Question 456 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Your project is halfway through its schedule, and you are performing a variance analysis. You find that the cost performance index (CPI) is 0.85 and the schedule performance index (SPI) is 1.1. What is the MOST likely cause of this situation?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "most likely"

    Why it matters: Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The team is working overtime to meet deadlines, resulting in higher labor costs

A CPI of 0.85 indicates that for every dollar spent, only $0.85 of earned value is being delivered, meaning the project is over budget. An SPI of 1.1 indicates the project is ahead of schedule (10% more work completed than planned). The most likely cause is that the team is working overtime to achieve the schedule gains, which increases labor costs (e.g., overtime pay rates) without a proportional increase in output, driving the cost overrun.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Scope has been reduced without corresponding cost reduction

    Why it's wrong here

    Scope reduction would likely improve CPI and SPI, not this pattern.

  • There is a calculation error in the earned value data

    Why it's wrong here

    Assuming error without evidence is not the most likely cause.

  • The team is working overtime to meet deadlines, resulting in higher labor costs

    Why this is correct

    Overtime can accelerate schedule but increases cost, explaining CPI <1 and SPI >1.

    Clue confirmation

    The clue word "most likely" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • The project is under budget and ahead of schedule

    Why it's wrong here

    CPI <1 indicates over budget, not under budget.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates see SPI > 1.0 and CPI < 1.0 and incorrectly assume a data error, rather than recognizing the realistic project management trade-off of overtime causing cost overruns while accelerating schedule.

Detailed technical explanation

How to think about this question

In earned value management (EVM), CPI = EV/AC and SPI = EV/PV. Overtime directly increases AC (actual cost) due to premium pay rates (e.g., 1.5x or 2x base rate), while EV (value of work performed) may increase linearly with extra hours but at a lower efficiency due to fatigue, resulting in CPI < 1.0. The SPI > 1.0 confirms the schedule gain from the extra hours. This scenario is a classic 'crashing' trade-off where cost increases to compress the schedule.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: The team is working overtime to meet deadlines, resulting in higher labor costs — A CPI of 0.85 indicates that for every dollar spent, only $0.85 of earned value is being delivered, meaning the project is over budget. An SPI of 1.1 indicates the project is ahead of schedule (10% more work completed than planned). The most likely cause is that the team is working overtime to achieve the schedule gains, which increases labor costs (e.g., overtime pay rates) without a proportional increase in output, driving the cost overrun.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "most likely". Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jul 4, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.