- A
Ask the project sponsor to approve the alternative supplier
Why wrong: The contingency plan should have pre-approved actions; the PM can implement it.
- B
Replan the project schedule to accommodate the delay
Why wrong: Replanning without using the contingency plan may cause unnecessary delays.
- C
Perform a new risk analysis to assess the impact
Why wrong: The risk was already identified and planned; re-assessing may delay response.
- D
Activate the contingency plan and engage the alternative supplier
Since the risk was identified and a contingency plan exists, the PM should implement it.
Implementing Contingency Plans for Identified Risks
This PMP practice question tests your understanding of people — leading projects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A key vendor informs you that due to raw material shortages, they cannot deliver a critical component on time. This component is on the critical path. The risk register included this as a high-probability risk with a contingency plan to use an alternative supplier. What should you do FIRST?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Activate the contingency plan and engage the alternative supplier
D is correct because the risk was already identified, assessed as high-probability, and a contingency plan (alternative supplier) was documented in the risk register. When the risk occurs, the first action is to execute the pre-approved contingency plan, not to reanalyze or seek new approvals, as the plan was already vetted during risk planning.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Ask the project sponsor to approve the alternative supplier
Why it's wrong here
The contingency plan should have pre-approved actions; the PM can implement it.
- ✗
Replan the project schedule to accommodate the delay
Why it's wrong here
Replanning without using the contingency plan may cause unnecessary delays.
- ✗
Perform a new risk analysis to assess the impact
Why it's wrong here
The risk was already identified and planned; re-assessing may delay response.
- ✓
Activate the contingency plan and engage the alternative supplier
Why this is correct
Since the risk was identified and a contingency plan exists, the PM should implement it.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates confuse the need for a new risk analysis or approval with the fact that the contingency plan was already approved and documented, leading them to waste time on unnecessary steps instead of executing the pre-planned response.
Detailed technical explanation
How to think about this question
In project risk management, a contingency plan is a pre-defined set of actions to be taken when a specific risk event occurs, and it is typically included in the risk register with a trigger condition. Activating the plan immediately upon trigger avoids schedule slippage on the critical path, as the alternative supplier should have been pre-qualified and ready to step in. This aligns with the PMBOK Guide's 'Implement Risk Responses' process, which emphasizes executing planned responses without delay.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
People — Leading Projects — study guide chapter
Learn the concepts, then practise the questions
- →
People — Leading Projects practice questions
Targeted practice on this topic area only
- →
All PMP questions
892 questions across all exam domains
- →
Project Management Professional PMP study guide
Full concept coverage aligned to exam objectives
- →
PMP practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PMP practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
People — Leading Projects practice questions
Practise PMP questions linked to People — Leading Projects.
Process — Managing Technical Aspects practice questions
Practise PMP questions linked to Process — Managing Technical Aspects.
Business Environment — Strategy and Value practice questions
Practise PMP questions linked to Business Environment — Strategy and Value.
Business Environment: strategy and project benefits practice questions
Practise PMP questions linked to Business Environment: strategy and project benefits.
PMP fundamentals practice questions
Practise PMP questions linked to PMP fundamentals.
PMP scenario practice questions
Practise PMP questions linked to PMP scenario.
PMP troubleshooting practice questions
Practise PMP questions linked to PMP troubleshooting.
Practice this exam
Start a free PMP practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PMP question test?
People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Activate the contingency plan and engage the alternative supplier — D is correct because the risk was already identified, assessed as high-probability, and a contingency plan (alternative supplier) was documented in the risk register. When the risk occurs, the first action is to execute the pre-approved contingency plan, not to reanalyze or seek new approvals, as the plan was already vetted during risk planning.
What should I do if I get this PMP question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more ways this is tested on PMP
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. A key vendor informs you that they cannot deliver a critical component on time due to a raw material shortage. This component is on the critical path. The risk was identified and documented in the risk register. What should you do FIRST?
medium- A.Escalate the issue to the project sponsor
- ✓ B.Implement the contingency plan defined in the risk register
- C.Contact the vendor to negotiate a new delivery date
- D.Immediately look for an alternative vendor
Why B: Since the risk was already identified and documented in the risk register, the project team should have prepared a contingency plan for this specific scenario. The PMBOK Guide states that when a risk occurs, the first action is to implement the pre-defined contingency plan to minimize impact. This is a proactive, planned response rather than a reactive scramble, and it aligns with the 'Plan Risk Responses' and 'Implement Risk Responses' processes.
Keep practising
More PMP practice questions
- During a sprint review, the product owner rejects a completed user story because it does not meet the acceptance criteri…
- During a daily standup, a developer mentions she is blocked by a dependency from another team. The issue was not previou…
- A project manager is leading a digital transformation initiative. Midway through the project, a new regulation is introd…
- Your project is a large infrastructure build. You have completed the planning phase, but the sponsor has put pressure on…
- You are managing a software development project using a hybrid approach. During a sprint review, the product owner reque…
- Your agile project has been experiencing declining velocity over the last three sprints. During the retrospective, the t…
Last reviewed: Jun 24, 2026
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.