Question 141 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

Managing Team Member Performance Issues

This PMP practice question tests your understanding of process — managing technical aspects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A team member consistently misses deadlines, causing delays in the project. The project manager has had informal conversations with the team member, but the issue persists. What is the BEST next step?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule a private meeting with the team member to discuss the issue, identify root causes, and create a performance improvement plan with clear expectations

Option C is the correct action because it directly addresses the performance issue collaboratively, aiming to understand root causes and set clear expectations through a documented performance improvement plan. This aligns with PM best practices for managing team member performance. Option A is incorrect because reassigning without addressing the root cause may shift the problem rather than solve it. Option B escalates prematurely before attempting direct resolution. Option D is punitive and may damage team morale without understanding underlying issues.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Reassign the team member to a less critical task to minimize impact

    Why it's wrong here

    Avoids the underlying performance issue.

  • Escalate the issue to the team member's functional manager immediately

    Why it's wrong here

    Escalation should come after attempts to resolve directly.

  • Schedule a private meeting with the team member to discuss the issue, identify root causes, and create a performance improvement plan with clear expectations

    Why this is correct

    Direct communication and collaborative problem-solving is the best approach.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Remove the team member from the project and replace them with a more reliable resource

    Why it's wrong here

    Removing without addressing root cause is too drastic and may not be possible.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Schedule a private meeting with the team member to discuss the issue, identify root causes, and create a performance improvement plan with clear expectations — Option C is the correct action because it directly addresses the performance issue collaboratively, aiming to understand root causes and set clear expectations through a documented performance improvement plan. This aligns with PM best practices for managing team member performance. Option A is incorrect because reassigning without addressing the root cause may shift the problem rather than solve it. Option B escalates prematurely before attempting direct resolution. Option D is punitive and may damage team morale without understanding underlying issues.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

3 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A team member consistently misses deadlines, causing delays in dependent tasks. During a one-on-one meeting, the team member admits to feeling overwhelmed and unsure how to prioritize work. What should the project manager do FIRST?

easy
  • A.Reassign the team member's tasks to other team members to avoid further delays
  • B.Provide coaching and training on time management and prioritization techniques
  • C.Inform the project sponsor that a team member is underperforming and may need to be replaced
  • D.Formally document the issue in the team member's performance record

Why B: Option B is correct because the team member's issue stems from feeling overwhelmed and lacking prioritization skills. The project manager should first address the root cause by providing coaching or training on time management and prioritization, which aligns with the PM's role as a servant leader and coach. Option A is incorrect because reassigning tasks without addressing the underlying problem does not help the team member develop and may cause further issues. Option C is incorrect because escalating to the sponsor is premature and should be considered only after the PM has taken appropriate actions to support the team member. Option D is incorrect because documenting in the performance record is punitive and not a first step; the PM should first offer support.

Variation 2. A team member consistently misses deadlines, causing delays for the rest of the team. You have already spoken to the team member informally, but the behavior continues. What is the BEST next step?

easy
  • A.Remove the team member from the project
  • B.Escalate the issue to the team member's functional manager
  • C.Have a formal meeting with the team member to discuss expectations and consequences
  • D.Reassign the team member to less critical tasks

Why C: The PM should address performance issues formally by documenting the issue and discussing it with the team member, setting clear expectations and consequences. This follows a progressive discipline approach.

Variation 3. A team member consistently misses deadlines, causing delays in the sprint. The project manager has had informal conversations, but the issue persists. What is the BEST next step?

medium
  • A.Reassign the work to other team members to avoid delays.
  • B.Schedule a formal meeting to discuss the issue, set clear expectations, and document the conversation.
  • C.Escalate the issue to the team member's functional manager for disciplinary action.
  • D.Remove the team member from the project and request a replacement.

Why B: The PM should follow the performance management process, starting with a documented conversation. Option B is correct. Option A escalates too quickly; Option C avoids the issue; Option D is too drastic.

Keep practising

More PMP practice questions

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.