Question 786 of 892
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

Evaluating Impact of Vendor Delay on Critical Path

This PMP practice question tests your understanding of people — leading projects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A key vendor has notified you that they cannot deliver a critical component on time due to a raw material shortage. This component is on the project's critical path. What should you do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Evaluate the impact on the project schedule and identify possible alternatives, such as sourcing from another vendor

Option D is correct because the first step in any project management issue is to analyze the impact and explore alternatives before taking action. Since the component is on the critical path, any delay directly affects the project finish date, so you must evaluate schedule impact and identify options like sourcing from another vendor to mitigate the risk.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Initiate legal proceedings against the vendor for breach of contract

    Why it's wrong here

    Legal action is a last resort and may delay the project further.

  • Crash the schedule by adding resources to other tasks to compensate for the delay

    Why it's wrong here

    Crashing should be considered after understanding the full impact and exploring all options.

  • Immediately escalate the issue to the project sponsor

    Why it's wrong here

    Escalation is appropriate after the PM has assessed the situation and determined that sponsor involvement is needed.

  • Evaluate the impact on the project schedule and identify possible alternatives, such as sourcing from another vendor

    Why this is correct

    Assessing impact and exploring alternatives is the proactive first step in managing vendor issues.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often jump to escalation (Option C) or aggressive schedule compression (Option B) without first performing the required impact analysis, which is the foundational step in the PMI problem-solving framework.

Trap categories for this question

  • Scenario analysis trap

    Escalation is appropriate after the PM has assessed the situation and determined that sponsor involvement is needed.

Detailed technical explanation

How to think about this question

In project schedule management, the critical path determines the shortest possible project duration; any delay on a critical path activity directly extends the project finish date. The first step in risk response is to perform a schedule impact analysis using techniques like critical path method (CPM) calculations to quantify the delay, then evaluate alternatives such as fast-tracking, crashing the specific delayed activity, or sourcing from alternative vendors. This aligns with the PMBOK Guide's 'Plan Risk Responses' and 'Monitor and Control Project Work' processes, emphasizing analysis before action.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Evaluate the impact on the project schedule and identify possible alternatives, such as sourcing from another vendor — Option D is correct because the first step in any project management issue is to analyze the impact and explore alternatives before taking action. Since the component is on the critical path, any delay directly affects the project finish date, so you must evaluate schedule impact and identify options like sourcing from another vendor to mitigate the risk.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.