Question 346 of 892
Process — Managing Technical AspectsmediumMultiple SelectObjective-mapped

Two Schedule Compression Techniques That Don't Significantly Increase Cost

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project is running behind schedule. You need to compress the schedule without significantly increasing cost. Which TWO techniques should you consider?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Add resources from non-critical path activities to critical path tasks

Option A is correct because adding resources from non-critical path activities to critical path tasks is a form of resource leveling or resource optimization that can compress the schedule without significant cost increase, as it reallocates existing resources rather than hiring new ones. Option B is correct because fast-tracking involves performing activities in parallel that were originally planned sequentially, which can reduce the project duration without adding costs, though it may increase risk.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Add resources from non-critical path activities to critical path tasks

    Why this is correct

    Crashing with available resources can compress schedule with minimal cost if resources are already allocated.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Fast-track activities by performing them in parallel

    Why this is correct

    Fast-tracking can compress schedule without cost increase but may increase risk.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Eliminate non-essential deliverables without approval

    Why it's wrong here

    Eliminating scope requires formal change control.

  • Reduce quality standards to save time

    Why it's wrong here

    Reducing quality is not acceptable; it increases rework risk.

  • Reduce project scope without change control

    Why it's wrong here

    Scope changes must go through change control; this is not a compression technique.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The PMP exam often tests the distinction between schedule compression techniques (fast-tracking and crashing) and unauthorized scope or quality changes, so candidates may mistakenly choose options that seem to save time but violate project management processes.

Detailed technical explanation

How to think about this question

Schedule compression techniques like fast-tracking and resource leveling are part of the Develop Schedule process in the PMBOK Guide. Fast-tracking increases risk of rework due to overlapping activities, while resource leveling can extend the schedule if not carefully managed. In practice, fast-tracking is often used in construction projects where sequential dependencies are reduced, but it requires careful analysis of lead and lag relationships to avoid negative float.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Add resources from non-critical path activities to critical path tasks — Option A is correct because adding resources from non-critical path activities to critical path tasks is a form of resource leveling or resource optimization that can compress the schedule without significant cost increase, as it reallocates existing resources rather than hiring new ones. Option B is correct because fast-tracking involves performing activities in parallel that were originally planned sequentially, which can reduce the project duration without adding costs, though it may increase risk.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.