- A
Reject the request to avoid scope creep.
Why wrong: Should evaluate the benefit before rejecting.
- B
Accept the request and manage the risk with a contingency plan.
Why wrong: Changes must go through formal change control.
- C
Initiate a change request and present the trade-offs to the change control board.
Following the change management process ensures alignment with project goals.
- D
Ignore the request because it is out of scope.
Why wrong: Ignoring stakeholders can damage relationships.
Quick Answer
The correct answer is to initiate a change request and present the trade-offs to the change control board. This is mandated by the PMBOK Guide because any out-of-scope feature, even one with business value, must follow the formal integrated change control process to protect the project baseline. The project manager’s role is not to decide on scope changes unilaterally but to analyze the request, document the trade-off between added business value and increased risk, and let the Change Control Board (CCB) make an informed governance decision. On the PMP exam, this scenario tests your understanding of scope management and change control procedures, often appearing as a trap where you might be tempted to accept the feature due to its business value. The common mistake is to bypass the CCB and negotiate directly with the stakeholder. Memory tip: “Value does not bypass governance—always route scope changes through the CCB.”
PMP Practice Question: Business Environment: strategy and project benefits
This PMP practice question tests your understanding of business environment: strategy and project benefits. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
During project execution, a key stakeholder requests a feature that is not in the scope. The project manager analyzes the request and determines it would add significant business value but also increase risk. What should the project manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Initiate a change request and present the trade-offs to the change control board.
Option C is correct because the PMBOK Guide mandates that any out-of-scope feature must go through the formal change control process. By initiating a change request, the project manager documents the trade-offs (business value vs. increased risk) and lets the Change Control Board (CCB) make an informed decision, ensuring alignment with project governance and stakeholder expectations.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Reject the request to avoid scope creep.
Why it's wrong here
Should evaluate the benefit before rejecting.
- ✗
Accept the request and manage the risk with a contingency plan.
Why it's wrong here
Changes must go through formal change control.
- ✓
Initiate a change request and present the trade-offs to the change control board.
Why this is correct
Following the change management process ensures alignment with project goals.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Ignore the request because it is out of scope.
Why it's wrong here
Ignoring stakeholders can damage relationships.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates confuse proactive risk management (Option B) with the mandatory change control process, forgetting that any scope change must first be formally approved by the CCB, not just managed with a contingency plan.
Detailed technical explanation
How to think about this question
In project management, the change control system is a documented process that includes submitting a change request, evaluating impacts (cost, schedule, risk, quality), and obtaining CCB approval before implementation. The PM's role is to facilitate this process, not to decide unilaterally. A real-world scenario: a software project receives a request for a new API integration; the PM must submit a change request with a risk assessment (e.g., increased security vulnerabilities) and let the CCB approve or reject based on business priorities.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Business Environment: strategy and project benefits — study guide chapter
Learn the concepts, then practise the questions
- →
Business Environment: strategy and project benefits practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
Business Environment: strategy and project benefits — This question tests Business Environment: strategy and project benefits — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Initiate a change request and present the trade-offs to the change control board. — Option C is correct because the PMBOK Guide mandates that any out-of-scope feature must go through the formal change control process. By initiating a change request, the project manager documents the trade-offs (business value vs. increased risk) and lets the Change Control Board (CCB) make an informed decision, ensuring alignment with project governance and stakeholder expectations.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more ways this is tested on PMP
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. You are a project manager overseeing a 12-month ERP implementation. During sprint 6 of 20, the product owner informs you that a key stakeholder wants to add a new reporting module that was not in the original scope. The team estimates this would add 3 weeks to the schedule. What should you do FIRST?
medium- A.Ask the team to begin work on the module immediately to accommodate the stakeholder
- B.Inform the stakeholder that no changes can be made once the project has started
- C.Add the requirement to the product backlog and let the team address it in a future sprint without formal approval
- ✓ D.Submit a change request through the Integrated Change Control process and assess the impact on scope, schedule, and cost
Why D: Option C is correct because PMI requires all scope changes to go through the Integrated Change Control process. The PM must evaluate the impact and obtain approval before any work begins. Option A is wrong because implementing the change without approval bypasses change control. Option B is wrong because refusing outright without assessing impact is not the correct approach. Option D is wrong because telling the team to start work immediately violates the change control process.
Keep practising
More PMP practice questions
- A project manager is leading a digital transformation initiative. Midway through the project, a new regulation is introd…
- Order the steps for closing a project or phase.
- Sequence the steps for performing a qualitative risk analysis.
- Arrange the steps for controlling project changes.
- Order the steps for performing project quality assurance.
- Order the steps for creating a Work Breakdown Structure (WBS).
Last reviewed: Jun 11, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.