Question 720 of 892
Process — Managing Technical AspectshardMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are managing a hybrid project with both predictive and agile components. A key risk from the risk register materializes: a critical vendor may go bankrupt, threatening delivery of a hardware component needed for the predictive phase. The risk response plan includes 'mitigate by identifying alternative vendors.' However, the only alternative vendor quotes a price that would exceed the project cost baseline by 10%. What should you do NEXT?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Initiate a change request to increase the cost baseline, documenting the risk response and vendor selection

When a risk response (mitigate by identifying alternative vendors) is executed and the chosen response causes a cost overrun, the correct next step is to initiate a change request to formally update the cost baseline. This aligns with the PMBOK Guide's change control process, ensuring the project's budget reflects the approved risk response and maintains traceability. Option B is correct because it follows the formal change management process required for any deviation from the cost baseline.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Proceed with the alternative vendor and inform the sponsor of the cost overrun after the fact

    Why it's wrong here

    Proceeding without change control violates the project management plan.

  • Initiate a change request to increase the cost baseline, documenting the risk response and vendor selection

    Why this is correct

    Since the response exceeds the baseline, formal change control is required.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Accept the risk and hope the vendor recovers, avoiding the cost increase

    Why it's wrong here

    Acceptance is a valid response but not when a proactive response was planned and feasible.

  • Escalate to the sponsor for a decision on whether to cancel the project

    Why it's wrong here

    Escalation to cancel is premature; a change request is the appropriate next step.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates may think the risk response plan authorizes immediate action without formal change control, but the PMP exam emphasizes that any change to the cost baseline requires a documented change request, even when executing a pre-planned risk response.

Detailed technical explanation

How to think about this question

In hybrid projects, the cost baseline is a formal component of the project management plan, and any change to it must go through the integrated change control process (PMBOK Guide, Section 4.6). The risk response plan's 'mitigate' strategy is executed by selecting the alternative vendor, but the resulting cost increase triggers a change request to update the cost baseline, not an automatic acceptance of the overrun. This ensures that the project's performance measurement baseline remains accurate and that stakeholders are formally informed of the financial impact.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Initiate a change request to increase the cost baseline, documenting the risk response and vendor selection — When a risk response (mitigate by identifying alternative vendors) is executed and the chosen response causes a cost overrun, the correct next step is to initiate a change request to formally update the cost baseline. This aligns with the PMBOK Guide's change control process, ensuring the project's budget reflects the approved risk response and maintains traceability. Option B is correct because it follows the formal change management process required for any deviation from the cost baseline.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.