During project execution, a stakeholder requests a change to the project scope. What is the first step the project manager should take?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to the change control board

The first step in change control is to document the change request and submit it for impact analysis.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Inform the sponsor of the change

    Why it's wrong here

    The sponsor may be informed, but the first step is to submit a change request.

  • Submit a change request to the change control board

    Why this is correct

    The change request is the first formal step.

  • Implement the change immediately

    Why it's wrong here

    Changes must go through the change control process.

  • Update the project baseline

    Why it's wrong here

    Baselines are updated only after approval.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.