initiation.
D.It provides sufficient information for the project board to decide whether it is worthwhile to initiate the project.
AnswerD

The project brief is the pre-project document that gives the project board enough information to authorize the Initiating a Project process. It contains the project definition, outline business case, and project approach, allowing a go/no-go decision on whether to invest in the more detailed initiation work.

Why this answer

The project brief is created before the project starts and gives the project board the information it needs to decide whether to authorize the initiation stage. It includes the outline business case, project definition, and project approach, but not the detailed baselined products that come later in the project initiation documentation.

Exam trap

The trap here is confusing the project brief with the project initiation documentation, assuming the brief contains the detailed business case or authorizes delivery.

128
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do first?

A.Issue an Exception Report to the Project Board
B.Update the Business Case to reflect the new cost
C.Close the project as it is no longer viable
D.Approve additional budget using contingency
AnswerA

Forecast breach of a cost tolerance is an exception, so the Project Manager escalates by issuing an Exception Report to the Project Board, which decides how to respond. This satisfies the stem's first action, since tolerances cannot be exceeded without Board authorisation.

Why this answer

In PRINCE2, when a project is forecast to exceed a tolerance (in this case cost tolerance), the Project Manager must escalate the deviation to the Project Board by producing an Exception Report. The Project Board then decides whether to approve a change, request more information, or take corrective action. This is the defined 'manage by exception' principle — the Project Manager does not unilaterally approve additional budget or change the Business Case.

Exam trap

PRINCE2F often tests the boundary between Project Manager and Project Board authority — candidates incorrectly pick 'approve additional budget' or 'update the Business Case' because those seem like logical next steps, but both are Board-level decisions, not PM actions.

How to eliminate wrong answers

Option B is wrong because updating the Business Case is a Project Board responsibility (the Business Case is owned by the Executive) and would only follow a Board decision, not precede it. Option C is wrong because closing the project is a Project Board decision based on continued business justification; the Project Manager cannot close a project simply because a tolerance is forecast to be exceeded. Option D is wrong because approving additional budget (drawing on contingency) is a Project Board authority, not the Project Manager's — the Project Manager's role is to report the exception and recommend options, not to authorize the spend.

129
MCQhard

Which of the following is a characteristic of a project, as defined by PRINCE2?

A.It is a permanent organization with ongoing operations
B.It introduces no change to the organization
C.It is part of business as usual
D.It produces a unique product, service, or result
AnswerD

PRINCE2 defines a project as a temporary organisation created to deliver one or more business products according to an agreed Business Case. Uniqueness of the product, service or result is a defining characteristic, distinguishing projects from routine operational work.

Why this answer

PRINCE2 defines a project as a temporary organization created for the purpose of delivering one or more business products according to an agreed Business Case. A defining characteristic is that it produces a unique product, service, or result, and it is finite in duration with defined start and end points. Option D captures this core PRINCE2 principle that projects are distinct from business as usual because they deliver something new and unique.

Exam trap

PRINCE2F often tests the distinction between projects and business as usual, and candidates commonly confuse the temporary nature of projects with the permanence of operational organizations.

How to eliminate wrong answers

Option A is wrong because PRINCE2 explicitly defines a project as a temporary organization, not a permanent one — permanence is a characteristic of business as usual (BAU), not projects. Option B is wrong because projects inherently introduce change; PRINCE2's entire purpose is to manage the change from the current state to a desired future state. Option C is wrong because PRINCE2 draws a sharp distinction between projects and business as usual — projects are temporary endeavors that sit outside routine operations.

130
Multi-Selectmedium

Which THREE of the following are PRINCE2 practices (themes)?

Select 3 answers
A.Waterfall
B.Risk
C.Sprint Planning
D.Quality
E.Business Case
AnswersB, D, E

Risk is one of the seven PRINCE2 practices, alongside business case, organisation, plans, quality, change and progress. It satisfies the stem's requirement by being a recognised practice, governing how the project team identifies, assesses and controls uncertainty throughout each stage of the project lifecycle.

Why this answer

In PRINCE2, the seven themes (now called practices in PRINCE2 2017) describe aspects of project management that must be addressed continually, and Risk (B), Quality (D), and Business Case (E) are three of them. Risk (B) is correct because PRINCE2 requires a Risk theme/practice covering risk identification, assessment, and response throughout the project. Quality (D) is correct because the Quality theme/practice defines how the project will verify that products meet requirements and achieve fitness for purpose.

