- A
Inform the sponsor and ask for a decision
Why wrong: While informing the sponsor is important, the PM should first formally document the change request for proper review.
- B
Instruct the team to implement the requirement immediately to ensure compliance
Why wrong: Implementing without a change request bypasses the change control process, even for mandatory requirements.
- C
Submit a change request describing the new requirement and its impact on scope, schedule, and cost
All changes, including mandatory ones, must go through the change control process to assess impact and obtain approval.
- D
Update the project management plan to include the new requirement without formal approval
Why wrong: Updating the plan without approval violates the change control process.
PMP Process — Managing Technical Aspects Practice Question
This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
During a project's execution phase, a new regulatory requirement is discovered that will impact the project scope. The requirement is mandatory and must be implemented. What is the first action the project manager should take?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Submit a change request describing the new requirement and its impact on scope, schedule, and cost
Option C is correct because the PMBOK Guide mandates that any change impacting scope, schedule, or cost must be formally documented and processed through the Integrated Change Control (ICC) process. A change request is the first formal step to capture the new regulatory requirement, its impact on the project baselines, and to obtain approval before implementation. This ensures compliance with the regulatory mandate while maintaining project governance and traceability.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Inform the sponsor and ask for a decision
Why it's wrong here
While informing the sponsor is important, the PM should first formally document the change request for proper review.
- ✗
Instruct the team to implement the requirement immediately to ensure compliance
Why it's wrong here
Implementing without a change request bypasses the change control process, even for mandatory requirements.
- ✓
Submit a change request describing the new requirement and its impact on scope, schedule, and cost
Why this is correct
All changes, including mandatory ones, must go through the change control process to assess impact and obtain approval.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Update the project management plan to include the new requirement without formal approval
Why it's wrong here
Updating the plan without approval violates the change control process.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates confuse 'mandatory' with 'immediate implementation,' forgetting that even mandatory changes must follow the formal change control process to maintain baseline integrity and project governance.
Detailed technical explanation
How to think about this question
Under the hood, the Integrated Change Control process (PMBOK 4.6) requires that all changes to baselines (scope, schedule, cost) be evaluated for impact, documented in a change request, and approved by the Change Control Board (CCB) or authorized stakeholder. In regulated industries (e.g., healthcare, finance), a mandatory regulatory change still requires a formal change request to update the project charter, scope statement, WBS, and schedule—ensuring the change is auditable and traceable. A real-world scenario: a new GDPR requirement during a software project would trigger a change request to assess impact on data handling features, cost for compliance updates, and schedule for testing, rather than immediate implementation.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Process — Managing Technical Aspects — study guide chapter
Learn the concepts, then practise the questions
- →
Process — Managing Technical Aspects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Submit a change request describing the new requirement and its impact on scope, schedule, and cost — Option C is correct because the PMBOK Guide mandates that any change impacting scope, schedule, or cost must be formally documented and processed through the Integrated Change Control (ICC) process. A change request is the first formal step to capture the new regulatory requirement, its impact on the project baselines, and to obtain approval before implementation. This ensures compliance with the regulatory mandate while maintaining project governance and traceability.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More PMP practice questions
- During a sprint review, the product owner rejects a completed user story because it does not meet the acceptance criteri…
- During a daily standup, a developer mentions she is blocked by a dependency from another team. The issue was not previou…
- A project manager is leading a digital transformation initiative. Midway through the project, a new regulation is introd…
- Your project is a large infrastructure build. You have completed the planning phase, but the sponsor has put pressure on…
- You are managing a software development project using a hybrid approach. During a sprint review, the product owner reque…
- Your agile project has been experiencing declining velocity over the last three sprints. During the retrospective, the t…
Last reviewed: Jul 4, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.