Question 759 of 892
People — Leading ProjectseasyMultiple SelectObjective-mapped

First Step in the Formal Change Control Process

This PMP practice question tests your understanding of people — leading projects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

You are managing a project where a key stakeholder requests a scope change that would add significant value but also increase risk and cost. Which TWO actions should you take FIRST?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Document the change request and submit it through the change control process

Option B is correct because the PMBOK Guide requires that all scope changes be formally documented and submitted through the change control process, regardless of perceived value. This ensures traceability, stakeholder alignment, and proper evaluation before any action is taken. Option C is correct because analyzing the impact on scope, schedule, cost, and risk is a mandatory step within the integrated change control process to inform the decision-making body (e.g., CCB).

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Reject the change because it introduces additional risk

    Why it's wrong here

    Rejecting without analysis is not appropriate; the change may be beneficial after mitigation.

  • Document the change request and submit it through the change control process

    Why this is correct

    Formal documentation and submission are required steps.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Analyze the impact of the change on scope, schedule, cost, and risk

    Why this is correct

    Assessing impact is necessary before making a decision.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Accept the change because it adds value to the project

    Why it's wrong here

    Accepting without assessing impact bypasses change control and due diligence.

  • Update the project baseline to include the new scope

    Why it's wrong here

    Baseline updates require change control approval first.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The PMP exam often tests the misconception that a change adding value should be immediately accepted or rejected based on risk alone, when the correct first step is always to document and analyze through the formal change control process.

Detailed technical explanation

How to think about this question

In the PMBOK Guide's integrated change control process, the sequence is: 1) document the change request, 2) perform impact analysis (scope, schedule, cost, risk, quality), 3) submit to the CCB for approval or rejection, and 4) if approved, update the baseline and implement. A common real-world scenario is a stakeholder requesting a feature that adds business value but introduces technical debt; the project manager must first log the request and analyze trade-offs before any decision. The change log and change request form are the official artifacts that ensure auditability and prevent scope creep.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Document the change request and submit it through the change control process — Option B is correct because the PMBOK Guide requires that all scope changes be formally documented and submitted through the change control process, regardless of perceived value. This ensures traceability, stakeholder alignment, and proper evaluation before any action is taken. Option C is correct because analyzing the impact on scope, schedule, cost, and risk is a mandatory step within the integrated change control process to inform the decision-making body (e.g., CCB).

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During a project status meeting, a stakeholder requests a change that would improve the product but significantly impact the critical path. The project manager has not yet evaluated the change. What should the project manager do?

medium
  • A.Document the change request, assess the impact, and submit it to the change control board for approval
  • B.Accept the change to satisfy the stakeholder and update the project plan immediately
  • C.Reject the change because it impacts the critical path and would delay the project
  • D.Inform the stakeholder that the change will be considered after the current phase is complete

Why A: The correct answer is A because the PMBOK Guide mandates that all change requests must be formally documented and assessed for impact on constraints like the critical path before any decision is made. Submitting the evaluated change to the Change Control Board (CCB) ensures proper governance and prevents unauthorized scope creep, even if the stakeholder is influential.

Variation 2. During a sprint review, the product owner requests a significant change to a feature that was just completed. The change would improve user experience but would require reworking two sprints' worth of work. The project is already behind schedule. What should the project manager do first?

medium
  • A.Agree to the change since it improves user experience and ask the team to start rework
  • B.Document the change request and assess its impact on the project constraints before submitting for approval
  • C.Reject the change because the project is already behind schedule
  • D.Add the change to the product backlog for a future release without adjusting the current sprint

Why B: Option B is correct because the project manager must first follow the formal change control process by documenting the change request and assessing its impact on the triple constraints (scope, schedule, cost) before any approval or rejection. This aligns with the PMBOK Guide's Integrated Change Control process, which ensures that changes are evaluated systematically to avoid uncontrolled scope creep, especially when the project is already behind schedule.

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.