Business Case (E) is correct because the Business Case theme/practice ensures the project remains desirable, viable, and achievable, justifying continued investment. Waterfall (A) is not a PRINCE2 theme but a sequential development approach, and Sprint Planning (C) is a Scrum event, not a PRINCE2 practice.

131
MCQeasy

Which PRINCE2 process is triggered by the Project Mandate and produces the Project Brief?

A.Managing a Stage Boundary
B.Directing a Project
C.Initiating a Project
D.Starting Up a Project
AnswerD

Starting Up a Project is triggered by the Project Mandate and produces the Project Brief, along with the initiation stage plan. It precedes Initiating a Project, which then develops the Project Initiation Documentation from that brief.

Why this answer

The Starting Up a Project process is triggered by the Project Mandate and produces the Project Brief. This process ensures that the project has a viable business case and that the necessary resources and stakeholders are identified before any detailed planning begins. The Project Brief is the key output that summarizes the project's justification, scope, and approach, serving as the foundation for the Initiating a Project process.

Exam trap

The trap here is that candidates often confuse the Starting Up a Project process with Initiating a Project, mistakenly thinking the Mandate triggers the creation of the PID, but PRINCE2 explicitly separates the initial viability check (Starting Up) from detailed planning (Initiating).

How to eliminate wrong answers

Option A is wrong because Managing a Stage Boundary is triggered at the end of each management stage to plan the next stage and update the business case, not by the Project Mandate. Option B is wrong because Directing a Project is the process for the Project Board to make key decisions and monitor progress, not to produce the Project Brief from the Mandate. Option C is wrong because Initiating a Project uses the Project Brief to create the Project Initiation Documentation (PID), but it is not triggered by the Mandate; the Mandate triggers Starting Up a Project first.

132
Multi-Selecthard

A project board is reviewing the PRINCE2 principles with a newly appointed project manager. The board wants to emphasize that PRINCE2 is a flexible method that must be adapted to the project's context while still maintaining essential governance. Which TWO of the following statements correctly describe how PRINCE2 principles are applied? (Choose two.)

Select 2 answers
A.A project can omit the 'manage by exception' principle if the project board prefers to be involved in all decisions.
B.If a project is small, the project manager can decide to apply only the principles that are most relevant to that project.
C.The 'learn from experience' principle only applies at the end of the project during the Closing a Project process.
D.Tailoring can affect processes, themes, roles, and management products, but it cannot remove any of the seven principles.
E.The seven principles must be applied in every project, but they can be tailored in how they are implemented.
AnswersD, E

Tailoring allows adaptation of processes, themes, roles, terminology, and management products to suit the project. However, all seven principles must remain applied; tailoring cannot be used to justify removing a principle such as continued business justification or manage by exception. This statement accurately reflects the relationship between tailoring and principles.

Why this answer

PRINCE2 requires all seven principles to be applied on every project, but tailoring allows the method to be adapted to the project's environment. Processes, themes, roles, and management products can be tailored, but principles cannot be removed. The statements that all principles must be applied and that tailoring cannot remove principles correctly describe this relationship.

Exam trap

The trap here is believing that a small or low-risk project can omit principles that seem less relevant, when in fact all seven principles remain mandatory and only their implementation is tailored.

133
MCQhard

A project manager is running a PRINCE2 project to implement a new customer relationship management system. The project board has asked for assurance that the project remains aligned with corporate strategy and that the investment is still justified. Which PRINCE2 theme directly addresses the ongoing viability of the project and the justification for the investment?

A.Risk
B.Progress
C.Organization
D.Business Case
AnswerD

The business case theme is concerned with establishing whether the project is desirable, viable and achievable, and with maintaining that justification throughout the project. In this CRM implementation, the project board uses the business case to confirm continued alignment with corporate strategy and to decide whether to continue, change or stop the project. This theme directly addresses ongoing viability and investment justification, making it the correct answer.

Why this answer

The business case theme in PRINCE2 ensures that the project remains desirable, viable and achievable, and it is the mechanism through which the project board confirms ongoing alignment with corporate strategy and justifies continued investment. Other themes support this, but the business case is the owner of continued business justification. Therefore, the correct answer is the business case theme.

Exam trap

The trap here is confusing themes that support the business case, such as risk or progress, with the theme that directly owns ongoing viability and investment justification.

