Question 302 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

What to Do with Lessons Learned: Update Organizational Process Assets

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is closing a project. Several lessons learned were documented throughout the project. What should the PM do with the lessons learned?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit them to the PMO for inclusion in the organizational process assets

Option C is correct because lessons learned are a key input to organizational process assets (OPA). Submitting them to the PMO ensures they are formally captured, stored, and made available for future projects, enabling continuous process improvement. This aligns with the PMBOK Guide's guidance on updating OPAs during project closure.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Include them in the final project report and then discard them

    Why it's wrong here

    Discarding lessons learned is a waste of organizational knowledge.

  • Archive them in the project file for reference only

    Why it's wrong here

    While archiving is part of it, the knowledge should be shared with the organization.

  • Submit them to the PMO for inclusion in the organizational process assets

    Why this is correct

    Lessons learned should be stored in the organizational process assets to benefit future projects.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Distribute them to the project team for their personal development

    Why it's wrong here

    The purpose is organizational learning, not just individual.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may think archiving in the project file (Option B) is sufficient, but PMI emphasizes that lessons learned must be contributed to the organizational process assets to benefit the entire organization, not just the current project team.

Detailed technical explanation

How to think about this question

Lessons learned are a critical component of the 'Close Project or Phase' process (PMBOK Guide 6th Edition, Section 4.7). They are formally documented and stored in the organizational process assets, which include historical information, lessons learned repository, and project files. The PMO typically manages this repository, ensuring that knowledge is not siloed but shared across the organization to improve future project performance and avoid repeated mistakes.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Submit them to the PMO for inclusion in the organizational process assets — Option C is correct because lessons learned are a key input to organizational process assets (OPA). Submitting them to the PMO ensures they are formally captured, stored, and made available for future projects, enabling continuous process improvement. This aligns with the PMBOK Guide's guidance on updating OPAs during project closure.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.