Question 144 of 892
People — Leading ProjectsmediumMultiple ChoiceObjective-mapped

What to Do First When a Critical Path Component is Delayed: Analyze Impact and Explore Mitigation

This PMP practice question tests your understanding of people — leading projects. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A key vendor informs you that they will be unable to deliver a critical component on time due to a production issue. This component is on the critical path. What should the project manager do FIRST?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analyze the impact on the project schedule and explore mitigation options such as fast-tracking or alternate suppliers.

Option C is correct because the immediate priority when a critical path component is delayed is to analyze the schedule impact and identify mitigation options (e.g., fast-tracking, crashing, or alternative suppliers) before escalating or taking contractual action. This aligns with the PMBOK Guide's iterative risk response process, where the project manager must first assess the situation and determine feasible corrective actions to minimize schedule variance.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • File a claim against the vendor for breach of contract.

    Why it's wrong here

    Legal action is a last resort; first attempt to resolve collaboratively.

  • Update the risk register and inform the sponsor about the delay.

    Why it's wrong here

    Informing is good, but the PM should also analyze impact and explore alternatives.

  • Analyze the impact on the project schedule and explore mitigation options such as fast-tracking or alternate suppliers.

    Why this is correct

    This is the recommended proactive response: analyze, then act.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Immediately find a new vendor to deliver the component.

    Why it's wrong here

    Without assessing impact, this may not be the best solution; also, contract terms may apply.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse 'immediate escalation' (updating the risk register or informing the sponsor) with the correct first step of 'analyze and mitigate' — PMI expects the project manager to take proactive, analytical action before communicating upward or taking legal steps.

Detailed technical explanation

How to think about this question

In critical path management, any delay on a critical path activity directly extends the project finish date unless schedule compression techniques (fast-tracking or crashing) are applied. Fast-tracking involves performing activities in parallel that were originally sequential, which increases risk of rework, while crashing adds resources to reduce duration at increased cost. The project manager must first perform a schedule impact analysis using the project's network diagram and critical path method (CPM) to quantify the delay and then evaluate trade-offs between cost, risk, and schedule before deciding on a response.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

People — Leading Projects — This question tests People — Leading Projects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Analyze the impact on the project schedule and explore mitigation options such as fast-tracking or alternate suppliers. — Option C is correct because the immediate priority when a critical path component is delayed is to analyze the schedule impact and identify mitigation options (e.g., fast-tracking, crashing, or alternative suppliers) before escalating or taking contractual action. This aligns with the PMBOK Guide's iterative risk response process, where the project manager must first assess the situation and determine feasible corrective actions to minimize schedule variance.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More PMP practice questions

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.