134
MCQmedium

A programme manager is setting up a new project to develop a mobile banking app. The organisation already has a Programme Office that provides templates, tools, and assurance reviews. The project manager is deciding how to tailor PRINCE2 for this project. Which principle of PRINCE2 supports the decision to use the Programme Office's templates and assurance reviews?

A.Manage by stages
B.Continued business justification
C.Learn from experience
D.Tailor to suit the project environment
AnswerD

This principle requires PRINCE2 to be adapted to the project's size, complexity, and organisational context. Using the Programme Office's templates and assurance reviews is an example of tailoring to the existing environment, ensuring the method fits the organisation's standards and governance without reinventing processes.

Why this answer

The principle 'Tailor to suit the project environment' explicitly requires that PRINCE2 be adapted to the project's context, including organisational standards, tools, and governance. Leveraging the Programme Office's templates and assurance reviews is a direct application of this principle, ensuring the method is fit for purpose without unnecessary duplication.

Exam trap

The trap here is confusing tailoring with learning from experience, since both involve using past or existing assets, but tailoring is about adapting the method to the environment, not about actively seeking lessons.

135
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Close the project
B.Continue and report later
C.Raise an Exception Report
D.Increase the project budget
AnswerC

Cost tolerance breach means the stage or project plan can no longer be delivered within its agreed limits, so the deviation must be escalated to the Project Board. The Exception Report documents the cause, impact and options, enabling the Board to decide whether to authorise a revised plan.

Why this answer

The PM must escalate via an Exception Report to the Project Board.

136
MCQmedium

What is the difference between a Request for Change and an Off-specification in PRINCE2?

A.A Request for Change is raised by the Project Manager; an Off-specification is raised by the Team Manager
B.A Request for Change is always urgent; an Off-specification is not
C.A Request for Change proposes a change to a product; an Off-specification indicates that a product does not meet its specification
D.There is no difference; they are synonymous
AnswerC

These are distinct issue types on different axes. A Request for Change asks to alter an already-agreed product's baseline, whereas an Off-specification reports that a product has failed to meet its agreed specification. Both are captured in the Issue Register and assessed for impact.

Why this answer

In PRINCE2, a Request for Change (RFC) is a formal proposal to change a product's specification, baseline, or agreed-upon configuration, while an Off-specification is a notification that a product does not meet its agreed specification or that a planned product cannot be delivered as defined. The RFC seeks approval for a change, whereas the Off-specification reports a deviation that has already occurred or is inevitable.

Exam trap

The trap here is that candidates confuse the direction of the issue: an RFC is about changing the specification for future products, while an Off-specification is about a product already failing to meet the current specification, and PRINCE2 tests this distinction by offering options that blur the roles or urgency.

How to eliminate wrong answers

Option A is wrong because both RFCs and Off-specifications can be raised by any project stakeholder, not exclusively by the Project Manager or Team Manager; the Project Manager is responsible for reviewing and escalating them, but the raising party is not restricted. Option B is wrong because urgency is not a defining characteristic of an RFC; an RFC can be urgent or routine, and an Off-specification can also be urgent if it threatens project delivery. Option D is wrong because RFCs and Off-specifications are distinct concepts: an RFC proposes a change to a product's specification, while an Off-specification reports a failure to meet the existing specification.

137
MCQeasy

Which principle of PRINCE2 is being applied when a project is divided into management stages?

A.Manage by exception
B.Focus on products
C.Learn from experience
D.Manage by stages
AnswerD

Dividing a project into management stages directly enacts the Manage by Stages principle, which requires that the project be planned, monitored and controlled stage by stage. The stem's act of splitting work into discrete management stages is precisely this principle in operation.

Why this answer

The PRINCE2 principle 'Manage by Stages' states that a project must be planned, monitored, and controlled on a stage-by-stage basis, with each management stage providing a control point for the project board. Dividing a project into management stages is the direct application of this principle. It enables incremental governance and go/no-go decisions at stage boundaries.

Exam trap

PRINCE2F often tests the confusion between principles that sound similar in governance contexts — 'Manage by Stages' (stage division) versus 'Manage by Exception' (tolerance-based escalation) — so candidates must match the principle to its precise definition.

