Question 713 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

Vendor Delay on Critical Path: Implement Pre-Planned Risk Response

This PMP practice question tests your understanding of process — managing technical aspects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A key vendor informs you that they cannot deliver a critical component on time due to a raw material shortage. This component is on the critical path. The vendor has a history of poor performance. What should the project manager do FIRST?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Implement the risk response plan that was developed for this vendor risk

Option C is correct because the project manager should first implement the risk response plan that was developed for this vendor risk. Since the vendor has a history of poor performance, this risk should have been identified during planning, and a response plan (e.g., using an alternative supplier or buffer stock) should already exist. Acting on the pre-approved plan ensures a structured, timely response without unnecessary delays or escalation.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Immediately contact alternative vendors to find a replacement

    Why it's wrong here

    This may be part of the risk response, but first follow the plan.

  • Perform schedule compression techniques to recover the delay

    Why it's wrong here

    May be needed after implementing the risk response.

  • Implement the risk response plan that was developed for this vendor risk

    Why this is correct

    The risk was identified, so execute the planned response.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Escalate to senior management for a decision

    Why it's wrong here

    Escalation should be a last resort.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often jump to reactive solutions (like finding a new vendor or compressing the schedule) instead of first consulting the pre-planned risk response, which is the correct first step per PMBOK's risk management process.

Detailed technical explanation

How to think about this question

In project risk management, the risk response plan is a documented strategy that includes specific actions, triggers, and owners for handling identified risks. For a critical-path vendor with poor performance history, a typical response might include a pre-qualified backup supplier or a contractual penalty clause. Implementing this plan first ensures alignment with the risk register and avoids ad-hoc decisions that could introduce new risks or violate procurement agreements.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Implement the risk response plan that was developed for this vendor risk — Option C is correct because the project manager should first implement the risk response plan that was developed for this vendor risk. Since the vendor has a history of poor performance, this risk should have been identified during planning, and a response plan (e.g., using an alternative supplier or buffer stock) should already exist. Acting on the pre-approved plan ensures a structured, timely response without unnecessary delays or escalation.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

4 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A critical vendor informs you that they cannot deliver a key component on time due to a raw material shortage. The component is on the critical path. You have identified this risk in the risk register with a medium probability and high impact. The planned response was to accept the risk. What should you do first?

hard
  • A.Escalate to the project sponsor for decision
  • B.Evaluate the current situation and determine if the accept response is still appropriate or if a different response is needed; submit a change request if necessary
  • C.Immediately crash the schedule by adding resources to the critical path
  • D.Inform stakeholders that the project will be delayed by the duration of the component shortage

Why B: Option B is correct because the first step when a risk materializes is to reassess the situation against the existing risk response. Since the planned response was 'accept,' you must evaluate whether acceptance is still viable given the new reality. If not, you need to select a different response (e.g., mitigate or avoid) and submit a change request to formally adjust the project plan. This aligns with the PMBOK® Guide's iterative risk management process, where risk responses are revisited when triggers occur.

Variation 2. A key vendor notifies you that they cannot deliver a critical component on time due to raw material shortages. This component is on the critical path and has no float. The vendor suggests using a substitute material that meets specifications but costs 20% more. What should the project manager do FIRST?

hard
  • A.Invoke the penalty clause in the vendor contract for late delivery
  • B.Accept the vendor's suggestion to use the substitute material to avoid delay
  • C.Submit a change request to evaluate the substitute material, including cost and schedule impacts
  • D.Look for alternative vendors who can deliver the original component on time

Why C: Option C is correct because any change to the procurement approach (substitute material) requires a change request to assess cost and schedule impacts before approval.

Variation 3. You are the PM for a highway construction project. A key vendor informs you that they cannot deliver the steel beams on time due to a factory fire. This risk was identified in the risk register with a mitigation plan to have a backup supplier. However, the backup supplier's price is 20% higher. Which TWO actions should you take?

medium
  • A.Inform the sponsor about the cost increase and request a budget adjustment
  • B.Add the vendor's failure to the risk register as a new risk
  • C.Authorize the team to source alternative materials locally
  • D.Execute the contingency plan and engage the backup supplier
  • E.Update the project management plan to use a different construction method

Why A: Option A is correct because when the identified risk materializes, the contingency plan (backup supplier) should be executed, but the associated cost increase must be communicated to the sponsor and a budget adjustment should be requested. Option D is correct because the previously planned contingency plan is to engage the backup supplier, which is the appropriate immediate action. Option B is incorrect because the vendor's failure is not a new risk—it is the occurrence of an already identified risk. Option C is incorrect because sourcing alternative materials locally would bypass the established contingency plan and could introduce new risks without proper evaluation. Option E is incorrect because changing the construction method would require a formal change request and is not the immediate response to the risk occurrence.

Variation 4. During project execution, a key vendor notifies you that they cannot deliver a critical component on time due to a raw material shortage. This component is on the critical path. The vendor suggests using a substitute material that is not yet approved by your quality team. What should the project manager do FIRST?

hard
  • A.Implement the risk response defined in the risk register
  • B.Accept the delay and update the project schedule
  • C.Escalate to the project sponsor and request additional time
  • D.Immediately terminate the vendor contract and find a new supplier

Why A: Option A is correct because the risk (vendor delay) was previously identified and documented in the risk register, along with a planned response. The project manager should first implement that planned response rather than taking other actions. Option B is incorrect because accepting the delay without trying the planned response is premature and may not be the best course of action. Option C is incorrect because escalation is not necessary if a pre-planned risk response exists. Option D is incorrect because immediately terminating the contract is an extreme reaction that ignores the agreed-upon risk response.

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.