PRINCE2F Practice Question: Overview of PRINCE2 and the project environment

A Project Board is considering whether to authorize the initiation of a project. Which document should they review?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Brief

The Project Brief contains the outline Business Case, project approach, and other information needed for the Project Board to decide whether to proceed to initiation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project Brief

    Why this is correct

    The Project Brief is the output of Starting Up a Project and contains the outline Business Case, project definition and approach. The Project Board reviews it to decide whether to authorise initiation, which then produces the Project Initiation Documentation.

  • ✗

    Business Case

    Why it's wrong here

    The Business Case justifies the project and is reviewed at the end of the Starting up a Project process, but it is not the document the Board reviews to authorise initiation. This is tempting because the Business Case underpins the decision, yet authorisation of initiation requires the Project Initiation Documentation.

  • ✗

    Stage Plan

    Why it's wrong here

    A Stage Plan covers a single management stage and is produced during initiation, so it cannot exist when the Board authorises initiation. This is tempting because Stage Plans are Board-approved documents, but they are created later; the correct document is the Project Initiation Documentation.

  • ✗

    Project Initiation Documentation

    Why it's wrong here

    The Project Initiation Documentation is reviewed at the end of the Initiating a Project process to authorise the project itself, not its initiation. This is tempting because it is the Board's key approval document, but authorising initiation requires the Project Brief, assembled during Starting up a Project.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.