PRINCE2F Practice Question: Overview of PRINCE2 and the project environment

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board

According to the management by exception principle, exceeding tolerance must be escalated to the Project Board via an Exception Report.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Continue and report in the next Highlight Report

    Why it's wrong here

    Immediate escalation is required.

  • Raise an Exception Report to the Project Board

    Why this is correct

    Correct; this triggers management by exception.

  • Increase the budget to cover the overrun

    Why it's wrong here

    The Project Manager cannot change tolerances without Board approval.

  • Close the project immediately

    Why it's wrong here

    The Board decides whether to close or not.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.