Question 434 of 892
Process — Managing Technical AspectshardMultiple ChoiceObjective-mapped

Handling Product Owner Priority Changes During a Sprint

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

In an agile project, the product owner frequently changes priorities within a sprint, causing the team to lose focus and velocity to drop. What should the project manager do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Facilitate a retrospective where the team can discuss the impact of changing priorities and agree on a process

Option B is correct because the project manager should first facilitate a retrospective to allow the team to collaboratively analyze the impact of changing priorities and agree on a process to protect the sprint goal. This aligns with the agile principle of continuous improvement and empowers the team to address the root cause without escalating prematurely or violating sprint commitments.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ask the team to accommodate the changes and work overtime to meet the original commitment

    Why it's wrong here

    Working overtime is not a sustainable solution and may demotivate the team.

  • Facilitate a retrospective where the team can discuss the impact of changing priorities and agree on a process

    Why this is correct

    The team and product owner can collaboratively find a solution that respects both agility and stability.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Escalate to the project sponsor that the product owner is interfering with the team

    Why it's wrong here

    Escalation should be considered after internal resolution attempts fail.

  • Tell the product owner that scope changes are not allowed during a sprint

    Why it's wrong here

    While scope changes are discouraged, the PM should first facilitate a discussion rather than impose rules.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often choose Option D (rigidly enforcing no scope changes) because they confuse the sprint backlog's stability with a complete ban on change, ignoring that agile frameworks allow negotiated trade-offs and that the first step should always be a facilitated team discussion.

Detailed technical explanation

How to think about this question

In Scrum, the sprint backlog is frozen once the sprint starts, but the product owner can negotiate with the team to swap out work if it does not jeopardize the sprint goal. A retrospective is a timeboxed event (typically 1.5 hours for a 2-week sprint) where the team inspects its process and creates a plan for improvements, such as defining a clear definition of done for priority changes or implementing a change control board for mid-sprint requests. In real-world scenarios, teams often use a 'change budget' (e.g., 10% of sprint capacity) to absorb urgent changes without disrupting the sprint goal.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Facilitate a retrospective where the team can discuss the impact of changing priorities and agree on a process — Option B is correct because the project manager should first facilitate a retrospective to allow the team to collaboratively analyze the impact of changing priorities and agree on a process to protect the sprint goal. This aligns with the agile principle of continuous improvement and empowers the team to address the root cause without escalating prematurely or violating sprint commitments.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During an agile project, the product owner frequently changes priorities during the sprint, causing the team to lose focus and miss sprint goals. The team expresses frustration in the retrospective. As the project manager, what should you do?

medium
  • A.Instruct the team to ignore the product owner's changes until the next sprint planning
  • B.Coach the product owner on the importance of not changing priorities during a sprint to protect the team's focus
  • C.Add a buffer to the sprint backlog to accommodate potential changes
  • D.Extend the sprint duration to allow the team to accommodate changes

Why B: Option B is correct because the product owner should be coached on agile principles, specifically the importance of not changing priorities during a sprint to protect the team's focus and sprint goal. Option A is wrong because ignoring the product owner undermines collaboration and agile values. Option C is wrong because adding buffer does not address the root cause and may reduce accountability. Option D is wrong because extending sprint duration does not solve the priority change issue and may lead to loss of time-boxing benefits.

Variation 2. You are managing an agile project. The product owner frequently changes priorities during the sprint, causing the team to lose focus and miss sprint goals. What should the scrum master do?

medium
  • A.Tell the team to ignore the product owner's changes and focus on the original sprint goal.
  • B.Coach the product owner on the importance of sprint goal stability and the impact of changes.
  • C.Ask the product owner to stop changing priorities and escalate to management.
  • D.Request a new product owner who understands agile principles.

Why B: Option B is correct because the scrum master should coach the product owner on their role. Option A is incorrect because the scrum master should not override the product owner. Option C is incorrect; the team cannot change priorities without product owner input. Option D is incorrect; the product owner is not empowered to remove the scrum master.

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.