CCNA Pkp Project Lifecycle Questions

15 of 165 questions · Page 3/3 · Pkp Project Lifecycle topic · Answers revealed

151
MCQeasy

What is the primary purpose of a Work Breakdown Structure (WBS) in project planning?

A.To break down the project scope into smaller, manageable components
B.To identify project risks
C.To create the project schedule
D.To assign resources to tasks
AnswerA

The WBS hierarchically decomposes scope into work packages.

Why this answer

A WBS decomposes the project scope into manageable work packages, forming the basis for estimating, scheduling, and controlling work.

152
MCQmedium

A project manager is estimating the cost of a new software development project. Since the project is similar to a previous one, the manager uses the cost of the previous project as a basis, adjusting for known differences. Which cost estimation technique is being used?

A.Parametric estimation
B.Bottom-up estimation
C.Analogous estimation
D.Three-point estimation
AnswerC

Analogous estimation relies on similarity to previous projects.

Why this answer

Analogous estimation uses historical data from similar projects to estimate costs. It is often used when limited information is available about the current project.

153
MCQmedium

During project planning, the team creates a hierarchical decomposition of the total scope of work to be carried out by the project team. Each descending level represents an increasingly detailed definition of the project work. What is this called?

A.Network diagram
B.Project schedule
C.Work Breakdown Structure (WBS)
D.Risk register
AnswerC

Correct. The WBS decomposes the total scope into manageable work packages.

Why this answer

The Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team. It organizes and defines the total scope of the project, with each level providing more detail.

154
MCQmedium

A project team is in the process of obtaining seller responses, evaluating proposals, and awarding a contract. Which procurement document is used to formally request a proposal from potential sellers?

A.Request for Information (RFI)
B.Request for Quote (RFQ)
C.Request for Proposal (RFP)
D.Statement of Work (SOW)
AnswerC

RFP is used to request proposals.

Why this answer

A Request for Proposal (RFP) is used to solicit proposals from sellers.

155
MCQmedium

A project manager is developing a network diagram and needs to represent an activity that can start only after its predecessor has finished. Which dependency type does this describe?

A.Finish-to-Start (FS)
B.Start-to-Start (SS)
C.Finish-to-Finish (FF)
D.Start-to-Finish (SF)
AnswerA

Correct: the successor starts only after the predecessor finishes.

Why this answer

Finish-to-Start (FS) is the most common dependency where the successor cannot start until the predecessor finishes.

156
MCQmedium

During project execution, a stakeholder requests a change to the project scope. What is the first step the project manager should take?

A.Inform the sponsor of the change
B.Submit a change request to the change control board
C.Implement the change immediately
D.Update the project baseline
AnswerB

The change request is the first formal step.

Why this answer

The first step in change control is to document the change request and submit it for impact analysis.

157
Multi-Selectmedium

A project manager is closing a project. Which THREE activities are part of the project closure process? (Select THREE).

Select 3 answers
A.Release project resources
B.Implement risk response strategies
C.Archive project documents
D.Create the Work Breakdown Structure
E.Obtain formal acceptance from the sponsor
AnswersA, C, E

Releasing resources is part of closing.

Why this answer

Project closure includes obtaining formal acceptance, archiving documents, and releasing resources. Risk response strategies are part of execution, and creating the WBS is part of planning.

158
MCQeasy

During the initiating phase of a project, a project charter is created. Which of the following is typically included in a project charter?

A.Project purpose and high-level scope
B.Detailed work breakdown structure
C.Risk register with identified risks
D.Earned value metrics
AnswerA

The project charter defines the high-level scope and purpose of the project.

Why this answer

The project charter includes the project purpose, objectives, high-level scope, budget, schedule, assumptions, constraints, and the authority of the project manager.

159
MCQmedium

A project manager is evaluating risk responses. For a risk with high probability and high impact, which risk response strategy is most appropriate to eliminate the threat?

A.Accept
B.Mitigate
C.Transfer
D.Avoid
AnswerD

Avoidance changes the project plan to completely eliminate the risk.

Why this answer

Avoidance is the only strategy that completely eliminates the threat by changing the project plan to avoid the risk. Transfer shifts liability, mitigate reduces impact/probability, and acceptance acknowledges the risk without action.

160
MCQmedium

A project team is experiencing conflicts and power struggles among members. According to Tuckman's stages of group development, which stage is the team likely in?

A.Performing
B.Storming
C.Forming
D.Norming
AnswerB

Storming involves conflict, power struggles, and resistance to group influence.

Why this answer

In the storming stage, team members may have differing opinions, leading to conflicts and power struggles as they assert themselves.

161
Multi-Selecteasy

Which TWO of the following are outputs of the monitoring and controlling process group? (Select two.)

Select 2 answers
A.Project charter
B.Risk register
C.Work breakdown structure
D.Performance reports
E.Change requests
AnswersD, E

Performance reports are outputs of monitoring and controlling.

Why this answer

Performance reports and change requests are typical outputs of monitoring and controlling. The project charter is an output of initiating, and the risk register is an output of planning.

162
MCQeasy

A project manager is preparing a procurement document that asks vendors to provide a price for a specific product. Which type of document is this?

A.Request for quotation (RFQ)
B.Request for proposal (RFP)
C.Request for information (RFI)
D.Statement of work (SOW)
AnswerA

RFQ is used to request a price for a specific product.

Why this answer

A request for quotation (RFQ) is used to obtain a price for a specific item.

163
Multi-Selecteasy

During project closing, a project manager must complete several activities. Which TWO are appropriate for project closure?

Select 2 answers
A.Create the project charter
B.Update the risk register
C.Archive project documents
D.Develop the project schedule
E.Obtain formal acceptance of deliverables from the sponsor
AnswersC, E

Correct. Archiving documents is part of closing.

Why this answer

Project closure includes formal acceptance from the sponsor/customer and archiving project documents. Releasing resources and lessons learned are also closure activities, but the question asks for TWO from the options.

164
MCQmedium

A vendor is hired to provide a service with a fixed price of $100,000, regardless of actual costs incurred. Which contract type is this?

A.Fixed-price
B.Time and Materials (T&M)
C.Cost-reimbursable
D.Cost-plus
AnswerA

Correct: fixed-price has a set price.

Why this answer

A fixed-price contract has a predetermined price that does not change based on the seller's cost performance.

165
Multi-Selecthard

A project manager is planning risk responses for identified risks. Which THREE are valid risk response strategies?

Select 3 answers
A.Ignore
B.Enhance
C.Avoid
D.Mitigate
E.Transfer
AnswersC, D, E

Correct: Avoid involves eliminating the risk.

Why this answer

The main risk response strategies are Avoid, Transfer, Mitigate, and Accept. Enhance is for opportunities, not threats.