How to eliminate wrong answers

Option A is wrong because 'Manage by Exception' concerns defining tolerances and escalating only when they are breached — it is about delegation and control thresholds, not stage division. Option B is wrong because 'Focus on Products' emphasizes defining and delivering products with agreed quality criteria, not structuring the project into stages. Option C is wrong because 'Learn from Experience' is about capturing and applying lessons throughout the project, not about stage-based governance.

138
MCQhard

In PRINCE2, what is the difference between tailoring and embedding?

A.Tailoring is done by the Project Board; embedding is done by the Project Manager
B.They are the same thing
C.Tailoring adapts PRINCE2 to a specific project; embedding incorporates PRINCE2 into the organization's culture
D.Tailoring is for large projects; embedding is for small projects
AnswerC

Tailoring adapts PRINCE2's processes, themes and roles to suit a specific project's scale and complexity, whereas embedding integrates the method into an organisation's culture and working practices. This distinction satisfies the stem by separating project-level adaptation from organisation-wide adoption.

Why this answer

Tailoring is adapting PRINCE2 to the project's specific context. Embedding is integrating PRINCE2 into the organization's management system.

139
MCQmedium

A project manager is reviewing a project that has been running for three months. The business case was approved with a cost tolerance of +/- 10%. The project has already spent 95% of the budget but has only completed 40% of the scope. The project board is meeting to decide the project's fate. The project manager should advise the board to:

A.Request a budget increase and complete the project
B.Continue as planned but monitor costs more tightly
C.Recommend closure of the project because the business case is no longer viable
D.Proceed with an exception plan without board approval
AnswerC

Spending 95% of budget against only 40% of scope breaches the approved +/-10% cost tolerance, so the business case no longer holds. Recommending closure lets the board stop further investment rather than continue a project whose forecast benefits cannot justify remaining spend.

Why this answer

The project has consumed 95% of the budget while delivering only 40% of the scope, making the original business case no longer viable. PRINCE2 requires continuous business justification; if the costs outweigh the benefits, the project should be closed. The project manager must advise the board to close the project as continuing would waste further resources.

Exam trap

PeopleCert often tests the misconception that a project can be saved by simply requesting more budget or monitoring costs, but PRINCE2 demands that the business case be re-evaluated when tolerance is breached, and if it is no longer viable, the project must be closed.

How to eliminate wrong answers

Option A is wrong because requesting a budget increase without reassessing the business case ignores the fundamental PRINCE2 principle of continued business justification; the board must first determine if the revised costs still deliver acceptable benefits. Option B is wrong because continuing as planned with tighter cost monitoring does not address the severe budget overrun (95% spent for 40% scope) and violates the principle of managing by stages, as the current stage is already out of tolerance. Option D is wrong because an exception plan must be approved by the project board; proceeding without board approval bypasses the PRINCE2 control process and the board's authority to decide the project's fate.

140
Multi-Selecthard

A project manager is preparing to tailor PRINCE2 for a small, low-risk project to update an internal website. The project manager wants to ensure that the tailoring is appropriate and does not compromise the principles. Which TWO of the following are valid considerations when tailoring PRINCE2 for this project? (Choose two.)

Select 2 answers
A.Skipping the Initiating a Project process and starting directly with Controlling a Stage.
B.Eliminating the Project Board and having the Project Manager report directly to the Programme Manager.
C.Reducing the number of management stages to one, as long as the Project Board still authorizes the project and reviews progress at key points.
D.Removing the Business Case theme entirely because the project is low-risk and internal.
E.Combining roles, such as having the Project Manager also act as the Team Manager, provided there is no conflict of interest.
AnswersC, E

Tailoring the number of stages is valid for small projects, provided that the Project Board retains control and can review progress. A single stage may be sufficient for a low-risk website update, but the Project Board must still authorize the project and review at key points to maintain the manage by exception principle and overall control.

Why this answer

Tailoring PRINCE2 for small projects allows combining roles and reducing stages, as long as the principles are maintained. Combining roles like Project Manager and Team Manager is acceptable if there is no conflict, and a single stage can be used if the Project Board still authorizes and reviews progress. Removing the Business Case, Project Board, or Initiating a Project process would violate PRINCE2 principles.

Exam trap

The trap here is thinking that tailoring means eliminating elements like the Business Case or Project Board, when in fact tailoring must still adhere to the seven principles.

← PreviousPage 2 of 2 · 140 questions total

Ready to test yourself?

Try a timed practice session using only Overview of PRINCE2 and the project environment questions.