Question 73 of 892
Process — Managing Technical AspectshardMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project is using a predictive approach. The schedule baseline shows that the project should be 50% complete by now, but only 40% of the work is done. The critical path has been impacted. Several team members are idle because of a dependency conflict. What is the BEST scheduling technique to address this?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Apply resource leveling to resolve the resource conflict and optimize the schedule

Resource leveling is the best technique because the project has idle team members due to a dependency conflict, which is a resource constraint. By adjusting the schedule to resolve the conflict, you can reallocate resources to critical path tasks and optimize the overall schedule without necessarily adding resources or changing the baseline. This directly addresses the root cause of the delay—resource contention—rather than just compressing the schedule.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Apply resource leveling to resolve the resource conflict and optimize the schedule

    Why this is correct

    Resource leveling adjusts the schedule to address resource constraints and reduces idle time.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Rebaseline the schedule to reflect the current progress

    Why it's wrong here

    Rebaselining is not a corrective action; it should only be done after approved changes.

  • Fast track the schedule by performing tasks in parallel

    Why it's wrong here

    Fast tracking increases risk and may not resolve the resource idle issue.

  • Crash the schedule by adding resources to critical path tasks

    Why it's wrong here

    Crashing may be effective but does not address the idle resources due to dependency conflicts.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse resource leveling with crashing or fast tracking, but the key clue is 'idle team members because of a dependency conflict'—this indicates a resource constraint, not a need for schedule compression.

Detailed technical explanation

How to think about this question

Resource leveling is a schedule optimization technique that adjusts start and finish dates based on resource constraints, often extending the project duration to resolve overallocation or conflicts. In predictive (waterfall) projects, it is applied after the critical path is identified, and it can shift non-critical tasks to free up resources for critical path work. A real-world scenario is when a shared specialist (e.g., a network engineer) is needed for two parallel tasks but can only work on one at a time; leveling would sequence those tasks to eliminate idle time.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Apply resource leveling to resolve the resource conflict and optimize the schedule — Resource leveling is the best technique because the project has idle team members due to a dependency conflict, which is a resource constraint. By adjusting the schedule to resolve the conflict, you can reallocate resources to critical path tasks and optimize the overall schedule without necessarily adding resources or changing the baseline. This directly addresses the root cause of the delay—resource contention—rather than just compressing the schedule.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.