PK0-005 Project Life Cycle Practice Question
A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Team members question the project manager's authority and disagree on tasks.
In the storming stage, team members may challenge each other and the project manager, leading to conflicts as they establish roles.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Team members disengage as the project ends.
Why it's wrong here
That describes adjourning.
- ✗
Team members are polite and avoid conflict.
Why it's wrong here
That describes forming.
- ✗
Team members work collaboratively and efficiently.
Why it's wrong here
That describes performing.
- ✓
Team members question the project manager's authority and disagree on tasks.
Why this is correct
Correct: Storming involves conflict and questioning.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.