Question 869 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project is behind schedule, and you need to compress the schedule. The critical path has been identified. What is the BEST schedule compression technique to use if you have additional budget available?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Crashing

Crashing is the correct technique because it involves adding resources (e.g., overtime, additional staff, or expedited shipping) to critical path activities to compress the schedule, and the question explicitly states additional budget is available. Unlike fast tracking, crashing does not increase risk but does increase cost, making it the best choice when budget is not a constraint.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Fast tracking

    Why it's wrong here

    Fast tracking performs activities in parallel, which can increase risk without additional cost, but the question specifies having additional budget.

  • Crashing

    Why this is correct

    Crashing adds resources to critical path activities to shorten duration, typically with increased cost.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Resource smoothing

    Why it's wrong here

    Resource smoothing adjusts activities without changing critical path length.

  • Resource leveling

    Why it's wrong here

    Resource leveling addresses resource constraints but may increase schedule.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse fast tracking with crashing, thinking both compress the schedule, but fast tracking increases risk while crashing increases cost—and the question explicitly provides additional budget, making crashing the clear choice.

Detailed technical explanation

How to think about this question

Crashing works by analyzing the cost-slope of each critical path activity—the cost per unit time saved—and selecting the activities with the lowest cost-slope to maximize schedule compression for the budget. In practice, crashing may involve adding parallel work shifts, hiring temporary contractors, or paying for expedited material delivery, but it can lead to diminishing returns if applied to non-critical paths or if the critical path changes. A subtle behavior is that crashing only works if the activity is effort-driven (i.e., adding resources reduces duration) and not constrained by physical limits like curing time or sequential dependencies.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Crashing — Crashing is the correct technique because it involves adding resources (e.g., overtime, additional staff, or expedited shipping) to critical path activities to compress the schedule, and the question explicitly states additional budget is available. Unlike fast tracking, crashing does not increase risk but does increase cost, making it the best choice when budget is not a constraint.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.